Loading...
HomeMy WebLinkAbout06 APPROVE AMENDMENT TO CSA WITH TETRA TECH~" Agenda Item _~,_ AGENDA REPORT Reviewed: City Manager Finance Director MEETING DATE: JULY 5, 2011 TO: WILLIAM A. HUSTON, INTERIM CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER SUBJECT: APPROVE AMENDMENT TO CONSULTANT SERVICES AGREEMENT WITH TETRA TECH FOR THE RAWLINGS RESERVOIR REPLACEMENT PROJECT CIP NO. 60136 SUMMARY Approval of Amendment No. 9 to the Consultant Services Agreement with Tetra Tech will provide for additional design services for the Rawlings Reservoir Replacement Project CIP No. 60136. RECOMMENDATION It is recommended that the City Council approve Amendment No. 9 to the Consulting Services Agreement with Tetra Tech for the Rawlings Reservoir Replacement Project CIP 60136 and authorize the Mayor and the City Clerk to execute the amendment on behalf of the City. FISCAL IMPACT The scope of services associated with the contract amendment is for a not to exceed amount of $184,400. Sufficient funds are budgeted and appropriated in the Rawlings Reservoir Replacement Project CIP No. 60136. DISCUSSION In 1996, an engineering study identified several structural deficiencies in the existing 3.82 million gallon (MG) Rawlings Reservoir. The reservoir was taken out of service in November 2004. The Rawlings Reservoir Replacement project consists of demolishing the existing reservoir and replacing it with two (2) circular pre-stressed concrete reservoirs of 3.0 MG each. During the on-going constructability review, it was deemed appropriate to separate the overall project into two phases: Phase I -Demolition and Phase II -Reservoir Construction. Phasing the project in this way enables the City to perform additional geotechnical investigations after the reservoir is demolished. This will greatly reduce the geotechnical unknowns under the existing reservoir and thus avoid potentially costly delays to the future reservoir construction. Amendment No. 9 to Tetra Tech's Consultant Services Agreement includes the design services to complete Phase II -Reservoir Construction plans and specifications incorporating the results of the additional geotechnical investigations, and additional design to grade back the adjacent property on the west in lieu of the more expensive tie-back shoring design. This amendment also includes Construction Phase Support Services during both Phase I and Phase II, including but not limited to shop drawing review, responding to the RFI's, minor plan changes, change order support, and record drawings. Rawlings Reservoir Replacement Project CIP 60136 July 5, 2011 Page 2 Tetra Tech is the design engineer for the Rawlings Reservoir Replacement Project. Based on the additional scope of services outlined above, Tetra Tech submitted proposals dated February 21, 2011 and April 15, 2011 in the total amount of $184,400. Staff has reviewed Tetra Tech's proposals and found them to be fair and reasonable based upon the amount of additional design services required. Staff recommends that the City Council approve Amendment No. 9 to the Consulting Services Agreement with Tetra Tech for the Rawlings Reservoir Replacement Project CIP No. 60136. The City Attorney has reviewed the Amendment and has approved it as to form. Stack, P.E. Public Works/City Engineer Attachment: Amendment to Agreement Location Map S:\City Council Items\2011 Council ItemsWmend CSA with Tetra Tech -Rawlings Reservoir Replacement CIP 60136.docx AMENDMENT NO. 9 TO CONSULTANT SERVICES AGREEMENT FOR ADDITIONAL ENGINEERING DESIGN SERVICES FOR RAWLINGS RESERVOIR REPAIR AND REPLACEMENT PROJECT THIS AMENDMENT NO. 9 TO CONSULTANT SERVICES AGREEMENT ("Amendment No. 9") is made and entered into this day of 2011 by and between the CITY OF TUSTIN, a municipal corporation hereinafter referred to as "City" and Tetra Tech, Inc. a California corporation, hereinafter referred to as "Consultant". REC_ WHEREAS, City and Consultant entered into a Consultant Services Agreement as of November 15, 2004 (the "Agreement") for design and engineering services for the Rawlings Reservoir Repair and Replacement Project; and WHEREAS, City and Consultant desire to amend Section 1 and Section 4 of the Original Agreement to provide additional engineering design services for the Rawlings Reservoir Repair and Replacement Project. NOW, THEREFORE in consideration of the mutual promises, covenants, and conditions contained herein, and upon the terms and conditions hereinafter set forth, the parties agree as follows: AGREEMENT Section 1: Section 1 of the Agreement is amended Section 1 of the Agreement is hereby amended in its entirety to read as follows. Consultant shall perform all work necessary to complete in a manner satisfactory to City, the services set forth in the City's Consultant Services Agreement dated November 15, 2004, a copy of which is attached hereto marked as Exhibit "A" and is by this reference incorporated into this Agreement. Consultant shall also perform all services set forth in Exhibit "A" to the Original Agreement and as set forth in Amendment Nos. 1 through 8. Consultant shall also perform all services as set forth in Exhibit "B" to this Amendment No. 9 attached hereto and incorporated into this Agreement by reference. Section 2: Section 4 of the Agreement is amended Section 4 of the Agreement is hereby amended in its entirety to read as follows: Section 4: Compensation A. The compensation to be paid under the Original Agreement shall be as set forth in Exhibit "A" and shall not exceed a total cost of $277,000.00. B. The compensation to be paid under Amendment Nos. 1-8 shall not exceed a total cost of $348,879.00. C. The compensation to be paid under Amendment No. 9 as set forth in Consultant's proposals dated February 21, 2011 and April 15, 2011 (Exhibit "B") shall not exceed a total cost of $184,400.00. D. Consultant shall submit detailed monthly invoices, based upon the actual work performed, accompanied by backup documentation as requested by the City. E. Progress payments for work completed shall be paid by the City as the work progresses, within thirty (30) days of receipt of Consultant's invoice with appropriate backup documentation. F. Consultant shall provide City with a brief monthly synopsis of all tasks performed and the fees accrued thereon in complete and sufficient detail to fully apprise City of work progress. Section 3: Except as expressly amended herein, all other provisions of the Original Agreement remain in full force and effect. Section 4: Miscellaneous A. If any term, covenant, condition, or provision of this Amendment No. 9 or the application thereof to any person or circumstance, shall to any extent be held by a court of competent jurisdiction to be invalid, void, or unenforceable, the remainder of this Amendment No. 9, or the application thereof to any person or circumstance, shall remain in full force and effect and shall in no way be affected, impaired, or invalidated thereby. B. This Amendment No. 9 shall be governed and construed in accordance with the laws of the State of California. In the event of any legal action to enforce or interpret this Amendment No. 9, the sole and exclusive venue shall be a court of competent jurisdiction located in Orange County, California, and the parties hereto agree to and do hereby submit to the jurisdiction of such court, notwithstanding Code of Civil Procedure Section 394. C. Each signatory to this Amendment No. 9 hereby warrants and represents that each has been authorized to enter into this Amendment No. 9 on behalf of the entity for whom they sign. (SIGNATURE PAGE TO FOLLOW] IN WITNESS WHEREOF, this Amendment No. 9 was executed by the parties on the day and year written above. "CITY" CITY OF TUSTIN Jerry Amante, Mayor ATTEST: (SEAL) Pamela Stoker, City Clerk APPROVED AS FORM: Doug Holland, City A rney "CONSULTANT" Tetra Tech, Inc. ~,. Steve Tedesco, Senior Vice President Engineering and Architecture Services EXHIBIT "A" CONSULTANT SERVICES AGREEMENT THIS AGREEMENT FOR CONSULTANT SERVICES, is made and entered into this I~_ day of _ ~e rrw,~r 2pp4, by and between the CITY OF TUSTIN, a municipal corporation, hereinafter referred to as "City", and Tetra Tech inc., hereinafter referred to as "Consultant'. REC- WHEREAS, City requires the services of a consultant to famish the necessary engineering services for the Rawlings Reservoir Repair and Replacement (CIP No. 6136) hereinafter referred to as "Project"; and . WHEREAS, Consultant has submitted to the City a proposal dated October 6, 2004, a copy of which is attached hereto marked as Exhibit "A" and is by this reference incorporated into this Agreement; and WHEREAS, Consultant is qualified to provide the necessary services for the Project and desires to provide said services; and WHEREAS, City desires to retain the services of Consultant for said Project. NOW, THEREFORE, for the consideration and upon the terms and conditions hereinafter set forth, the parties agree as follows: AGREEMENT Section 1: Scooa of Consultant's Services Consultant shall perform all work necessary to complete in a manner satisfactory to City, the services set forth in Exhibit "A". Section 2: Order of Precedence In the event of a conflict between or among any of the documents comprising this Agreement, the following order of precedence shall govern the provision in question: 1. This Agreement 2. Consultant's Proposal (Exhibit "A'~ Section 3: Time for Com letion The time for completion of the work to be pertormed by Consultant is an essential condition of this Agreement. Consultant shall prosecute regularly and diligently the work of this Agreement according to reasonable schedules established by the City for various items described and as outlined within Consultant's proposal. Consultant shall ~ 821•t Publk: Works ca uzoo4 not be accountable for delays in the progress of its work caused by any condition beyond its control and without the fault or negligence of Consultant. Section 4: Compensation A. The compensation to be paid under this Agreement shall be as set forth in Exhibit "A", not to exceed a total cost of $277,000.00 B. Consultant shall submit detailed invoices, based upon the actual work pertom~ed accompanied by backup documentation as requested by the City. C. Progress payments for work completed shall be paid by City as the work progresses, within thirty (30) days of the date of Consultant's invoice. D. Consultant shall provide City with a monthly itemization of all work performed, and the fees accrued thereon, in complete and sufficient detail to fully apprise City thereof Section 3: indeuendent Contractor Consultant's relationship to City in the performance of this Agreement is that of an independent contractor. Consultant's personnel performing services under this Agreement shat! at all times be under Consultant's exclusive direction and control and shall be employees of Consultant and not employees of City. Consultant shall pay all wages, salaries and other amounts due its employees in connection with this Agreement and shall be responsible for all reports and obligations respecting them, such as social security, income tax withholding, unemployment compensation, workers' compensation and similar matters. Section 6: Indemnification Consultant agrees to defend, indemnify, and hold City, its officers, agents, employees, successors and assigns harmless from any loss, damage, injury, sickness, death, or other claim made by any person and from all costs, expenses and charges including attorney's fees caused by or arising out of Consultant's, its officers', agents', subcontractors`, or employees' negligent acts, negligent errors, or negligent omissions or willful misconduct, or conduct for which the law imposes strict liability on Consultant in the performance or failure to perform this Agreement. Section 7: Insurance A. Consultant shall maintain in full force and effect during the term of these Agreement policies of commercial general liability and automobile liability insurance (each of which shall include property damage and bodily injury) and each with limits of at least $1,000,000 combined single limit coverage per occurrence. ~~asz~.~ Public Works 2 CA 22004 B. Consultant shall maintain in full force and effect during the tens of this Agreement a policy of professional liability insurance coverage with limits of at least $1,000,000 combined single limit coverage per claim or per occurrence. If Consultant provides claims made professional liability insurance, Consultant shall also agree in writing either (1) to purchase tail insurance in the amount required by this Agreement or to cover claims made within five {5) years of the completion of Consultant's service under this Agreement, or (2} to maintain professional liability insurance coverage with the same carrier in the amount required by this Agreement for at least five (5) years after completion of Consultant's services under this Agreement. Consultant shall also provide evidence to the City of the purchase of the required tail insurance or continuation of the professional liability policy by executing the attached Letter Agreement on Consultant's letterhead. C. Consultant shall cant' and pay for such workers' compensation insurance as is required fully protect Consultant and its employees under Califomia Worker's Compensation Insurance Law. The insurance company shall agree to waive all rights of subrogation against the City for losses paid under the policy, which losses arose from the work performed by the named insured. D. Other applicable insurance requirements are: (1) Name the City, its officials and employees as an additional insured on the commercial, general and automobile policies. (2) The insurance shall be issued by a company authorized by the Insurance Department of the State of Califomia and rated A, VII or better (if an admitted carrier) or A-, X (if offered, by a surplus line broker), by the latest edition of Best's Key Rating Guide, except that the City will accept workers' compensation insurance rated B-VIII or better or from the State Compensation Fund. (3) The Insurance shall not be cancelled, except after thirty (30) days written prior notice to the City; and (4) The commercial general and automobile liability insurance shall each be primary as respects the City, and any other insurance maintained by the City shall be in excess of this insurance and not contribute to it. E. Upon execution of this Agreement, Consultant shall provide to City certificates of insurance showing the names of the insurers and the amounts of coverage and insurer endorsements evidencing the required insurance provisions. Insurer endorsements (or a copy of the policy binder if applicable} shall be provided as evidence of meeting the requirements of Subsections (1)(3) and (4) of Section 7D above and the waiver of subrogation requirement in Section C above. If self- insured for worker's compensation, Consultant shall submit to City a copy of its certification of self-insurance issued by the Department of Industrial Relations. Section 8: Termination of Agreement A. City and Consultant shall each have the right to terminate any or all of the services covered by this Agreement at any time for any reason by giving ten (14) business day written advance notice to -the other party. 174821 •'I 3 PubIIC Worka CA 111004 8. Upon termination of this Agreement, Consultant shall be paid for services rendered by the effective date of the termination. C. Upon termination of this Agreement or completion of the Project, all documents relating to the Project shall become the sole property of City. Should City terminate this Agreement pursuant to subparagraph A. of this Section, Consultant shall, within ten (10) business days of receipt of notice of termination, provide City with all documents within Consultant's possession relating to this Agreement and the Project, including but not limited to all completed documents and all drafts of uncompleted documents. Section 9• Notices Any notice allowed or required to be given shall be effective upon personal delivery thereof, or upon depositing thereof in the United States Postal Service, certified mail, return receipt requested, postage prepaid, addressed as follows: To City: City of Tustin Attn.: Tim D. Serlet, Director of Public Worics/City Engineer 300 Centennial Way Tustin, CA 92780 To Consultant: Tetra Tech Inc. Attn.: Steve Tedesco 16241 Laguna Canyon Road Suite 200 Irvine, CA 92618 Section 10: Miscellaneous Provisions A. Consultant shall proceed immediately and diligently to perform the services provided for in this Agreement upon receipt of notice from City to proceed therewith. B. No part of this Agreement may be assigned by Consultant without the prior written approval of City. C. This Agreement shat! extend to and be binding upon and inure to the benefit of heirs, executors, administrators, successors and assigns of the respective parties hereto. D. Consultant shall perform all services' required under this Agreement using that degree of care and skill ordinarily exercised under similar conditions in similar localities, and shall be responsible for all errors and omissions for services performed by Consultant under the terms of this Agreement. ~~ z~.~ Public Works 4 CA 22004 E. Consultant certifies that there shall be no discrimination against any employee who is employed in the work covered by this Agreement, or against any application far such employment, because of race, religion, color, sex or national origin including but not limited to, the following: employment, upgrading, demotion or transfer, recruitment, or recruitment adverfising, lay-off or termination, rate of pay or other forms of compensation, and selection for training, including apprenticeship. F. This Agreement shall be interpreted in accordance with California Law. The parties agree that the Orange County Superior Court is the exclusive venue for any lawsuits by either party regarding this Agreement 1N WITNESS WHEREOF, this Agreement was executed by the parties on the day and year first above written. ATTEST: ~~~ ~~~ Pamela Stoker, City Cf rk APPRC~/~D AS TO FORM: Gity Attorney "CI-TY° CITY OF T1~5TIN By~~tr v Mayor of he Ci o Tustin "CONSULTANT" Tetra Tech I By Title: Steve Tedesco, Division Senior Vice President ~ 4821.1 5 Public works CA 2/2004 TETRA TECH EXHIBIT "B" Febntazy 2 t, 201 I Mr. Kunal Mittal, P.E. City of Tustin 3()D Centennial Way Tustin, CA 92780 Reference: Rawlings Reservoir Repair and Reptacernent Project (CIP No. 6136) Proposal for Additional Engineering Services -Phase 2 (Amendment No. 9) Dear Mr. Mittal: Tetra Tech has been providing professional engineering services for this project since November 2004. Tetra Tech has completed the final plans and specifications and has submitted them to the City of Tustin. Tetra Tech has completed all of our scope of services per our existing Consulting Services Agreement (including all of our approved Amendments Nos. I through 7). As of January 27`x, 201 1, the City approved Amendment No. 8 for $19,900 to perform engineering services for the Phase Demolition of the existing Rawlings Reservoir. Tetra Tech is pleased to provide the following proposal for additional engineering services for the Rawlings Reservoir Project. In order to obtain additional geotechnical information for soils underlying the existing reservoir that can be used to assist the Contractors in bidding the reservoir construction project, the City has decided to separate the project into two phases: Demolition Phase (Phase i); and Reservoir Construction Phase (Phase 2). The City has previously authorized Tetra Tech to prepaze the Phase 1 (Demolition Phase) Plans and Specifications. By this correspondence, we are requesting approval of the additional services to prepare the Phase 2 (Reservoir Construction Phase) Plans and Specifications and the corresponding increase in our approved budget. Phasing Overview The intent of the additional services is to revise the plans and specifications to allow the City to bid the Demolition Phase of the Work prior to the actual Reservoir Construction Phase. Once the demolition work has been completed, additional geotechnical work can be performed. This additional geotechnical work will provide soils data relative to subsurface conditions that are underlying the existing reservoir that could not be previously obtained. This additional data will be used by the Contractors bidding the Reservoir Construction Phase as part of their shoring system design. This additional geotechnical data will reduce potential claims due to unknown subsurface conditions and will assist the Contractor in designing the shoring as well as constructing the proposed reservoirs. Assumptions The following are our assumptions in preparing this proposal: 1. Submit 90% and 100% design submittals of the Phase 2 work. 2. At each submittal, submit three sets of full size plans, reduced plans and project specifications. Tetra Terh, Inc. 17885 Von Karman. Suite 500, Irvine. CA 92614-6213 Tca 349.809-5000 F>:r.949.8O9.50t07 ~w~.vw.tetratech.com O TETRA TECH Mr. Kunal Mittal, P.E. February 21, 201 I Page 2 3. Final submittal will include reproducible signed construction drawings (mylar) and unbound signed specifications. ~. Front ends will be prepared by the City and Tetra Tech will review and comment. 5. City will provide all reproduction for bidding and distribute all addenda. The following is our preliminary schedule: • Submit 90% design submittal for Phase 2 three (3) weeks after receiving the additional geotechnical findings; • Allow two (2) weeks for the City and CM to review and provide comments; • We will submit to the County of Orange for grading permit once we receive the City and CM comments and make any major changes (assume a minimum of six week review period); • Submit 100% design submittal for Phase 2 three (3) weeks after receiving the City/CM comments and two (2) weeks after receiving the County of Orange review comments; • Allow two (2) weeks for the City and CM to review and provide comments; and • Submit final signed plans and specifications two (2) weeks after receiving the City/CM comments. Scone of Work Task 1: Project Management Tetra Tech will conduct Project Management activities to ensure adherence to schedule and budget, including frequent communication between the City, and the City's Construction Manager. For this proposal, we have assumed the project management activities will be required for up to Five (5) months. This should account for modifying and bidding the Construction Phase (Phase 2) plans and specifications based on the additional geotechnical findings. Tetra Tech will prepare bi-weekly a-mail status reports and monthly invoice back-up spreadsheets. Phase 2 (Reservoir Construction Phase) The previously submitted 100% plans and specifications will be revised to remove the portion of work included within the Phase 1 (Demolition Phase) work as well as the necessary revisions as the result of the additional geotechnical investigation findings and constructability review comments provided by the City's Construction Manager. We have assumed that these revisions will be minor in nature and will not require the preparation of additional sheets or details except as noted below. We have assumed that two additional sheets will be required to show the new cut slope and buttress grading and sections that have been discussed with the City, the Construction Manager and with Leighton. We have assumed that the conceptual design will be provided by the City's Construction Manager with additional information provided by Leighton Consulting, Inc. We have included the time and effort to submit these additional sheets to the County of Orange in order to obtain a grading permit. O TETRA TECH Mr. Kunal Mittal, P.E. February 2l, 2011 Page 3 Task 2: Preparation of Plans Revise the sheets to reflect the worked performed as part of the Demolition Phase I Plan Set, remove any references to the demolition work performed and provide notes for the remaining demolition work, and include the additional grading plan and section for the west side of the property. Revise the notes on the plans to account for the additional geotechnical information. Make minor changes to the plans based on the constructability review performed by the Construction Manager. Revise the sections and site plan to represent the final site plan prepared for the demolition phase of the work. Task 3: Preparation of Specifications Prepare new bid form, revise Summary of Work (Section 01010) and Bid Form, Measurement and Payment (Section 01150). Make revisions to the Technical Specifications as necessary due the additional geotechnical findings and comments obtained from the constructability review performed by the Construction Manager as well as the County of Orange Grading Permit conditions. Insert necessary Technical Specifications with only minor editing. Prepare engineer's construction cost estimate and preliminary construction schedule working with the City's Construction Manager. Task 4: Meetings and Processing of Plans We have assumed that the following meetings with the City and the City's Construction Manager will occur during this phase of the design work: discuss the additional geotechnical investigation work recommended; discuss additional geotechnical investigation findings and constructability review comments provided by Construction Manager; and 90%a design review meeting. Tetra Tech will process the plans and specifications with the City for the 90% and 100% design submittals. Task S: County of Orange Grading Permit Processing Tetra Tech will submit the additional grading plans to the County of Orange for a Grading Permit. Tetra Tech will meet with the County of Orange (we have assumed only one meeting) and make the revisions required as part of the grading permit review process. We have assumed that Leighton and the City's Construction Manager will provide the additional information and soils data requested by the County of Orange. We have also assumed that a separate plan set will not be required by the County. The City of Tustin will pay all permit application and review process fees. Task 6: Prepare Addendum to WQ~1lP Tetra Tech will prepare an addendum to the WQMP to include the proposed grading revisions and the phasing of the construction activities. Task 7: Bid Phase Services Tetra Tech will attend the Pre-Bid Meeting with the City/City's Construction Manager and prospective bidders to assist the City in answering any ques[ions regarding the reservoir construction plans. O TETRA TECH Mr. Kunal Mittal, P.E. February 21, 201 Page 4 We will provide assistance during the bidding period, answering questions from prospective bidders and preparing any necessary contract addendums. We have assumed that two (2) addendums may be necessary. Summary Tetra Tech is requesting the following increase in our budget authorization to compensate us for these additional services. Item Na, . Description of Additional Items o . Word; .f Requsstsd'Budgs~ . 1 Project Mana ement $ 2 900 2 Phase 2 Plans $ 22,200 3 Phase 2 S cifications $ ~ 400 4 Phase 2 Meetin sand Processin Plans $ ~ 100 5 Count of Oran a Gradin Permit Processin $ 5,500 6 Pre are Addendum to W MP $ 4000 7 Phase 2 Bid Phase Services 3 900 Total $ 50,000 We have included herewith a summary of the person-hour estimate for the additional work and our 201 I Hourly Rate Schedule. The above requested budget is based on the 2011 Hourly Rate Schedule. The following is summary of our existing approved budget, including Amendment No. 8: • Original Agreement: $ 2'7'7,000 • Amendment No. 1: $ 166,519 • Amendment No. 2: $ 4,800 • Amendment No. 3: $ 20,600 • Amendment No. 4: $ 19.360 • Amendment No. 5: $ 25,390 • Amendment No. 6: $ 38,:00 • Amendment No. 7: $ 39,000 • Amendment No. 8: $ 19,900 Existing Approved Budget: $ 610,669 We are proposing to perform this additional work as Amendment No. 9 to our existing agreement for the Design of the Rawlings Reservoir Project. D TETRATECFf Mr. Kunal Mittal, P.E. February 21, 201 l Page 5 We are prepared to start work immediately upon your written authorization. We appreciate the opportunity to submit this proposal. [f you have any questions, please do not hesitate to call me at (949) 809-5156. Sincerely, yd C~Vrn (, , Tom Epperson, Vice President Engineering & Architecture Services TLE/te P:\P03291\0030\WonipioDrafts\extra for Phase 2.doc Attachments City of Tustin Rawlings Reservoir Repalr and Replacement Protect Proposal forAddttlonal Engineering Services • Phase 2 (Amendment No. 9) Fee Summary Fws Tank Deeulp5on Sr. Project MsAa9u Projaa Manger Project Erbnea Dseyn Engkrser CARD Wad Proca»or T~ Flours t,ya 3ut.COnirectas Rabmbunedse TOTALS 1 Project Management ' _Project Management (5 months) 4 2 0 0 0 0 6 E1,500 SO $1,500 ~. ~. Bi-week (10) /Month (5) status reports 2 4 0 0 0 0 8 E7,350 E50 $1,400 "; _'. __ _____.. Subtotal 8 8 0 0 0 0 12 32,850 S50 52,900 2 Phase 2 Plans Remove Demolition plansrnotes 1 6 12 12 30 0 61 E8,555 E45 $8,600 New Grading plan 1 2 6 10 16 0 35 $4,855 $45 $4,900 '. .New Sechon and Grading Notes ,.. 1 2 4 8 12 0 27 E3,795 345 E3,840 Minor COns[ructaMliry Changes 0 0 2 4 8 0 14 $1,800 _ $0 E7,80g 'Revise abating site plaNsecGane 1 2 2 8 10 0 21 E2975 E85 $3,060 ', Subtotal 4 12 28 40 78 0 1S8 321,950 5220 522,200 3 Phase2 Spxificatbns &dform,.Sechon 01010 and 01150_ .. __2_ .. ... 2 _._.._8 4 0 _._2 _._. 18 $2,930 E60 E2,990 ' Rev lions to Technical Specs 1 2 4 0 0 2 9 E1,495 ..... .... E25 E1,520 Mnor edit n9 of Technical Spew 0. _ 1 _...4. 0 0 2 7 E1.020 EO E1,020 Engineer's COSt EShmate i 2 4 4 0 0 11 E1,835 E35 E1,870 Subtotal 4 7 20 8 0 8 45 37,250 3120 57,400 4 Phase 2 Meetlrps arM Processing '. '.Meetings (3) 3 3 0 D 0 1 7 E7,515 E45 E1.560 ' '., Processing of plans and specs. 0 0 2 4 4 1 11 57,410 E1,130 $2,540 SuMOtal 7 3 2 4 4 2 78 52,925 57,173 54,100 E County a Orange Grading Permit Meetingwith County of Orange 2 3 0 0 0 1 6 E7,240 $60 E1,300 ', Permit Processing 2 5 8 4 4 1 24 E3,920 $280 E4,200 Subtotal 4 8 8 4 4 2 30 55,180 5340 53,500 8 Prepare Addendum to WQMP Prepare Addendum 0 2 6 8 4 1 21 $2,970 E2,970 Processing of WOMP _..__._ 0 0 2 2 2 1 7 $910 $120 E1,030 __ ___. __ subtotal 0 2 5 70 6 2 28 53,550 5720 54,000 7 Phase 2 Bid Phase Servbes Attend Pre-Bid Meeting 2 0 0 0 0 1 3 E640 E10 E650 Answer Queatlona/Prepare Addenda 4 4 4 4 D i 17 E3,150 1100 E3,250 ', SuMOtal 8 4 4 4 0 2 20 33790 5710 53,900 Total 27 42 88 70 90 74 8H =47,888 =2,788 180,000 P:Y+aa291~003011yar4proUalrsYUSYn phew 2 propoeal.bs TETEA TECN, INC. TETRATECN toll HOURLY CHARGE RATE AND F.~CPENSE REIMBURSEMENT SCHEDULE Professional engineering Intern/TechniciaNAssistant....$ 65.00 Project Administrator .................................$ 80.00 Designer/CAD Operator/Engineer I ...........$ 120.00 Engineer II and IWSenior Designer ..........$ 130.00 Biologist .....................................................$ 120.00 Planner ........................................................$ 120.00 Senior Engineer/Landscape Architect........$ 140.00 Project Engineer/Project Coordinator ........$ 160.00 Senior Planner ............................................$ 160.00 Senior Scientist ...........................................$ (60.00 Project Manager/Sr. Project Coordinator...$ 200.00 Senior Project Manager ..............................$ 275.00 Program Director/Project Director .............$ 275.00 Adr~u--- mstrative Administrative Clerk ..................................$ 65.00 Word Processor/Admin. Support ................$ 90,00 Graphic Designer ........................................$ 125.00 Reimbursable In-House Cos Photo Copies (B&W 8.5"xl t").......$ 0.15/Each Photo Copies (B&W I 1 "x 17")........ $ 0.40/Each Color Copies (up to 8.5"x 1 I ") ........ $ 2.00/Each Color Copies (to 1 I "x 17") .............. $ 3.001Each Computer Usage ..............................$ 2. LO/Hour Compact Discs ................................ $ f 0.00/Each Large Format Copies ...................... $ 0.40/S.F. Mileage ............................................ $0.55/Mile * *current IRS POV Mileage Rate subject to change Company Vehicles .......................... $8.00/Hour Reproduction, special photography, postage, delivery services, express mail, out-of--area telephone calls, printing and any other services performed by subcontractor, wilt be billed at cost plus 1 S%. NOTE: All rates are effective from January I , 201 I to December 31, 2011. There will be a negotiated increase in rates, 5% maximum per year, for contracts extending beyond December 31, 2011. P:\P03291\00301 WordproDrattslExhibitA-201 I .doc O TETRA TECH April l5, 201 Ntr. Kunal Mittal, P.E. City of Tustin 300 Centennial Way Tustin, CA 92780 Reference: Rawlings Reservoir Repair and Replacement Project (C1P No. 6136) Proposal for Construction Support Services Dear Mr. Mittal: Tetra Tech has been providing professional engineering services for this project since November 2004. Tetra Tech has completed the final plans and specifications and has submitted them to the City of Tustin. Tetra Tech has completed all of our scope of services per our existing Consulting Services Agreement (including all of our approved Amendments Nos. 1 through 7). As of January 27`h, 20l I, the City approved Amendment No. 8 for $19,900 to perform engineering services for the Phase 1 Demolition of the existing Rawlings Reservoir. Tetra Tech is waiting for approval of Amendment No. 9 for $50,000 for the Phase 2 Reservoir Construction Phase (proposal dated February 21, 201 l ). In order to obtain additional geotechnical data for soils underlying the existing reservoir, the City has decided to separate the project into two phases: Demolition Phase (Phase 1); and Reservoir Construction Phase (Phase 2). Tetra Tech is pleased to provide the following proposal to provide Construction Support Services for both Phase 1 and Phase 2 construction projects. The following proposal has been prepared based on the assumption that Butier Engineering, Inc. will be providing the Construction Management during the construction of both phases. Scone of Work Task 1: Project Management Tetra Tech will conduct Project Management activities to ensure adherence to schedule and budget, including frequent communication between the City, and the City's Construction Manager. For this proposal, we have assumed the project management activities will be required for up to thirty (30) months. This is based on the Phase 1 Demolition Construction starting in June/July and the Phase 2 Construction duration of 500 working days. Tetra Tech will prepare monthly a-mail status reports and monthly invoice back-up spreadsheets. Demolition Phase (Phase !) Task 2: Construction Prajeet Meetings Tetra Tech will attend the Pre-Construction Meeting, and have assumed that we may be requested to attend two other construction project meetings to answer questions or provide input. Therefore, for this proposal, we have assumed that Tetra Tech will be requested to attend three (3) meetings. We have assumed that the meeting agenda and minutes will be prepared by Butier Engineeering, Inc. ~'=~'~ TF3i h, (nc 17885 ~/an Karman. Suite 500. Irvire. CA 9261 4-62 1 3 -~:1 `?d3 869-5600 =,zx 949.869.50107 :v~+vw.tetratech.cam O TETRA TECH Mr. Kunal Mittal, P.E. April l5, 201 I Page 2 Task 3: .Shop Drawing Review Tetra Tech will review and process shop drawing submittals. It may be in the City's best interest to have Butler Engineering, [nc, review several of the non-engineering shop drawing submittals, as well as Leighton review the geotechnical submittals in lieu of Tetra Tech. Based on this assumption, we have envisioned the following shop drawing submittals and the corresponding reviewing party: • Schedule and Schedule of Values (Butier) • BMP/SWPPP Submittals (Butier) • Fiber Rolls/Visqueen and Erosion Control Plans (Butier) • Sequence of Demolition (Tetra Tech and Butier) • Abatement Plan (Butier and National Econ) • Dewatering Plan (Butier) • Sound Wall (Tetra Tech) • Grading Plan (Tetra Tech) • Fencing and Gate (Butier) Therefore, we have assumed that we may need to review about four (4) different shop drawing submittals. We have also assumed that each submittal will need to be reviewed only twice (the original submittal and one re-submittal). Tetra Tech will complete our review of each submittal within ten (10) working days of receiving the submittal. Tetra Tech will maintain a log for shop drawings. Task 4: Requests for Information (RFIs) Tetra Tech will respond to Contractor's "Request for Information" as requested by the City/Construction Manager. We have assumed that the majority of the RFIs will be reviewed and responded to by Butler. For this proposal, we have assumed approximately five (5) RFIs will require our response. Tetra Tech will provide a response to each RFI within twenty-four (24) hours. In addition, Tetra Tech will provide revised design details and clarifications sketches in response to the Contractor's RFI. We have assumed one (1) such RFI will be required. Tetra Tech will notify the City within twenty-four (24) hours of receiving these RFIs with the proposed schedule for providing the revised design details and sketches. Tetra Tech will maintain a fog for RFIs. Task S: ~Liinor Plan Changes Tetra Tech will prepare minor plan changes due to changes in the field conditions and/or at the request of the Contractor and/or Construction Manager. For this proposal, we have assumed twenty (20) hours f'or these minor plan revisions. Tetra Tech will maintain a log of plan revisions. O TETRA TECH Mr. Kunal Mittal, P.E. April I5, 20l 1 Page 3 Task 6: Claange Order Srepport Tetra Tech will provide support services in reviewing Change Order requests provided by the Contractor. This will include discussions with the Construction Manager. We have assumed that the majority of the change order review and evaluation will be performed by Butier and Tetra Tech will only provide engineering review support. Eor this proposal, we have assumed a total of one (I) Change Order request will require our review. Task 7: Record Drawings Tetra Tech will prepare record drawings based on Contractor's and Construction Manager's red-lines. Tetra Tech will submit both mylars and electronic files. We have assumed that Butier Engineering, Inc. will provide all coordination of services: survey, concrete/material testing, geotechnical inspection, abatement inspection, sewer discharge permit coordination, private property coordination, County of Orange coordination, etc. Reservoir Construction Phase (Phase 2) Task 8: Construction Project Meetings Tetra Tech will attend the Pre-Construction Meeting, and have assumed that we may be requested to attend a construction project meeting every other month for the duration of the construction contract (assumed a total of ten (!0) construction meetings) to answer questions or provide input. Therefore, for this proposal, we have assumed that Tetra Tech will be requested to attend eleven (I I) meetings. We have assumed that the meeting agenda and minutes will be prepared by Butier Engineeering, Inc. Task 9: Shop Drawing Review Tetra Tech will review and process shop drawing submittals. It may be in the City's best interest to have Butier Engineering, Inc. review several of the non-engineering shop drawing submittals, as well as Leighton review the geotechnical submittals in lieu of Tetra Tech. Based on this assumption, we have assumed that Tetra Tech will be required to review approximately seventy (70) shop drawing submittals. We can provide a summary of these submittals if requested by the City. We have also assumed that each submittal will need to be reviewed only twice (the original submittal and one re- submittal). Tetra Tech will complete our review of each submittal within ten (10) working days of receiving the submittal. Tetra Tech will maintain a tog for shop drawings. Task 10: Requests for Information (RFIs) Tetra Tech wilt respond to Contractor's "Request for Information" as requested by the City/Construction Manager. We have assumed that several of the RFIs will be reviewed and responded to by Butier. For this proposal, we have assumed approximately twenty-five (25) RFIs will require our response. Tetra Tech will provide a response to each RFI within twenty-tour (24) hours. TETRA TECH ~Ir. Kunal Mittal, P.E. April l5, 201 I Page 4 In addition, Tetra Tech will provide revised design details and clarifications sketches in response to the Contractor's IZFI. We have assumed ten (10) of the above twenty-five (25) RFIs will require this additional response effort. Tetra Tech will notify the City within twenty-four (24) hours of receiving these RF1s with the proposed schedule for providing the revised design details and sketches. Tetra Tech will maintain a log for RFIs. Task 11: Minor Plan Changes Tetra Tech will prepare minor plan changes due to changes in the field conditions and/or at the request of the Contractor and/or Construction Manager. For this proposal, we have assumed sixty (60) hours for these minor plan revisions. Tetra Tech will maintain a log of plan revisions. Task 12: Change Order Support Tetra Tech will provide support services in reviewing Change Order requests provided by the Contractor. This will include discussions with the Construction Manager. We have assumed that the majority of the change order review and evaluation wilt be performed by Butier and Tetra Tech will only provide engineering review support. For this proposal, we have assumed a total of six (6) Change Order requests will require our review. Task 13: Record Drawings Tetra Tech will prepare record drawings based on Contractor's and Construction Manager's red-lines. Tetra Tech will submit both mylars and electronic files. We have assumed that Butier Engineering, Inc. will provide all coordination of services: survey, concrete/material testing, geotechnical inspection, sewer discharge permit coordination, County of Orange permit coordination, private property coordination, OCSD coordination, East Orange County Water District coordination, etc. In addition, we have assumed that Butier will provide the final inspection, coordinate the testing and start-up procedures, and prepare the Operation and Maintenance Manuals. 5ummarv Tetra Tech does not control the amount of submittals, RFIs or such that will be submitted by the Contractor. In addition, Tetra Tech does not control the adequacy of the submittals prepared by the Contractor or the level of additional information required by the Contractor. This proposal is based on the assumptions noted above for each scope of work task item. Tetra Tech will perform the above scope of services on a Time and Material Basis and will provide status summaries to the City each month. O TETRATECN lVtr. Kunal Mittal, P.E. April I5, ?011 Page 5 Tetra Tech recommends the City budget the following amount for the Construction Support Services: ltem~~o:'.- . Description of ~cop4 of Word= 1 Pro'ect Mana ement (30 months) ` Requested Budget. 2 Phase l Construction Meetin s (3 meetin s) ~ 14 800 3 Phase I Sho Drawin Review (4 sho drawin s) $ $ 1,300 3 300 ~ Phase 1 Re uests for Information (5/1 RFis) , 5 Phase 1 Minor Plan Chan es (20 hours) $ 3,500 6 Phase l Chan a Order Su rt (I CO) $ $ 2,600 2 ~ Phase 1 Record Drawin s '~ 8 Phase 2 Construction Meetin s (11 meetin s) ~ 1 500 9 Phase 2 Sho Drawin Review (70 sho drawin s) $ $ 5 200 47 000 10 Phase 2 Re uests for Information (25/10 RFIs) 1 I Phase 2 Minor Plan Chan es (60 hours) $ 16,100 12 Phase 2 Chan a Order Su rt (6 CO) $ 7'~ 13 Phase 2 Record DCaWU7QC $ !7'200 Total $134~gpp We have included herewith a summary of the person-hour estimate for the work and our Hourly Rate Schedule for the project (assuming the construction will not be completed until December 2013). The above requested budget is based on this Hourly Rate Schedule. We appreciate the opportunity to submit this proposal. If you have any questions, please do not hesitate to call me at (949) 809-5156. Si erely, ~> Tom Epperso~, P.E. Vice President Engineering & Architecture Services TLE/te P:1P03291\0030\WordproDrafts\proposal for construction support srrvices.doc Attachments ~_ W Z ~ ~ W H ~ W W ~ ~ O ~ x ~? z J ~ U ~ w a. ~°n ° o °o °o °o °o °o °o ° °o 0 0 ° vi N~ o M M in ~ O~ vl .r o N O O N N V] 00 ~O „may cA6s ~--~ M M N N V) v3~vassdsds -, vi r ~ ~ ~ '"' O 6s~ `j M ~, . v~" dsds ~• ~ '• ~ O O ~ ~p ~ ~ N ~ ~ Oro N ~ 000 ~ ONO ~ ~ o M r N Vi O ~ ~ ~ ~ M O ~ ~ ~ N ~o ~ ~ ~ d' ~ O M ,~ ~ O Uj 69 b9 b9 69 6A 69 69 ~ 6A 6~R b9 6~9 ~ ~ 69 ~ ~ ~ i9 6 G7 ~y O O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O 0 0 0 0 0 0 0 0 0 0 0 0 0 0 O O O O N O O N ^~ V O~ 0 0~ ~--~ N N O O O 0 0~~ 0 ~O N 0 0~ ~n O~~ ~ U ~~~iii W~ o 0 0 o v o 0 0 0~ o° o 0 0 0~ ~ M ~ c~ (~C " O O O O O O 7 O N ~D O O O o0 O 00 ~ N w ~ a~ o0 0 000000~o N o°o~oNO a~ o° M ~ov~no~o?y ~ooNONO ~ :° ~ O M O •--~ N O V O [~ ~O ,~-i oo O N O ~ CQ R CC J~ O t 7 O 7 ~ ~ ~ a ~ U N i. c C ~y ~ by "" ~ Q ~ .^'.i ~ sti ate" bA 'n R Q " .. ~ U 0 . ~ .~.. O U .C . ~ .N.i O U ` a> Y ~ N V ~" O ~ y N~ p O~ ~i en ° ~ ~ o a `° ~y ~, ~ ~ , ~ ~ n, F '~ v ~ a7 ~ G4 w ~ ~ on ~ ~ ~ ~. ~ ~ ~ ~ c ~ ~ U ~ ~ ~ ~ }' U ~ ~ a i d~~ .o ~ ~ O '~ w b~ •~ a~ ^ . ~ h O 3 <° ~ •° •~ pq ~ y a 4 ~ Q o ~ ~a ~ ~O O p U V] Chi /. U Chi ~ U c~/~ Ri ~ U Chi r i G~ ~ ~ N M ~ ~ ~C l~ ~ 00 01 ~ -~ ~ -M-~ F A a V W H F- W H TETRATECH l ""1 2011 to 2013 HOURLY CHARGE RATE AND E`CPENSE REIIVIBURSEIV[ENTSCHE0ULE Professional Engineering Intern!Technician/Assistant....$ 68.00 Project Administrator .................................$ 80.00 Designer/CAD Operator/En ineer [ g .......... Engineer II and IIUSenior Designer ......... .$ 128.00 .$ 138.00 Biologist .................................................... Planner .$ 120.00 .......................... ................... $ ! 20.00 . .... Senior Engineer/Landscape Architect ........$ 140.00 Project Engineer/Project Coordinator ........ $ 168.00 Senior Planner ............................................ Senior Scientist $ I G0.00 ........................................... Project Manager/Sr. Project Coordi t $ 160.00 na or... Senior Project Manager .............................. $ 208.00 $ 285.00 Program Director/Project Director ............. $ 285.00 Admi---ni~trative Administrative Clerk ............................:.....$ 70.00 Word Processor/Admin. Support ................$ 92 00 Graphic Designer ........................................$ 125.00 Reimbursable In-House Costs Photo Copies (B&W 8.5"x11").......$ 0.15/Each Photo Copies (B&W t 1"x 17")....... .$ 0.40/Each Color Copies (up to 8.5"x 1 I ") ........ $ 2.00/Each Color Copies (to 1 I "x 17") .............. $ 3.00/Each Computer Usage .............................. $ 2.10/Hour Compact Discs ................................ $10.00/Each Large Format Copies ...................... $ 0.40/S.F. Mileage .......................... .$0.55/Mile *current IRS POV Mileage Rate subject to change Company Vehicles ...........................$8.00/Hour Reproduction, special photography, postage, delivery services, express mail, out-of--area telephone calls, printing and any other services performed by subcontractor, will be billed at cost plus 1 ~%. NOTE: All rates are effective from January I, 2011 to December 31, 2013. There will be a negotiated increase in rates, 5% maximum per year, for contracts extending beyond December 31, 2013. P:\P03291\003(NWcxdproDrafts\ExhibitA-201 t to 20t3.doc V ® J = O~. r^ ~O~ ~ Iv 1. yy~j ~~ ~ ~ ~~' y~ ~~~~ ~~~'~ b~'O v ~ti Z F-- Q U ~~ p~' Odba ti '~ s ~ ~P~ U \ ~ ~~ \ ~ ~. \ ~o \ ~ ~oti~ ~ ~ ~tib~ 0 ~, ~ zv~ ~~~ b~. ~~\ QO ~ ~P Jv ~O v / ~~ ~ d ~„_~ x ~~J ~ o 0 R $ ~ ~O $ 1 F O U O z U ... w W U w O w w o~ Z OQC Q z H U 7