HomeMy WebLinkAbout10 PROJECT 400041,2 07-21-97AGENDA
NO. 10
7-21-97
I nte r-C o
DATE: July 14, 1997
TO:
FROM'
SUBJECT:
William A. Huston, City Manager
Community Services Department
PROGRESS REPORT ON CEDAR GROVE PARK (PROJECT 400041)
AND HERITAGE WAY PARK (PROJECT NO, 400042)
~IJIVIMARY: The City Council has reqUested momhly progress reports on' each of these
projects, · '~ ' - ' : '- . : ',"~ .'..":'.'~,': ::., ':~. ~ .. ~:~::'". :~ i
RECOMMENDATION:
Receive and file.
BACKGROUND:
The City COuncil has requested momhly progress reports on the status of Heritage
Way Park and Cedar Grove Park. AS of this date, the 'parks are proceeding as
follows:
Cedar Grove.Park
1. Building permit has been obtained.
2. Notice to Proceed has been issued as of July 8, 1997.
3. The Contractor has mobilized the grading equipment onto the site.
4. Constmcti°n water meter has been obtained from the IRWD.
5. Protective fencing is in progress along the horse/bike trail at the perimeter of the
site.
.6.
.
Site. survey by the Contractor is completed.
Shop drawings are being processed. The first 11 submittals were received by
RIM, and we have akeady processed eight of them
Grading will start on Monday, July 14, 1997.'
HeritaGe Way Park
1. RIM submitted 50% complete working drawings on July 3, 1997, approximately
one week ahead of schedule.
.
Copies of these plans were routed to each department normally involved with plan
check, including the Police Department. Comments are due back by the end of
the day, July 16m.
3. Attached is a copy of the Project Schedule. The work is prOceeding per the
Schedule.
l~ike H;nley --/~
Director of Community Sery.~
Attachment
cc: File G. 1
Wd/MAH/WAH/:scJProgress Report July 14, 1997
Fentative Project S lule
December 16, 1996
(Revised February 23, 2 99 7)
(Revised April 22, 199 7)
ItERITAGE WAY NEIGltBORHOOD PARK
City of Tustin
PHASE DESCRIPTION
I. i%L4,STER PLAN
A. Submit revised DDR to City
B. Obtain Aerial Topo
t
DESIGN DEVELOPMENT
A. Submit Tot Lot/Group Picnic Area and Rollerhockey Area to.City
for.review and approval.
B. Obtain C. ity approval
III. · CONSTRUCTION DRAWINGS
A. Submit Drawings at 50% completion
B. City Review (1 week)
C. Submit Drawings at 100% completion
D..City Review (1 week)
E. Submit for signature
IV,
ADVERTISE FOR BID
A.' Award Bid
START CONSTRUCTION
(90 calendar days)
CONSTRUCTION COMPLETE/MAINTENANCE
PARK OPEN '
TARGET DATE
April 25, 1997 -
May 2
May 16
May 23
July 11
July 18
Aug 8
Aug 15
Aug 22
Aug
Sept
Oct -. Dec 1997.
Jan - March 1998
Aprill 1998
Heritage Park Schedule/615 -02-3
:
Page 1