WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/WATER SERVICES DIVISION
AWARD OF CONTRACT FOR WATER MAIN REPLACEMENT PROJECT
(C.I.P. NO. 600137)
SUMMARY I
This action is a request for authorization to award a construction contract for replacement of
deteriorating and undersized water mains at various locations listed below.
RECOMMENDATION
It is recommended that the Tustin City Council, at their regular meeting of April 20, 1998, award the
contract for the subject project to John T. Malloy, Inc. of Los Angeles, California, in the amount of
S312,054.64.
FISCAL IMPACT
The amount of this contract is $312,054.64. There is currently $444,880 remaining in the FY 1997/98
Water Service Capital Improvement Program budget allocated for completion of this project.
BACKGROUND
Bids were opened on April 7, 1998 for subject project and 10 bids were.received as follows'
John T. Malloy, Inc., Los Angeles .................................................................... $312,054.64
RLT Construction, Anaheim .............................................................................. $314,762.15
The Allison Co., Murrieta .................................................................................. $334,346.38
Wayne Perry, Inc., Buena Park ......................................... :.'. .............................. $335,093.15
Kana Pipeline, Inc., Placentia ............................................................................ $345,245.00.
Steve Casada Construction, Inc., Anaheim ........................................................ $355,000.00
RL Sewers, Paramount ....................................................................................... $357,076.80
Gillespie Construction, Costa Mesa ................................................................... $361,028.80
Majich Bros., Inc., Altadena .............................................................................. $367,575.95
Savala Construction, Irvine ................................................................................ $420,036.43
The low bid by John T. Malloy, Inc. is 15.8% under the engineer's estimate of $370,700.
The Contractor's references have been verified and their past job performances are satisfactoD~.
DISCUSSION
This project consists of the replacement of water mains on Lemona Lane southerly of La Colina Drive;
Windsor Place between Vanderlip and 17th Street; Cameron Lane southerly of Vanderlip Avenue; Ehlen
Way, Brenan Way, Harp Court, Manning Drive northerly of Warren Avenue and Fairmount Way
southerly of Fairhaven Avenue. These water mains will improve water system supply and circulation
and reduce maintenance and repair costs in these areas.
Following is the anticipated schedule for completion of the project:
Award of Contract ........................................................... 04/20/98
Begin Construction ............................................... .. ........... 05/18/98
Complete Construction .................................................. 08/18/98
Director of Public Works/City Engineer
TDS:GRV:klb/COUNCIL:Award Water Main 600137