WILLIAM A. HUSTON, crI~ MANAGER.
PATRICK SANCI-IEZ, DIRECTOR, PARKS AND RECREATION SERVICES
PROGRESS REPORT: CED~ GROVE PARK (PROJECT NO. 400041) AND
ItERITAGE PARK (PROJECT NO. 400042)
RECOMMENDATION:
Receive and file.
BACKGROUND:
The City Council has requested monthly progress reports on the status of Cedar Grove and Heritage Parks. As of
this date the parks are proceeding as follows:
Cedar Grove Park (Project No. 400041)
The project is 100% complete. The punch list inspection has been completed and the 90-day period for
maintenance has expired. The Notice of Completion is agendized for the September 21~ City Council meeting.
Heritage Park (Project No. 400042)
The overall project is 85% complete.
· The hockey fink dasher board RMF System is 99% complete, with the perimeter fence 100% complete.
· The underground drainage system is 98% complete.
· The restroom sheeting, plumbing and roofing installation are all complete.
· Electrical work in the park is 95% complete, with site lighting 75% complete.
· All picnic pads have been poured.
· Landscaping is 50% complete.
· Tot lot installation is 75% complete.
Park Dedication is scheduled for Saturday, October 31, 1998, at 10:00 a.m.