HomeMy WebLinkAbout05 APPROVE PLANS AND SPECS FOR TRAFFIC SIGNAL BATTERY0 AGENDA REPORT
MEETING DATE: MARCH 6, 2012
TO: JEFFREY C. PARKER, CITY MANAGER
Agenda Item
Reviewed:
City Manager
Finance Director
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE TRAFFIC SIGNAL BATTERY BACKUP
SYSTEM INSTALLATIONS — PHASE 1 CIP NO. 40079 AND THE TRAFFIC
SIGNAL CONTROLLER EQUIPMENT UPGRADES/REPLACEMENTS — PHASE
1 CIP NO. 40080
SUMMARY
The plans and specifications for both the traffic signal Battery Backup System Installations — Phase
1 CIP No. 40079 and the Controller Equipment Upgrades/Replacements — Phase 1 CIP No. 40080
have been prepared and are ready to be bid.
RECOMMENDATION
It is recommended that the City Council adopt Resolution No. 12-18 approving the plans and
specifications for the Battery Backup System Installations— Phase 1 CIP No. 40079 and the Traffic
Signal Controller Equipment Upgrades/Replacements — Phase 1 CIP No. 40080, and authorize the
City Clerk to advertise to receive bids.
FISCAL IMPACT
Sufficient funds in the amount of $155,000 for the BBS and $140,000 for the TSC upgrades have
been budgeted and appropriated in the Fiscal Year 2011-2012 Capital Improvement Program
utilizing Measure M2 FairShare.
DISCUSSION AND BACKGROUND
The installation of Battery Backup Systems (BBS's) at traffic signals is desired in order to maintain
safe, normal vehicular operations when planned or unplanned electrical interruptions occur.
Although BBS's are currently being installed at all new traffic signals, there is a need to install them
at older traffic signals through a retrofit process.
The program currently shown in the Capital Improvement Program (CIP) includes four phases
spread out over four (4) successive fiscal years, thereby ensuring that all city -maintained traffic
signals have operational battery backup systems. The project under consideration is the first
phase of CIP No. 40079, consisting of eleven (11) traffic signals along Irvine Boulevard from
Myford Road to Yorba Street, excluding Tustin Ranch Road and Prospect Avenue which already
have BBS's. It also includes five (5) traffic signals along Tustin Ranch Road from La Colina Drive
to Pioneer Way.
CIP No. 40080 consists of three phases of upgrades or replacements of existing traffic signal
controller equipment spread over three (3) successive fiscal years due to the aging inventory. The
current project under consideration is the first phase of CIP No. 40080, and includes replacement
Battery Backup Installations and Traffic Signal Controller Upgrades
March 6, 2012
Page 2
of the entire controller cabinet assemblies on Irvine Boulevard at B Street, Fashion Lane,
Charloma Drive and Browning Avenue. Also, upgrades to existing controller and detection
equipment will be performed on Irvine Boulevard at Myford Road and Red Hill Avenue; at nine
intersections along Tustin Ranch Road from Auto Center Drive to Portola Parkway, excluding the
new signal at Greenway Drive/Adams Drive; and on Jamboree Road at Patriot Way and Pioneer
Road.
CIP's 40079 and 40080 are being bid together because the work in each project is similar in nature
and can be performed more efficiently by the same contractor. The tentative schedule for
construction of the projects is as follows:
• Authorization to Advertise for Bids ...................................................
. - 03/06/2012
• First Legal Advertisement ........... ......... -- .......... ........................
- 03/08/2012
• Second Legal Advertisement... . ... ........ ........................
....... ....... 03/15/2012
• Bid Opening ........... ............ .......... ....................... ..........
....... ... 04/05/2012
• Award of Contract ....... ......................................... ....................
.... - 04/17/2012
• Start Construction.. ..... ..... -- ...................................................
...... 05/14/2012
• Complete Construction ...... ................... ...............
................... 08/10/2012
Since these two projects involve the replacement and repair of existing facilities with minor
modifications, they are Categorically Exempt under California Environmental Quality Act (CEQA)
requirements. Notices of Exemption have been prepared for the projects, and recorded with the
County of Orange.
S. Stack, P.E.
of Public Works/City Engineer
Attachment 1: Resolution No, 12-18
Attachment 2: Location Maps
S:\City Council Items12012 Council Items\Approve P&S for 1313S Installations(CIP 40079) & Signal Controller Upgrades(CIP
40080).docx
ATTACHMENT 1
Resolution No. 12-18
RESOLUTION NO. 12-18
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE TRAFFIC SIGNAL BATTERY
BACKUP SYSTEM INSTALLATIONS — PHASE 1 CIP NO. 40079 AND THE TRAFFIC
SIGNAL CONTROLLER EQUIPMENT UPGRADES/REPLACEMENTS — PHASE 1 CIP
NO. 40080, AND AUTHORIZING ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract
for the construction of the Traffic Signal Battery Backup System Installations — Phase 1 CIP No.
40079 and the Traffic Signal Controller Equipment Upgrades/Replacements — Phase 1 CIP No.
40080; and
WHEREAS, the City Engineer has presented plans and specifications for the construction
of said work; and
WHEREAS, these projects are categorically exempt from the requirements of the California
Environmental Quality Act (CEQA); Class 1, Section 15301: Existing Facilities;
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by the
City Engineer are hereby approved as the plans and specifications for:
Traffic Signal Battery Backup System Installations— Phase 1 CIP No. 40079
and
Traffic Signal Controller Equipment Upgrades/Replacements — Phase 1 CIP No. 40080
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of the
work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held
on the 6th day of March 2012.
ATTEST:
Pamela Stoker, City Clerk
John Nielsen, Mayor
STATE OF CALIFORNIA
COUNTY OF ORANGE )SS
CITY OF TUSTIN
1, Pamela Stoker, City Clerk and ex -officio Clerk of the City Council of the City of Tustin, California,
do hereby certify that the whole number of the members of the City Council is five; that the above
and foregoing Resolution No. 12-18 was duly and regularly passed and adopted at a regular
meeting of the City Council held on the 6`"
day of March, 2012 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
PAMELA STOKER,
City Clerk
ATTACHMENT 2
Location Maps
TRAFFIC SIGNAL BATTERY BACKUP SYSTEM
GIP NO. 40079 (PHASE 1)
Ail I-A
A'
vAFmErR>ERc m
FOURiN smm mmah, Wo. )v
5 F
FEST STREET �
wsm Ru x
W6AM A%U*"X p
4 � ROEBlSpN dE
EORm muff
y `/
TUSTIN LEGACY `
LEGEND:
'' !d• ` : �i, ! ^ PROPOSED 0ATMmmtm 9ACIQIP SYSiEII NSTNUTpFS AT WW
somm P T nm
y _1.. !a' FVRK RIM MAY
LOCATION MAP FMRIJARY
SIGNAL CABINET ASSEMBLY REPLACEMENTS &
X11:1
-.00ATION MAP