HomeMy WebLinkAbout12 PROJECT 400042 08-17-98DATE: AUGUST 17, 1998
NO. 12
8-17-98
Inter C o/
TO:
FROM:
SUBJECT:
WILLIAM A. HUSTON, CITY MANAGER
PATRICK SANCHEZ, DIRECTOR, PARKS AND RECREATION SERVICES
PROGRESS REPORT: CEDAR GROVE PARK (PROJECT NO. 400041)
AND HERITAGE PARK (PROJECT NO. 400042)
ISIJMMARY:. City .Council has requested, monthly progress,.reports on Cedar Grove and
Heritage Parks. ~
RECOMMENDATION:
Receive and file.
BACKGROUND:
City Council has requested monthly progress reports on the status of Cedar Grove and
Heritage Parks. As of this date the parks are proceeding as follows:
Cedar Grove Park .(Project No. 400041)
The project is approximately 100% complete. All that remains are the following:
· Completion of the punch list inspection
· Re-circuiting of the flagpole light circuits (to leave flagpole lights on all night)
· Repair of the drinking fountain
· Irrigation repairs
· The remainder of the 90-day maintenance period
Maintenance period to conclude on September 1 st
Repairs have been made to the tot lot area to repair two hazards that have been noticed
since the park opened.
Heritage Park (Project No. 400042)
· The overall project is 70% com!21ete.
· The hockey rink concrete has been poured; concrete walkways around hockey rink
are complete.
· The underground drainage system is 95% complete, and all the drain structures have
been installed.
· The restroom building is 95% complete.
· The basketball court slab is complete.
· The curb and gutter on-site are 90% complete.
· Installation of valves, laterals and electric conduit is in place for the irrigation sYstem.
· The excess dirt has been hauled away and fmal grading is underway.
· Recent inspections of the tot lot fall zones found that the exact dimension
specifications for toys are in order.
· Parking lot approaches have been poured.
· The walkway parallel to Tustin Ranch Road is 100% poured.
· Demolition on Kinsman Circle and Heritage Way is complete. Concrete has been
poured.
· Re-cutting of tot-lot is complete, and boulder placement is in progress.
· Monument sign is 95% complete.
· Tree planting is in progress.
Park Dedication is scheduled for September 19, 1998.
Respectfully submitted,
Patrick Sanchez
Director, Parks and Recreation Services
SC
CC:
Gary Magill, Recreation Superintendent
e/mydocs/PS/Staff Reports/Progress Report CGP & HP.doc