HomeMy WebLinkAboutC.C. 13 ASPHALT OVLAY 05-04-92CONSENT CALENDAR NO. 13
5-4-92
n e r 0 M
)ATE: MAY 41 1992
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR ASPHALT CONCRETE REHABILITATION AND
OVERLAY PROJECT, 1991-92 FY, PHASE I (P.W. FILE #R-92-3)
RECOMMENDATIONS:
It is recommended that the Tustin City Council, at their meeting of
May 4, 1992, award the contract to Boral Resources, Inc. in the
amount of $359,782.96 for the subject project.
BACKGROUND:
Six bids were received on April 29, 1992 and are summarized as
follows:
Boral Resources, Inc., Pomona .................... $359,782.96
R. J. Noble Company, Orange ....................... 370,664.41
Excel Paving Co., Long Beach ..................... 394,975.87
Excalibur Contracting, Inc., Lake Forest 395,903.92
All American Asphalt, Corona ..................... 399,487.90
Sully -Miller Contracting Co., Orange ............. 413,223.40
The low bid is 21.6% below the engineer's estimate of $459,029.10.
The current budget provides $1,011,000 for major street maintenance
programs for 1991-92 FY. Therefore, $651,217.04 will remain for
Newport Avenue overlay project, 1991-92 FY, Phase II and other
street rehabilitation projects.
Robert Ledendecker Wisam Altowaiji
Director of Public Works/City Engineer Associate Civil Engineer
RL:WA:ccg:phase I