HomeMy WebLinkAbout05-ATTACHMENT 2 (COOPERATIVE AGREEMENT NO. D02-119-2)ATTACHMENT 2
Cooperative Agreement No. D02 -119 -2
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
Amendment No. 2 to Cooperative Agreement D02 -119
This Amendment No.
2 to Cooperative Agreement
D02 -119,
hereinafter referred to as
"AMENDMENT NO. 2,"
is entered into and effective as of
_ of
, 2015, by and
among
AND
AND
ORANGE COUNTY FLOOD CONTROL
DISTRICT, a body corporate and politic in the
State of California, hereinafter referred to as
"DISTRICT,"
COUNTY OF ORANGE, a political subdivision
of the State of California, hereinafter referred
to as "COUNTY,"
CITY OF TUSTIN, a municipal corporation,
hereinafter referred to as "CITY,"
which are sometimes individually referred to as "PARTY," or collectively as "PARTIES."
RECITALS
WHEREAS, DISTRICT, COUNTY and CITY entered into that certain Joint Cooperative
Agreement (D02 -119) dated March 11, 2003, hereinafter referred to as the "Agreement," which
established that the CITY would be responsible for constructing infrastructure to support the future
development of the former Marine Corps Air Station Base (also known as the "Tustin Legacy ").
The Agreement required the CITY, among other things, to design and construct segments of the
Peters Canyon Channel immediately adjacent to Tustin Legacy to satisfactorily convey 100 year
storm flows ( "PETERS CANYON CHANNEL IMPROVEMENTS "). The Agreement also required
the CITY to establish how its infrastructure obligations under the Agreement would be scheduled,
107146.1 1 Page 1 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
engineered, financed, operated and maintained;
WHEREAS, on June 8, 2004 the PARTIES entered into that certain Amendment No. 1 to
Joint Cooperative Agreement ( "Amendment No. 1 ") which revised the Agreement to tie
completion of the PETERS CANYON CHANNEL IMPROVEMENTS to the future development of
Tustin Legacy, specifically requiring the CITY to commence construction on the PETERS
CANYON CHANNEL IMPROVEMENTS prior to its issuance of certificates of use and occupancy
for the 1001st residential unit, or on more than 270 acres of the land which drains into Peters
Canyon Channel, whichever occurs first;
WHEREAS, the CITY has approved construction of residential units within Tustin Legacy
making issuance of certificate of occupancy for more than 1001 residential units imminent, which
would trigger CITY's requirement to commence construction on the PETERS CANYON CHANNEL
IMPROVEMENTS;
WHEREAS, construction of the PETERS CANYON CHANNEL IMPROVEMENTS in
accordance with the Agreement, as amended, would interfere with the time - sensitive Peters
Canyon Channel Pipeline water quality project work ( "Pipeline Project ") in the same vicinity. A
delay in the Pipeline Project schedule may jeopardize the OCTA Measure M2 Tier 2 environmental
grant funding it has been awarded, and greatly increase its overall Project costs due to necessary
coordination; and,
WHEREAS, the PARTIES mutually desire to further amend the Agreement to defer
construction of PETERS CANYON CHANNEL IMPROVEMENTS in accordance with the terms
herein to accommodate the construction of the Pipeline Project.
107146.1 Page 2 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
NOW, THEREFORE the PARTIES hereto agree as follows:
1. RECITALS
The provisions, definitions, and statements of intentions set forth in the recitals above are
incorporated into this AMENDMENT NO. 2.
2. DEFINITIONS
All capitalized terms used and not otherwise defined in this AMENDMENT NO. 2, but
defined in the Agreement, as amended by Amendment No. 1, shall have the meanings set
forth in the Agreement, as amended.
3. REVISIONS
a) Subsection 5.3.3.4 is deleted in its entirety and hereby substituted with the following:
5.3.3.4 The CITY shall ensure that construction of the PETERS CANYON CHANNEL
IMPROVEMENTS (excluding any PETERS CANYON CHANNEL IMPROVEMENTS which
are obligations of the COUNTY pursuant to Section 2.2 of the Agreement) is completed at
no cost to the DISTRICT or to the COUNTY. A contract for PETERS CANYON CHANNEL
IMPROVEMENTS shall have been awarded for and construction commenced prior to the
issuance of certificates of use and occupancy for the 12015' residential unit or certificates
of use and occupancy on more than 270 acres of land within the Master Developer
Footprint of the New Development, whichever occurs first. Once construction of PETERS
CANYON CHANNEL IMPROVEMENTS commences, the CITY shall make every effort to
ensure Developer's completion of PETERS CANYON CHANNEL IMPROVEMENTS within
fifteen months after award of the contract. "New Development" includes all land at Tustin
Legacy that drains to Peters Canyon Channel, as shown on Exhibit B.
107146.1 Page 3 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (FO6), and Peters Canyon Bikeway
b) All references in the Agreement, as amended, to Public Facilities and Resources
Department (PFRD) and /or Resources and Development Management Department
(RDMD) are changed to OC Public Works (OCPW).
4. AUTHORITY
The PARTIES to this AMENDMENT NO. 2 represent and warrant that this AMENDMENT
has been duly authorized and executed and constitutes the legally binding obligation of
their respective organization or entity, enforceable in accordance with its terms.
5. NO OTHER CHANGES; RATIFICATION
Except as expressly set forth in this AMENDMENT NO. 2, each and all of the terms,
conditions and covenants in the Agreement as amended by Amendment No.1 shall remain
unchanged and in full force and effect, and are hereby ratified by the Parties.
6. COUNTERPARTS
This AMENDMENT NO. 2 may be executed in counterparts, each of which shall be
deemed an original, but all of which together shall constitute one and the same document.
107146.1 Page 4 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
IN WITNESS WHEREOF, each PARTY hereto has executed this AMENDMENT NO. 2 by
its duly authorized representatives as of the date set forth above.
Date:
Date:
APPROVED AS TO FORM:
Office of the County Counsel
Orange County, California
0
Deputy
Date:
ORANGE COUNTY FLOOD CONTROL DISTRICT
a body corporate and politic
By
Chairman of the Board of Supervisors
Orange County, CA
SIGNED AND CERTIFIED THAT A COPY OF
THIS AGREEMENT HAS BEEN DELIVERED
TO THE CHAIR OF THE BOARD PER G. C.
Sec 25103, Reso 79 -1535
Attest:
Clerk of the Board of Supervisors
Orange County, California
Page 5 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
COUNTY OF ORANGE
a political subdivision of State of California
Date: By
Chairman of the Board of Supervisors
Orange County, CA
Date:
APPROVED AS TO FORM:
Office of the County Counsel
Orange County, California
0
Deputy
Date:
SIGNED AND CERTIFIED THAT A COPY OF THIS
AGREEMENT HAS BEEN DELIVERED TO THE
CHAIR OF THE BOARD PER G. C. Sec 25103, Reso
79 -1535
Attest:
Clerk of the Board of Supervisors
Orange County, California
Page 6 of 7
Project: Barranca Channel (F09) - Armstrong Amendment No.2 to Agreement D02 -119
Crossing, Armstrong Storm Drain, Peters Canyon
Channel (F06), and Peters Canyon Bikeway
Date:
Date:
APPROVED AS TO FORM:
City Attorney
Page 7 of 7
CITY OF TUSTIN,
a municipal corporation
M.
06
Mayor, City of Tustin
Clerk