HomeMy WebLinkAbout05 EDINGER AVENUE WELL PROJECT-PHASE I DRILLING CIP 60165AGENDA REPORT
OW
MEETING DATE: OCTOBER 16, 2012
TO: JEFFREY C. PARKER, CITY MANAGER
Agenda Item 5
Reviewed.
City Manager CA
Finance Director
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER
SUBJECT: APPROVE PLANS AND SPECIFICATIONS AND AUTHORIZE
ADVERTISEMENT FOR BIDS FOR THE EDINGER AVENUE WELL
PROJECT — PHASE I DRILLING CIP 60165
SUMMARY
The plans and specifications for the Edinger Avenue Well Project — Phase I Drilling CIP 60165
have been prepared and the project is ready to be bid.
RECOMMENDATION
It is recommended that the City Council:
1. Appropriate $1,800,000 from the 2011 Water Revenue Bond Fund (Fund 305) to the
Edinger Avenue Well Project — Phase I Drilling CIP 60165; and
2. Adopt Resolution No. 12 -90 approving the plans and specifications for the Edinger
Avenue Well Project — Phase I Drilling CIP 60165, and authorize the City Clerk to
advertise to receive bids.
FISCAL IMPACT
Sufficient funds, in the amount of $200,000, have been budgeted for the preliminary design
phase of the Edinger Avenue Well Project in the Fiscal Year 2012 -2013 Capital Improvement
Program Budget. Well drilling was planned for FY 2014/15. To advance Phase I Well Drilling,
$1,800,000 will need to be appropriated from the bond proceeds from 2011 Water Revenue
Bond issuance. There is a $5,000,000 fund balance in net bond proceeds in Fund 305.
DISCUSSION
The construction of the Edinger Avenue Well CIP 60165 has been advanced to coordinate with
the construction of the Residence Inn and the Fairfield Inn by RD Olson Company and to
complete the drilling phase of the project before the grand opening and occupancy of the hotels.
The proposed project will be implemented in two phases: Phase I Drilling, and Phase II
Construction /Equipping. This project will enable the City to improve its groundwater production
and reliability. Ultimately, the well will be contained within in a structure that is approximately
2,000 square feet in size, designed to match and blend with the adjacent architecture and land
use.
The proposed well will be drilled in two passes (i.e. pilot borehole and reamed borehole) using
the reverse circulation rotary drilling method with installation of a gravel envelope to stabilize the
formation materials. A 17.5 -inch pilot borehole will be drilled to an estimated total depth of
1,300 feet.
Edinger Avenue Well Project CIP 60165
October 16, 2012
Page 2
Once the pilot borehole has been drilled, a suite of geophysical logs will be obtained. Isolated
aquifer zone testing will then be performed, the results of which will be used to quantify aquifer
yield and ground water quality. This data will be instrumental for preparation of the final well
design such that the best possible ground water quality can be achieved. Production rates for
the proposed well are expected to range from approximately 1,500 gallons per minute (gpm) to
2,500 gpm.
Drilling, construction, development, and testing of the well will require approximately 75 work
days to complete (not including weekends). During that period of time several phases of the
work will require 24 -hour continuous operations on the part of the drilling contractor. The
number of work days required for each major phase of well installation, and the nature of that
work (i.e., 24 -hour or daylight only) is summarized below:
Conductor Installation 1 Daylight Only
Mobilization
Pilot Borehole Drilling
Isolated Aquifer Zone Testing
Well Construction
Initial Well Development
Demobilization of Drilling Rig /
Mobilization of Test Pump & Motor
Final Development
Step Drawdown Aquifer Test
24 -Hour Constant Rate Aquifer Test
Well Disinfection
5 Daylight Only
6 24 -Hour Continuous
8 24 -Hour Continuous
3 24 -Hour Continuous
7 24 -Hour Continuous
7 Daylight Only
6 Daylight Only
1 Daylight Only
2 24 -Hour Continuous
1 Daylight Only
Gyroscopic & Video Surveys 1 Daylight Only
Edinger Avenue Well Project CIP 60165
October 16, 2012
Page 3
The tentative project schedule for the drilling phase is as follows:
• Authorization to Advertise for Bids .......................
.....................10 /16/2012
• First Legal Advertisement ....................... ...............................
10/18/2012
• Second Legal Advertisement ................... ...............................
10/25/2012
• Bid Opening ........................................ ...............................
11/19/2012
• Award of Contract... ... .........................................................
12/04/2012
• Start Construction ................................ ...............................
01/15/2013
• Complete Construction .......................... ...............................
05/01/2013
Based on current material prices and recent bids for similar types projects, the estimated cost
for drilling, constructing, development, construction management & engineering, testing, and
contingency is approximately $ 1,800,000.
The Edinger Avenue Well Project CIP 60165 is Categorically Exempt under California
Environmental Quality Act (CEQA) requirements. A Notice of Exemption has been prepared for
the project, and will be recorded with the County of Orange following Council approval of the
plans and specifications.
S. Stack, P.E.
of Public Works /City Engineer
Attachment 1: Resolution No 12 -90
Attachment 2 Vicinity Map
S' \City Council Items\2012 Council Items\Approval of P &S Edinger Avenue Well Drilling CIP 60165.docx
ATTACHMENT 1
Resolution No. 12 -90
RESOLUTION NO. 12 -90
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA
APPROVING PLANS AND SPECIFICATIONS FOR THE EDINGER AVENUE WELL
PROJECT — PHASE I DRILLING CIP NO. 60165, AND AUTHORIZING ADVERTISEMENT
FOR BIDS
WHEREAS, it is the intention of the City Council of the City of Tustin, California to contract
for the construction of the Edinger Avenue Well Project — Phase I Drilling CIP No. 60165; and
WHEREAS, the City Engineer has presented plans and specifications for the construction
of said work; and
WHEREAS, the project is categorically exempt from the requirements of the California
Environmental Quality Act (CEQA); Class 3, Section 15303: New Construction or Conversion of
Small Structures;
NOW, THEREFORE, BE IT RESOLVED that the plans and specifications presented by the
City Engineer are hereby approved as the plans and specifications for:
Edinger Avenue Well Project — Phase I Drilling CIP No. 60136
BE IT FURTHER RESOLVED that the City Clerk is hereby authorized and directed to
advertise as required by law for the receipt of sealed bids or proposals for the performance of the
work specified in the aforesaid plans and specifications;
PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin held
on the 16`h day of October 2012.
John Nielsen, Mayor
ATTEST:
Pamela Stoker, City Clerk
STATE OF CALIFORNIA )
COUNTY OF ORANGE ) SS
CITY OF TUSTIN )
I, Pamela Stoker, City Clerk and ex- officio Clerk of the City Council of the City of Tustin, California,
do hereby certify that the whole number of the members of the City Council is five; that the above
and foregoing Resolution No. 12 -90 was duly and regularly passed and adopted at a regular
meeting of the City Council held on the 16`h day of October, 2012 by the following vote:
COUNCILMEMBER AYES:
COUNCILMEMBER NOES:
COUNCILMEMBER ABSTAINED:
COUNCILMEMBER ABSENT:
PAMELA STOKER,
City Clerk
ATTACHMENT 2
Vicinity Map
VICINITY MAP
Edinger Avenue
Well Project
I (CIP No. 60165)
lyy°
i Y t
P
IMR y
r Yy Y�
r
d t
TUSTIN
RANCH v
a
a `
�h met. v
't r p
r •tS,j,�
r �
4
TJSTN LEGACY
v
.� NO SCALE
' G
y F99�
PROJECT LOCATION
2100 E. Edinger Avenue
Santa Ana, CA 92705
A. T
Q•
FILE: CIP- 60163- MCINITY.dwg