HomeMy WebLinkAbout10 FY 2012-13 ROADWAY REHAB/CITYWIDE SIDEWALK REPAIR PROJECTAGENDA REPORT Agenda Item Reviewed: City Manager Finance Director 10 MEETING DATE: APRIL 16, 2013 TO: JEFFREY C. PARKER, CITY MANAGER FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER SUBJECT: AWARD CONTRACT FOR THE FY 2012 -13 ROADWAY REHABILITATION AND CITYWIDE SIDEWALK REPAIR PROJECT CIP 70001 SUMMARY Staff is requesting that the City Council award a construction contract to the lowest responsive /responsible bidder for the Fiscal Year (FY) 2012 -13 Roadway Rehabilitation and Citywide Sidewalk Repair Project CIP 70001. RECOMMENDATION It is recommended that the City Council award a construction contract to the lowest responsive /responsible bidder, Sequel Contractors, Inc., in the amount of $1,139,028.79, for the FY 2012 -13 Roadway Rehabilitation and Citywide Sidewalk Repair Project CIP 70001 and authorize the Mayor and the City Clerk to execute the contract documents on behalf of the City. FISCAL IMPACT Sufficient funds in the amount of $1,760,000 has been budgeted and appropriated in the Fiscal Year 2012 -2013 Capital Improvement Program Budget. CIP 70001 is part of the City's on -going Maintenance of Effort (MOE) obligation to maintain eligibility for Renewed Measure M (M2) funding. Funding is provided through a combination of General Fund and Gas Tax. DISCUSSION The Roadway Rehabilitation and Citywide Sidewalk Repair CIP 70001 for Fiscal Year 2012 -13 includes asphalt concrete pavement repair, asphalt concrete overlay, slurry sealing, and traffic striping on various streets within Zone 1 of the City's Pavement Management Program. Zone 1 is generally bounded by the north city boundary, the SR -55 Freeway to the west, Irvine Boulevard to the south, and Newport Avenue to the east. The project also includes citywide sidewalk repair which focuses on removal and replacement of damaged sidewalk to correct tripping hazards at numerous locations throughout the City based on an annual field survey conducted by the Engineering Division. The Engineer's Estimate was $1,268,965. Formal bids were publicly opened on April 9, 2013 and reviewed by Public Works. Six (6) bids were received and are summarized below by order of least dollar amount: • Sequel Contractors, Inc $ 1,139,028.79 • Palp, Inc., dba Excel Paving Company $ 1,198,583.75 • R.J. Noble Company $ 1,224,865.12 • All American Asphalt $ 1,234,234.00 • Hardy & Harper, Inc $ 1,252,000.00 • Roy Allan Slurry Seal Inc $ 1,326,562.31 FY 2012013 Roadway Rehabilitation & Citywide Sidewalk Repair CIP 70001 April 16, 2013 Page 2 Staff has reviewed the references and the State Contractor's License for Sequel Contractors, Inc. and has determined that they are appropriate for the subject project. It is recommended that the City Council award the construction contract to the lowest responsive /responsible bidder, Sequel Contractors, Inc., for the FY 2012 -13 Roadway Rehabilitation and Citywide Sidewalk Repair Project CIP 70001 and authorize the Mayor and the City Clerk to execute the contract documents on behalf of the City. Stack, P.E. D rec • o' Public Works /City Engineer Attachment: Location Map S: \City Council Items\2013 Council Items\Award of Contract for Roadway Rehab (CIP 70001).docx CITY OF TUSTIN PROJECT NAME: ANNUAL ROADWAY AND PUBLIC INFRASTRUCTURE MAINTENANCE PROGRAM (MOE) (CIP NO. 70001)