AWARD OF BID FOR PEPPERTREE & MAGNOLIA TREE PARKS
RENOVATION PROJECT NO. 2039
SUMMARY:' A request ofthe City CoUncil t0 award Constmefi0nSe~ceS::lo Big Ben
ConstrUctiOn Company ofNewP0nBeaCh for a not tO exCeed am0~nt .0[$599,700 four me
peppertree Park and Magnolia Tree Park Ren69ati0n Pr0j~i' ~ additional request tora
Supplemental Appropriation of $210,000 from the Park Development. Fund is necessary
to complete the project.
RECOMMENDATION:
It is recommended that the City Council take the following action subject to an
appropriation of $210,000 from the Parks and Recreation Services Parks Development
Fund to Capital Improvement Project No. 2039.
.
Award a contract for the construction of Peppertree Park and Magnolia Tree Park
Renovation (Project No. 2039) to Big Ben Construction Company of Newport
Beach, in the amount not to exceed, $599,700.
FISCAL IMPACT:
The project requires a total of $755,000 to complete as bid. The original appropriation
for the project was $545,000, which was allocated as follows:
Capital Improvement Fund-General Fund
Grant- County of Orange Urban Park & Recreation Program
Park Development Fund
Redevelopment Agency -Town Center Area
$195,000
$100,000
$ 10,000
$240,000
BACKGROUND AND DISCUSSION:
On November 17, 1999, bids were opened for the Peppertree Park & Magnolia Tree Park
Renovation Project. This project includes the renovation and replacement of the
restrooms at Peppertree Park and Magnolia Tree Park. Additional amenities included in
this project are as follows:
Peppertree & Magnolia Tre~
Project No. 2039
Page 2
Renovation
Peppertree Park
Construction of the band shell picnic area
Refurbishment of the existing picnic shelter
Replacement of tot lot equipment
Improvements to the Tustin Area Senior Center lounge and patio area
Magnolia Tree Park
New tot lot equipment
Tennis court resurfacing
Sealed bids for the combined projects were opened, and nine construction companies
submitted responsible bids.
CONTRACTOR
Big Ben Construction Co.
Groundwater Remediation Construction Co.
Urbantec
Construct 1 One Corp,
Alexander Associates
SMC Construction
AJ Construction Ent.
Construction Systems
Newman-Midland
Bm.
$599,700.00
$676,382.88
$692,719.00
$711,372.03
$728,946.38
$788,679.19
$825,443.00
$855,408.00
$880,105.00
The Project Manager has determined that Big Ben Construction Co. holds a valid
Contractor's License, has checked references and reviewed the bid. The City Attorney
will complete a review of the required bonds and insurance certificates. Construction of
the project should begin in early January 2000. Completion of the project is estimated to
be May 15, 2000.
Following the bid opening, it was determined that the original appropriation of $545,000
was inadequate to complete the project. The original appropriation was determined in
June 1998. Since that time, the scope of work has significantly changed to include
additional amenities such as the band shell picnic shelter, improved tot lot equipment,
additional renovations to the Senior Center, and significant additional requirements for
ADA compliance.
The expenses to date total $64,195.00, which included Architectural, Engineering and
preparation of Construction Documents.
Peppertree & Magnolia.Tree. __,cs Renovation
Project No. 2039
Page 3
The projected expenses for the project include:
Construction Bid
10% contingency
Add Alternates to meet ADA compliance
Difference in the scope of work in relation to the
past appropriation
$599,700
$59,900
$22,3OO
$54,7O0
The Supplemental Appropriation request is $210,000.
These upgrades to substandard public infrastructure systems and public facilities and the
provision for the installation and constmction of new public improvements help meet the
requirements of delivering adequate park and recreation, facilities to the community of
Tustin.
Respectfully,
Director, Parks
Recreation Services
cc: Ron Nault, Finance Director