HomeMy WebLinkAbout12 PROJECT 400042 03-16-98AGFN A
DATE:
March 10, 1998
Inter-Com
NO. 12
3-16-98
TO'
FROM:
SUBJECT:
William A. Huston, City Manager
Parks and Recreation Services
PROGRESS REPORT ON CEDAR GROVE pARK (PROJECT NO, 400041)
AND HE~TAGE PARK (PROJECT NO 400042)
I sUMMARyf Th'eCity C°~c~q has'requested m°nthly P!7°gress' rep0~s'°n each oftheSe '/
projectsI ~.i~,.,~:' :7'i:,i! '. i~.:..-.:~i. ~:" ii ~:,,~ .
RECOMMENDATIONi
Receive and file.
BACKGROUND:
The City Council has requested monthly progress reports on the status of Heritage
Park and Cedar Grove Park. As of this date, the parks are proceeding as follows:
Cedar Grove Park (Project No. 400041)
The overall project is approximately 95% complete. Some details of the work are as
follows:
1. Restroom building is 99% complete.
2. Irrigation piping and control wiring is complete.
3. Concrete curbs and asphalt paving for the parking lot are complete.
4. Concrete curbs and walks at the three playground areas are cOmplete.
5. Playground equipmem is complete.
6. Wood fencing is complete.
7. The basketball court and picnic area slabs are poured; trellis columns and
main beams are complete.
8. The streambed/water feature is 99% complete.
9. Soil amendments are complete. Planting of bushes is 80-90% complete.
10. Trees are 100% planted.
11. The project is about 6-8 weeks behind the original schedule due to thirty
days of rain delay and field conditions, and 2-3 weeks of additional work. It
is tentatively anticipated that perimeter landscaping, building and
playground facilities could be completed by mid-April 1998, if there are no
further weather delays.
Due to wet weather, availability of the hybrid Bermuda stolons for the
playing fields is delayed until late April, provided there is no additional rain
delay, which will cause the 90-day maintenance period to run through the
end of July.
Heritage Park ~roject No. 400042)
1. Over excavation and rough grading are in progress.
2. Numerous building materials have been submitted for review.
3. Progress has been slow due to E1Nino rains. Project is approximately 35
days delayed due to rain.
Acting Director, Parks and Recreation Services
cc: File G. 1
W,t MAH/WAH/:sc/Progress Report 3/11/1998