HomeMy WebLinkAbout11 CATCH BASIN PROJ. 05-06-02AGENDA REPORT NO. 11 , 4~,06-02 · 400-45 MEETING DATE: MAY 6, 2002 TO: FROM: WILLIAM A. HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION SUBJECT: REJECTION OF BIDS FOR THE FISCAL YEAR 2001/2002 CATCH BASIN INSERT PROJECT (PROJECT NO. 402-6222) SUMMARY City staff is recommending that the City Council reject all bids for the project at this time. The City received four bids for this project, all higher than the engineer's estimate. City staff will revise the plans and specifications and bring this project back to the City Council for consideration at a future date. RECOMMENDATION It is recommended that the City Council reject all bids received on the Catch Basin Insert Project (Project No. 402-6222) for Fiscal Year 2001/2002 and direct staff to revise the plans and specifications to include additional locations funded by additional grant funds. FISCAL IMPACT There is no fiscal impact resulting from this action. BACKGROUND On February 19, 2002, the City Council adopted Resolution No. 02-23 approving the plans and specifications for the Catch Basin Insert Project (402-6222), and authorized and directed the City Clerk to advertise for bids. On March 28, 2002, bids for the project were opened and evaluated. The City received four bids, all higher than the engineer's estimate. There were also various questions regarding the manufacture and installation methodology of the catch basin inserts that caused a perception of ambigiuity among the bidders. City staff has been working with the City Attorney's office to address these questions. It was determined that although the specifications were clear and provided concise information, the City may wish to consider re-bidding the project to provide further clarity of the items. The Catch Basin Insert Project (402-6222) included 103 catch basins selected on the basis of site priority. Additional grant funding to be provided by the County to the City will allow for an estimated 40 additional catch basins to be tiffed with the inserts. City staff has received verbal authorization from the County to delay implementation of the current Fiscal' Year 01/02 funding and to combine it with the new funding into a single project, which is anticipated to be constructed during Fiscal Year 02/03. City staff will revise the plans and specifications and bring this project back to the City Council for consideration at a future date as one project with combined grant funding from Fiscal Year 01/02 and Fiscal Year 02/03. Rejection of Bids for the Fiscal Year 2001/2002 Catch Basin Insert Project (Project No. 402-6222) May 6, 2002 Page 2 Tim D. Serlet Director of Public Works/City Engineer Dana R. Kasdan ~ Engineering Services Manager S:\City Council Items~02 City Council Items~Bid Rejection Catch Basin Insert Project.doc