HomeMy WebLinkAbout10 APPROVE PLANS AND SPECS FOR CITY YARD ROOF~ Agenda Item 10 - - - ~ RG E N DR R E P Q RT Reviewed: ~_ ,, City Manager _ s' Finance Director MEETING DATE: SEPTEMBER 6, 2011 TO: WILLIAM A. HUSTON, INTERIM CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE ADVERTISEMENT FOR BIDS FOR THE CITY YARD MECHANIC SHOP ROOF REPLACEMENT CIP NO. 10032 SUMMARY Plans and specifications for the City Yard Mechanic Shop Roof Replacement CIP No. 10032 have been prepared and the project is ready to be bid. Staff is requesting permission to advertise and to purchase, in advance, the necessary roofing materials utilizing the State Department of General Services pursuant to Tustin City Code 1624(c). RECOMMENDATION It is recommended that the City Council: 1. Adopt Resolution No. 11-58 approving the plans and specifications for the City Yard Mechanic Shop Roaf Replacement CIP No. 10032 and authorize the City Clerk to advertise and receive bids; and 2. Adopt Resolution No. 11-59 authorizing the State Department of General Services to acquire on behalf of the City roofing materials from the Garland Roofing Company, Inc. of Cleveland, OH in the amount of $53,686.82; FISCAL IMPACT $200,000 has been budgeted and appropriated in the Fiscal Year 2011-2012 Capital Improvement Program for this project. DISCUSSION The City Yard Mechanic Shop was constructed in 1978. While the roof of this facility has exceeded its life-expectancy, there have been periodic problems that have resulted in water intrusion during inclement weather. Although repairs to the facility have minimized the intrusion problems, a complete replacement of the roof is now recommended. The plans and specifications have been completed and this project is now ready to advertise for bid. This project, as specified, will correct all deficiencies, reduce the amount of annual maintenance required, improve facility's reliability, protect the structural integrity of building components, and will include a 30-year warranty. A major advantage of using the California Multiple Award Schedule (CHAS} for purchasing of materials for a roofing project is the financial incentive. This CHAS pricing is negotiated and includes a significant discount for materials over materials pricing contained in a contractor's bid. Approve Plans and Specifications for City Yard Roof September 6, 2011 Page 2 Contractor's materials pricing are typically marked up an average of 30%. For this project staff is projecting savings of approximately $14,500. The tentative schedule for construction of the project is as follows: • Authorization to Advertise for Bids ............................................09/06/2011 • First Legal Advertisement ......................................................... 09/08/2011 • Second Legal Advertisement .................................................... 09/15!2011 • Bid Opening ............................................................................. 09/27/2011 • Award of Contract .....................................................................10/18/2011 • Start Construction .................................................................... 11!14/2011 • Complete Construction ................:..............................................1/17!2012 This project is Categorically Exempt under California Environmental Quality Act (CEQA) and a Notice of Exemptjlon has been filed and recorded with the County Recorder's Office. Douglas .S. Stack, P.E. Dreetor,of Public Works/City Engineer Attachment A: Resolution No. 11-58 Attachment B: Resolution No. 11-59 SaCity Council Items\2011 Council ItemsWpproval of PS City Yard Vehicle Maintenance Shop Raof (CIP 10032).docx Attachment A RESOLUTION NO. 11-58 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA APPROVING PLANS AND SPECIFICATIONS FOR THE CITY YARD MECHANIC SHOP ROOF REPLACEMENT (CIP 10032) WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract for the construction of the City Yard Mechanic Shop Roof Replacement (CIP No. 10032); and WHEREAS, the City Engineer has presented plans and specifications for the construction of said work; and WHEREAS, this project is categorically exempt from the requirements of the California Environmental Quality Act; Class 1, Section 15301: Facilities Replacement; and NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by the City Engineer are hereby approved as the plans and specifications for: City Yard Mechanic Shop Roof Replacement (CIP No. 10032) BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to advertise as required by law for the receipt of sealed bids or proposals for the perFormance of the work specified in the aforesaid plans and specifications; PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held on the 6t" day of September 2011. Jerry Amante, Mayor ATTEST: City Clerk STATE OF CALIFORNIA ) COUNTY OF ORANGE ) SS CITY OF TUSTIN } I, Pamela Stoker, City Clerk and ex-officio Clerk of the City Council of the City of Tustin, California, do hereby certify that the whole number of the members of the City Council is five; that the above and foregoing Resolution No. 11-58 was duly and regularly passed and adopted at a regular meeting of the City Council held on the 6t" day of September 2011 by the following vote: COUNCILMEMBER AYES: COUNCILMEMBER NOES: COUNCILMEMBER ABSTAINED: COUNCILMEMBER ABSENT: PAMELA STOKER, City Clerk Attachment B RESOLUTION NO. 11-59 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA AUTHORIZING THE DEPARTMENT OF GENERAL SERVICES OF THE STATE OF CALIFORNIA TO PURCHASE CERTAIN ITEMS WHEREAS, the City has need to purchase various material, supplies and equipment in order to conduct the operations of the City; and WHEREAS, Section 1624, Item C of the Tustin Municipal Code authorizes the State of California to purchase materials, supplies, and equipment if it can be acquired more cheaply or efficiently by the state; NOW, THEREFORE, BE IT RESOLVED that the City Council of the City of Tustin, California, does hereby authorize the Procurement Division, Department of General Services of the State of California, to purchase roofing materials for and on behalf of the City of Tustin pursuant to Section 10324 of the California Public Contract Code, and that Mr. William A. Huston, Interim City Manager, is hereby directed to sign and deliver all necessary requests and other documents in connection therewith and for and on behalf of the City of Tustin. PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held on the 6th day of September 2011. Jerry Amante, Mayor ATTEST: Pamela Stoker City Clerk STATE OF CALIFORNIA ) COUNTY OF ORANGE ) SS CITY OF TUSTIN ) I, Pamela Stoker, City Clerk and ex-officio Clerk of the City Council of the City of Tustin, California, do hereby certify that the whole number of the members of the City Council is five; that the above and foregoing Resolution No. 11-59 was duly and regularly passed and adopted at a regular meeting of the City Council held on the 6t" day of September, 2011 by the following vote: COUNCILMEMBER AYES: COUNCILMEMBER NOES; COUNCILMEMBER ABSTAINED: COUNCILMEMBER ABSENT PAMELA STOKER, City Clerk