HomeMy WebLinkAbout07 TUSTIN RANCH ROAD PHASE 2-BRIDGE OVERCROSSINGAgenda Item 7
AGENDA REPORT Reviewed:
City Manager
Finance Director JA
MEETING DATE: SEPTEMBER 4, 2012
TO: JEFFREY C. PARKER, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER
SUBJECT: TUSTIN RANCH ROAD PHASE 2 ROADWAY IMPROVEMENTS PROJECT
BRIDGE OVERCROSSING
SUMMARY
The Tustin Ranch Road Extension project is entering the second and final phase of construction. With
the construction contract, bonds, and insurances approved and executed, a Notice to Proceed has
been issued to RJ Noble with a project start date of August 23, 2012.
A key component of the Phase 2 work is the bridge overcrossing Edinger Avenue, the Regional
Orange County Flood Control Santa Ana /Santa Fe Channel, and the Southern California Regional Rail
Authority (SCRRA) Railway tracks. Construction of the bridge will require the installation of 190 driven
piles to support the bridge superstructure and pile placement will generate noise and vibration typical
of any pile- driving operation. In addition, due to the close proximity of the rail tracks trains will sound
their horns traversing the construction zone as a measure of life safety and precaution pursuant to the
project agreement with SCRRA.
RECOMMENDATION
Receive and file.
FISCAL IMPACT
n/a
DISCUSSION
Normal construction activity will occur on weekdays during normal working hours (7:00 AM to 6:OOPM)
as allowed in the Tustin Municipal Code. However, there will be times when certain aspects of work
will need to occur on weekends and at night as directed by SCRRA in an effort to continue rail service
during the daytime. Public outreach will be paramount. The project team will ensure that is a top
priority and ensure the neighboring community is kept well informed in an utmost timely manner.
The pile- driving operation is scheduled to occur from mid - September to the beginning of December
2012. The operation will occur weekdays no earlier than 8:00 AM until 5:OOPM, although other
construction will begin at 7:00 AM per City Code. Again, due to the close proximity of 48 piles to the
railroad tracks these piles will need to be installed during the weekends when rail traffic is reduced. It
is anticipated that four weekends, both Saturday and Sunday, between the end of October and mid -
November will be needed to install these piles. Pile- driving on weekends will begin no earlier than
9:00 AM and end at 4:00 PM. To attenuate noise, the contractor will be installing sound blankets
around the support structure for the pile- driving apparatus.
Tustin Ranch Road Phase 2 Construction Project
September 4, 2012
Page 2
Pile- driving on weekends will begin no earlier than 9:00 AM and end at 4:00 PM. To attenuate noise,
the contractor will be installing sound blankets around the support structure for the pile- driving
apparatus. Night -time construction work is limited between 9:00 PM and 4:00 AM. Night -time work
will also be necessary to install and remove some of the overhead structure formwork after the pile
and foundation installation is complete. Notices will be sent out in advance to the community nearby
when that work is scheduled.
Access to the north side of the railroad tracks to install the piles and foundations in that area and
construct the overhead structure will be via the abandoned Katherine Spur between the Peppertree
and Tustin Meadows communities. The contractor will be transporting materials, equipment, and
personnel through this area. Use of this area will be heaviest during pile- driving and foundation
installation operations and then somewhat intermittently until completion of the bridge.
Information pertaining to this next phase of construction has been included in the City Scene as well
as on the City's webpage. The attached notice will be sent out to residents within the Peppertree,
Tustin Meadows, and Columbus Square communities detailing this information and providing contact
information for questions and inquiries.
Stack, P.E.
Public Works /City Engineer
Attachment: Resident Notice
S: \City Council Items\2012 Council Items \Receive file TRR Phase 2 Construction - Edinger Overcrossing.docx
September 5, 2012
Dear Tustin Resident:
As part of our continuing commitment to improving traffic flow throughout the city, the
City is extending Tustin Ranch Road from Walnut Avenue to Warner Avenue as you probably
are aware. Construction is being done in two phases. Phase 1 consisting of grading, storm
drain, and retaining wall work has recently been completed and we are beginning Phase 2 of
the project. Phase 2 will consist of the remaining street utilities, pavement, sidewalks,
landscaping and the bridge over Edinger Avenue, the railroad tracks, and the flood control
channel and will last for several months.
So what can you expect? First, the contractor will be using the abandoned railroad spur
located between Tustin Meadows and Peppertree for staging and construction access to the
area between the railroad and the flood control channel. Use of this spur will be heaviest during
the pile- driving and foundation construction operation and will be sporadic thereafter until
completion of the bridge. During construction, obviously there will be an increase in
construction activity and you will hear more train horns than usual in the vicinity of the future
overpass as a railroad safety measure to alert workers of oncoming trains. Beginning late
September, the installation of 190 piles and associated foundation work which are required for
supporting the bridge will begin. It is estimated that pile- driving alone will take two to two- and -a-
half months to complete. The contractor will be installing sound attenuation blankets around the
support structure for the pile- driving hammer to minimize noise and pile- driving operations will
be limited to the weekday hours of 8 a.m. to 5 p.m. For railroad and job site safety, the segment
of the pile- driving operations closest to the railroad tracks are required to be completed only
during weekends and the foundation work only at night when rail traffic is minimized. This
weekend and night work is anticipated to occur between late September and mid - January. Pile -
driving under these special circumstances working both Saturday and Sunday will be limited to
the hours of 9 a.m. to 4 p.m. The schedule for required night work will be minimized as much as
possible, limited to the hours of 9 p.m. to 4 a.m. However, weekend pile- driving and related
nighttime work will not be allowed over the Thanksgiving Holiday and the period from Monday,
12/24 thru Tuesday, 1/1/2013 in consideration of the Holiday Season. Lastly, some work to
erect formwork and the superstructure over the railroad tracks is also required to be done at
night, again for railroad and job site safety. The exact schedule for this phase of work in 2013
will be finalized at a later date after the pile- driving and foundation work is completed. A
subsequent notice will follow once those dates are determined.
We have added a new section to the city homepage which will provide you with up -to-
date information on construction and can be accessed at www.tustinca.orp.
We ask for your patience and understanding during this time. Should you have any
questions or concerns regarding this project, please feel free to contact me at (714) 573 -3389 at
your convenience.
Sincerely,
Ken Nishikawa, P.E.
Tustin Legacy Development Services Manager