HomeMy WebLinkAbout06 AWARD CONTRACT FOR ARMSTRONG AVE & WARNER AVE EXTENSIONAgenda Item 6
AGENDA REPORT Reviewed:
0 City Manager
Finance Director
MEETING DATE: APRIL 15, 2014
TO: JEFFREY C. PARKER, CITY MANAGER
FROM: DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS /CITY ENGINEER
SUBJECT: AWARD CONTRACT FOR THE ARMSTRONG AVENUE AND WARNER
AVENUE EXTENSION PHASE 2 STREET IMPROVEMENTS
CONSTRUCTION PROJECT, CIP NOS. 70201 & 70202
SUMMARY
With the substantial completion of the Phase I grading and storm drain installation, staff is
recommending that the City Council award the construction contract for the Armstrong
Avenue and Warner Avenue Extension Phase 2 Street Improvements to the lowest
responsive /responsible bidder, R.J. Noble Company, and appropriate funding for
construction, construction engineering, management and inspection.
RECOMMENDATION
It is recommended that the City Council:
1. Appropriate $700,000 from unencumbered Irvine Ranch Water District
Reimbursement (Fund 200), $4,200,000 from unencumbered Community
Facilities District 06 -01 Construction Fund (Fund 434), $500,000 from
unencumbered Community Facilities District 06 -01 Annexation Construction
Fund (Fund 438), $1,000,000 from unencumbered Street Lighting Fund (Fund
142), in addition to funds already appropriated in the amount of $7,100,000 from
TSIA and Measure M2 RCP for a total project appropriation of $13,500,000; and
2. Award the construction contract for the Armstrong Avenue and Warner Avenue
Extension Phase 2 Street Improvements Construction Project, CIP Nos. 70201 &
70202 to the lowest responsive /responsible bidder, R.J. Noble Company in the
amount of $10,552,962.61 and authorize the Mayor and the City Clerk to execute
the contract documents on behalf of the City and authorize the City Manager to
expend said funds in an amount not -to- exceed $13,500,000 for construction, dry
utility fees, geotechnical engineering, construction engineering, management and
inspection.
Award Contract for Armstrong Avenue & Warner Extension Street Improvements Project
April 15, 2014
Page 2
FISCAL IMPACT
With the recommended action, sufficient funds will be available to cover project
expenditures. The project is funded through a combination of sources that includes Santa
Ana - Tustin Transportation System Improvements Authority (TSIA), Measure M2 Regional
Capacity Program (RCP), Irvine Ranch Water District (IRWD) Capital Facilities
Reimbursement, Community Facility District (CFD) 06 -01 Construction and Annexation,
and Street Lighting funds.
The original funding approach, as approved in the Fiscal Year 2013 -2014 CIP budget,
included $9,300,000 in Land Proceeds and $4,000,000 in MCAS Backbone Fees. MCAS
Backbone Fees have been used to fund the sewer realignment in Tustin Ranch
Road / Barranca Parkway and the Barranca Parkway Channel undergrounding and street
widening improvement. Staff is also reserving a major portion of Land Proceeds pending
resolution with the California Department of Finance (DoF) to finalize any outstanding
obligation necessary to further absolve the City's MICAS Tax Allocation Bond Proceeds
(MCAS TAB) held in abeyance by the State. As a result, staff is recommending alternative
appropriations as a means to move forward with the Phase 2 improvements of Armstrong
and Warner Avenues and allow the City to fulfill its obligations to the Orange County
Transportation Authority and The Irvine Company.
Project expenditures include:
Construction Contract ........ ............................... $ 10,552,962.61
Dry Utility Fees ................. ............................... $ 600,000.00
Geotechnical Engineering .. ............................... $ 195,000.00
Construction Engineering ... ............................... $ 250,000.00
Construction Management and Inspection ............. $ 430,000.00
Contingency ..................... ............................... $ 1,472,037.39
TOTAL $ 13,500,000.00
The table on the following page summarizes the appropriations approved in the Fiscal
Year 2013 -2014 CIP budget and the proposed appropriations necessary to move forward
with the project.
THIS SPACE INTENTIONALLY LEFT BLANK
Award Contract for Armstrong Avenue & Warner Extension Street Improvements Project
April 15, 2014
Page 3
Armstrong Avenue and Warner Avenue Extension
Phase 2 Street Improvements
Fund Description
FY 2013 -2014 CIP
Budget Allocation
Proposed Project
Funding
TSIA
$
3,000,000
$
3,000,000
Measure M2 RCP'
$
4,100,000
$
4,100,000
IRWD Reimbursement
$
-
$
700,000
CFD 06 -1 Construction
$
-
$
4,200,000
CFD 06 -1 Annexation
$
-
$
500,000
Street Lighting Fund
$
-
$
1,000,000
Land Proceeds
$
9,300,000
$
-
MCAS Backbone Fees
$
4,000,000
$
-
TOTAL
$ -
20,400,000""
$
13,500,000
* Total reimbursement up to $4,400,000 based on actual eligible expenses.
* *Includes $5,000,000 reimbursement to The Irvine Company for construction of Warner Avenue between Legacy Road
and Tustin Ranch Road.
The appropriation from the Street Lighting Fund will be transferred to the Capital
Improvement Fund (Fund 200) and used solely for expenditures related to dry utilities and
will be replenished with MCAS TAB funds when available after resolution with DoF. The
current MCAS TAB fund balance is approximately $32,000,000.
CORRELATION TO THE STRATEGIC PLAN
The construction of Armstrong Avenue and Warner Avenue roadway extension contributes
to the fulfillment of the City's Strategic Plan Goal A: Economic and Neighborhood
Development. Specifically, the project implementation of Strategy 1, which among other
items, is to develop critical phases of Tustin Legacy.
DISCUSSION AND BACKGROUND
On January 7, 2014 City Council approved plans and specifications and authorized the
City Clerk to solicit bids. The Engineer's Estimate $13,200,000.
Formal bids were publicly opened on March 4, 2014 and reviewed by Public Works. Ten
(10) bids were received by the noticed deadline and are summarized below by order of
least dollar amount:
• R.J. Noble Company .................. ............................... $ 10,552,962.61
• Palp Inc. dba Excel Paving Company ....................... $ 11,065,912.45
Shawnan ...................................... ..............................$ 11,373,777.70
• All American Asphalt .................. ............................... $ 11,700,397.98
• Hillcrest Contracting ................... ............................... $ 11,710,974.21
• Los Angeles Engineering ........... ............................... $ 12,251,032.75
Award Contract for Armstrong Avenue & Warner Extension Street Improvements Project
April 15, 2014
Page 4
• Environmental Construction, Inc . .............................. $ 12,625,982.34
• The Sun Group ........................... ............................... $ 15,415,093.00
• USS Cal Builders ....................... ............................... $ 15,487,354.00
• Minako America Corporation ...... ............................... $ 16,220,916.00
As is customary, staff has reviewed the references and verified the State Contractor's
License for R.J. Noble Company and has determined that they are in good standing and
current. Furthermore, R.J. Noble Company has been an outstanding contractor for the
City and has successfully completed the Tustin Ranch Roadway Improvements, the 20"
Sewer Realignment in Tustin Ranch Road / Barranca Parkway and the Barranca Channel
and Street Improvement currently under construction.
It is recommended that the City Council appropriate the supplemental funding and award
the construction contract to the lowest responsive /responsible bidder, R.J. Noble
Company, and authorize the Mayor and the City Clerk to execute the contract documents
on behalf of the City.
Stack, P.E.
Public Works /City Engineer
Attachment: Location Map
SACity Council Items\2014 Council Items \04- 15- 2014Wward of Contract for Armstrong & Warner Extension\Hward of Contract for
Armstrong Avenue (CIP 70201) and Warner Avenue (CIP 70202) Extension Phase 2 Street Improvements SC_dss3.docx
ARMSTRONG AVENUE AND WARNER AVENUE EXTENSION
PHASE 2 STREET IMPROVEMENTS
LOCATION MAP
qF PROJECT
1�(LOCATIONJy���
THE IRVINE CO. , CITY OF
c��y•. �4 �-'��� TUSTIN