Loading...
HomeMy WebLinkAbout10 N.O.C. CIP 7001 07-15-02 NO. 10 AGENDA REPORT MEETING DATE: JULY 15, 2002 400-45 TO: FROM: SUBJECT: WILLIAM A. HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION ACCEPTANCE OF PUBLIC IMPROVEMENTS AND AUTHORIZATION TO FILE THE NOTICE OF COMPLETION FOR THE ANNUAL MAJOR MAINTENANCE PROJECT, FY 2001-2002 (CIP NO. 7001), AND ANNUAL SIDEWALK, CURB AND GU'I'TER REPAIR PROJECT, FY 2001-2002 (PROJECT NO. 402-6235) SUMMARY Construction of the Annual Major Maintenance Project, FY 2001-2002 (ClP No. 7001) and Annual Sidewalk, Curb and Gutter Repair Project, FY 2001-2002 (Project No. 402-6235) have been completed to the satisfaction of the City Engineer and are now ready for City Council acceptance. RECOMMENDATION It is recommended that the City Council adopt Resolution No. 02-64 accepting the construction of the Annual Major Maintenance Project, FY 2001-2002 (CIP No. 7001), and Annual Sidewalk, Curb and Gutter Repair Project, FY 2001-2002 (Project No. 402-6235), and authorizing the recordation of the Notice of Completion, and direct the City Clerk to: 1. Release the Labor and Materials Bond not sooner than thirty-five (35) days after the date of recordation of the Notice of Completion; and 2. Release the Faithful Performance Bond not sooner than one-year after the date of recordation of the Notice of Completion; and Assuming no claims or stop payment notices are filed, it is further recommended that thirty-five (35) days after the date of recordation of the Notice of Completion the City Council authorize payment of the final 10% retention in the amount of $73,744.22 to R. J. Noble Company. The total final construction contract cost for the project is $737,442.20. FISCAL IMPACT The final construction contract cost for the Annual Major Maintenance Project is $546,831.00 and is funded by the City's Capital Improvement Program. This year a portion of the work was performed within the County of Orange and the City will be fully reimbursed for its costs by the County per Cooperative Agreement No. D01-126, which was approved by the City Council on January 7, 2002. The final construction contract cost for the Annual Sidewalk, Curb and Gutter Repair Project is $190,611.20 and is funded by the City's Engineering Division Operating Budget (402-6235). Annual Major Maintenance Project, FY 2001-2002 (CIP No. 7001), and Annual Sidewalk, Curb and Gutter Repair Project, FY 2001-2002 (Project No. 402-6235) July 15, 2002 Page 2 BACKGROUND AND DISCUSSION The construction of the Annual Major Maintenance Project and the Annual Sidewalk, Curb and Gutter Repair Project was completed on July 3, 2002. Both of these projects are part of the City's ongoing Maintenance of Effort (MOE) requirements to maintain eligibility for Measure M funding. All of the construction work for this project has been completed to the satisfaction of the City Engineer, and is now ready for City Council acceptance. Tim D. Serlet Director of Public Works/City Engineer Dana R. Kasdan Engineering Services Manager TDS:DRK:ccg:NOC for Annual Pvmt & Sidewalk Repair 01-02 & Reso 02-64.doc Attachments: Resolution No. 02-64 Location Exhibit 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 02-64 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA, ACCEPTING THE WORKS OF IMPROVEMENT AND AUTHORIZING THE RECORDATION OF THE NOTICE OF COMPLETION FOR THE CONSTRUCTION OF THE ANNUAL MAJOR MAINTENANCE PROJECT, FY 2001-2002 (CIP NO. 7001), AND ANNUAL SIDEWALK, CURB AND GUTTER REPAIR PROJECT, FY 2001-2002 (PROJECT NO. 402-6235) WHEREAS, R. J. Noble Company, having a contract with the City of Tustin to construct the hereinafter described public works and improvement; and WHEREAS, the City Engineer has duly certified to the construction and completion of said public improvement hereinafter mentioned in a manner satisfactory to the City Council of the City of Tustin; and WHEREAS, the City Council finds that said contractor has completed said public improvement hereinafter more particularly described in accordance with the provisions of the contract documents and the Notice of Completion, and acceptance of said public works and improvement should be filed and payment of the balance due said contract authorized in accordance with the contract documents; NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tustin that said public works and improvement is found to be complete, and the same is hereby accepted. Said public works and improvement is more particularly described as follows' Annual Major Maintenance Project, FY 2001-2002 (CIP No. 7001), and Annual Sidewalk, Curb and Gutter Repair Project, FY 2001-2002 (Project No. 402-6235) BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin is hereby authorized to execute and file a Notice of Completion for the acceptance of said public works and improvement described herein as required by law. PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held on the 15th day of July 2002. ATTEST: Jeffery M. Thomas, Mayor City Clerk Z _I igc