Loading...
HomeMy WebLinkAboutC.C. 03 2ND G.P. EXT. 05-18-92AG ijA ' milti v- /J, .e CONSENT CALENDAR NO. 3 5-18-92 MAY 18, 1992 10• WILLIAM A. HUSTON, CITY MANAGER FROM: COMMUNITY DEVELOPMENT DEPARTMENT Zr3IIJBJECT: SECOND GENERAL PLAN EXTENSION REQUEST RECOMMENDATION It is recommended that the City Council adopt Resolution No. 92-60 requesting that the State Office of Planning and Researchapprove a second 12 -month extension for City preparation and adoption of the updated General Plan. BACKGROUND AND DISCUSSION California State Law requires each City to adopt a comprehensive General Plan for the physical development of the City and any land outside its boundaries which bears a relationship to its planning activities. In response to the need for a more current General Plan, the Tustin City Council authorized a program as part of the 1990-91 budget and on February 4, 1991 approved a contract with Cotton/ Beland /Associates to undertake a comprehensive update of the General Plan. The General Plan was expected to be completed and approved by the City within 18 to 24 months. During this period, Section 65361 of the California Government Code authorizes the Office of Planning and Research (OPR) to grant local jurisdictions up to a one-year extension of time, with the possibility of an additional one year extension, if needed, in order to complete and adopt revisions to the mandatory elements of the General Plan. The intent of such extensions enables a jurisdiction to continue to process all project applications for subdivision, rezoning, use permits and variances where the land uses are consistent with an Interim Land Use Policy, without the fear of litigation. On May 6, 1991, the City Council adopted Resolution No. 91-44 requesting that the Director of the State Office of Planning and Research approve a twelve month extension for City preparation and adoption of an updated General Plan. At that time, the City Council made findings to justify the granting of an extension. These findings were found acceptable by the State, and the extension was granted on June 19, 1991. Since that time, the City has not completed the General Plan Update, but has made substantial progress toward its adoption. For City Council Report Resolution No. 1060 May 18, 1992 Page 2 example, the City has conducted public workshops, distributed a general plan questionnaire citywide, completed the preparation of technical memoranda for each of the elements, and reviewed alternate land use plans and goals and policies. The City expects that tasks will be completed and the document adopted in fall 1992, or no later than the end of 1992. In order to be eligible for a second extension, the City must submit an application that includes the following four items: 1) General Plan Extension Application Form 2) Resolution of the Legislative Body, adopted after a public hearing, stating findings/reasons why the General Plan needed to be revised and indicating that substantial progress has been made toward adoption of the revised General Plan since the granting of the first extension 3) Detailed Budget and Schedule for Plan Preparation and Adoption 4) Proposed Interim Policies and Procedures As was done for the first extension request, staff has prepared a resolution with findings based on the reasons for the requested second extension. In addition to the extension application proposal, an interim discretionary land use policy was prepared as required and included as Exhibit A of the attached resolution. This interim policy sets forth the land use policies that would be used by the City in evaluating a project's land use consistency with the goals of the City. Projects which are found to be inconsistent with these policies could not be approved by the City during the granted second extension period. The Interim Policy is basically no different than the City's current development policies and is similar to the policy adopted with the first extension. CONCLUSION Staff recommends that the City Council adopt Resolution No. 92-60 requesting a second 12 -month General Plan Extension and approving the Interim Discretionary Land Use Policy. r Scott Reekstin Cfrristine A. Shing ton Assistant Planner Assistant City Manatjer CAS:SR:kd/gp2exten.ccr Attachment: Resolution No. 92-60 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 92-60 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA REQUESTING A SECOND EXTENSION OF TIME TO REVISE THE CITY OF TUSTIN GENERAL PLAN. The City Council of the City of Tustin does hereby resolve as follows: Whereas, the various elements of the General Plan of the City of Tustin were adopted as follows: Housing, 1978; Land Use, 1973; Noise, 1975; Open Space /Conservation, 1972; Recreation, 1972; Circulation/ Scenic Highways, 1970; Safety, 1978 and have been expanded and amended from time to time to include adoption of various state -mandated and discretionary elements; and Whereas, the City of Tustin faces significant and continued growth pressures which require the updating of the City General Plan in order to maintain internal consistency among the elements and to serve as a useful tool to plan for and manage growth into the next century; and Whereas, recognizing that preparation of a General Plan is a multi-year endeavor, 1990-91 costs for preparation were budgeted at $102,500 and 1991-92 costs at $269,200; and as part of the City's three-year financial plan, the remainder of the funding is to be allocated to the 1992-93 budget; and Whereas, the City Council authorized the City Manager to execute a contract with Cotton-Beland Associates, Inc. on February 4, 1991 which would produce a revised General Plan in approximately 18 to 24 months; and Whereas, on May 6, 1991 the City Council requested that the Director of the California Office of Planning and Research grant an extension of time for a 12 (twelve) month period to complete the revision of all of the elements of the General Plan as allowed by law, knowing that the program would realistically take 18 to 24 months; and Whereas, the Director of the California Office of Planning and Research granted the request for an extension on June 19, 1991, which will expire on June 18, 1992; and Whereas, with the assistance of consultant services the City anticipates adopting an updated General Plan by 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17! 18 19 20 21 22 23 24 25 26 27 28 Resolution No. 92-60 Page 2 the end of 1992, within our original 18 to 24 month time frame; and Whereas, pursuant to Section 65361 of the California Government Code, the Director of the Office of Planning and Research of the State of California has the authority to grant a maximum of two extensions of time for completion or revision of the mandatory elements of the General Plan; and Whereas, the City Council finds that, pursuant to California Government Code Section 65361(a)(2), the following reasons exist to justify an extension of time to prepare timely revision to the elements of the General Plan: a. The City of Tustin is a city which has experienced rapid growth through development and annexations. Due to statutory -imposed processing deadlines, and to avoid imposing a development moratorium, a large part of the City's available in-house staff resources have been devoted largely to current planning. b. Staff turn -over has affected the continuity of past general plan preparation activities in the City. C. Despite continued efforts by the City of Tustin to update the General Plan over the years to include various state -mandated elements and to frequently revise the Housing Element (City was first city in Orange County with a 1989 Housing Element), the City did not previously have the financial resources to comprehensively update the General Plan. d. Due to rapid growth, the General Plan is in need of significant updating to maintain internal consistency among the elements and to serve as a useful tool to plan for and manage growth. e. The updating of the General Plan is an extensive, comprehensive process involving significant analysis, review, and public participation that requires more than 12 (twelve) months to accomplish. 1 2 3 4 5 6 7 8 9 10 11 121 V 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 Resolution No. 92-60 Page 3 f. During the period of the first extension, the City has made significant progress toward the adoption of the revised General Plan by conducting public workshops, distributing a citywide questionnaire, completing the preparation of technical memoranda for each of the elements, and reviewing alternate land use plans and goals and policies. g. The City has an adopted budget through the 1992-1993 fiscal year for the General Plan Update and has hired a consultant to prepare the Update. h. The General Plan Update is scheduled to be completed by the end of 1992. NOW, THEREFORE, Be It Further Resolved By the City Council of the City of Tustin as follows: 1. Based on the foregoing, the City of Tustin requests that the Director of the California Office of Planning and Research grant a second extension of time for a 12 -month period to complete the revision of all of the elements of the General Plan, as set forth on the Request for General Plan Extension attached hereto and incorporated herein by reference. 2. During the period of the second extension, the City of Tustin will follow the policies and procedures set forth in Exhibit A attached hereto. PASSED AND ADOPTED by the City Council of Tustin this 18th day of May, 1992. MARY WYNN, City Clerk LESLIE ANNE PONTIOUS, Mayor 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15� 16� 17 18 19 20 21 22 23 24 25 26 27 28 EXHIBIT A RESOLUTION NO. 92-60 INTERIM DISCRETIONARY LAND USE POLICY 1. The City, including the City Council, Planning Commission, and all other boards delegated individual land use decision-making authority under City ordinances, shall apply this Interim Discretionary Land Use Policy to review and process all discretionary land use projects. 2. During the effective period of this extension, no discretionary permits (parcel maps, tentative subdivision maps, zone changes, special use permits, variances, etc.) shall be approved by the City unless the City Council, and all other applicable decision-making authority under City ordinances, make formal findings, based on substantial evidence, that the proposal is consistent with the goals, policies and programs of the existing General Plan and the zoning and subdivisions ordinances of the City of Tustin; with the exception that properties outside the City limits, which are not currently within the City's sphere of influence, shall be processed consistent with the goals and policies of the City's General Plan. 3. All discretionary permits and projects shall be consistent with the adopted Housing Element of the General Plan. 4. Section 9213(e) of the Tustin City Code states that any territory included within the City, which, at the time of its annexation does not have a zone designated by prezoning, shall be designated by the zone which the territory bore under the County Zoning Ordinance, provided there is a district bearing the same designation. Any land which does not bear a designation which is also contained in the City Code, shall be designated as being in the "U" - Unclassified District. All properties with the zoning designation of Unclassified shall first secure a use permit prior to any new uses being established. 5. The City shall observe and meet CEQA requirements for Environmental Impact Report preparation, review and certification. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 171 18 19 20 21 22 23 24 25 26 27 28 Exhibit A - Resolution No. 92-60 Interim Discretionary Land Use Policy Page 2 6. The City shall observe and meet any applicable requirements for minimum processing time for the General Plan revision. 7. All draft elements and draft environmental documents shall be submitted to OPR for review and comment at least thirty (30) days prior to the City Council taking final action on the General Plan revision. 8. The City shall submit a copy of the final General Plan and the resolution of adoption for the General Plan to OPR upon adoption by the City Council. SR:kd\92-60