PROGRESS REPORT ON CEDAR GROVE PARK (PROJECT NO. 400041)
AND HERITAGE WAY PARK (PROJECT NO 400042)
RECOMMENDATION:
Receive and file.
BACKGROUND:
The City Council has requested monthly progress reports on the status of Heritage
Way Park and Cedar Grove Park. As of this date, the parks are proceeding as
follows:
Cedar Grove Park .(Project 400041)
1. Grading is complete.
2. Restroom walls are' complete; roof flaming in progress.
3. Concrete slab for basketball court is poured.
4. Concrete curbs for 2 of 3 play areas are completed.
5. Store drain pipe is completed.
6. Masonry columns for the trellis are in progress.
7. Sewer and water work is in progress and slightly behind schedule, due to extensive
plan check review by h-vine Ranch Water Department post building permit.
8. The footings and posts for the footbridge at the playground are completed. Framing
for the bridge is in progress.
,
Grading and irrigation are about two weeks behind schedule. The delay in
completion of the grading was due to the moving of the amphitheater to the
southwest to improve the visibility from the parking lot. All other work is on
schedule.
10. Overall, the project is approximately 20% complete at this date.
Heritage Way Park (Project No: 400042).
1. The Architect completed the plans and submitted for a second plan check.
2. Plan check was completed 9/5/97, and plans were returned to the Architect.
3. Contract and Bid forms were submitted to the City Attorney for review.
4. Plans should be ready to issue for bid in the next 2-3 weeks.
'