DATE'
OCTOBER 7, 1996
Inter-Com
TO:
FROM:
SUBJECT:
WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/WATER SERVICES DMSION
AWARD OF CONTRACT FOR WATER MAIN REPLACEMENTS, CITY PROJECT
NOS. 600123 AND 600124
RECOMMENDATION:
It is recommended that the Tustin City Council, at their regular meeting of October 7, 1996, award the
contract for the subject project to R.L.T. Construction, Inc. of Anaheim, California, in the amount of
$560,489.00.
FISCAL IMPACT:
The amount of this contract is $560,489.00. There is currently $650,000 of Capital Improvement Program
funding allocated for these projects in the FY 1996/97 Water Service Capital Improvement Program
Budget.
BACKGROUND:
Bids were opened on September 19, 1996, for subject project and 16 bids were received as follows:
1. RLT Construction, Inc.
2. Zarco Construction Co.
3. Steve Casada Construction
4. Atlas Allied, Inc.
5. John T. Malloy, Inc.
6. B.R. Day Construction
7. G.R. McKervey, Inc
8. Elser Constructors, Inc.
$560,489.00
$561,005.00
$570,436.60
$568,177.80
$626,057.50
$669,516.00
$669,972.00
$670,011.02
0.9/23/96 Tustin City Council Recommendation - Phase I, Task 7 Pipeline Award - R.L.T. Construction.doc
AWARD OF CONTRAC2 . oR WATER MAIN REPLACEMEN~I o, CITY PROJECT NOS. 600123
AND 600124
October 7, 1996
Page 2
9. Trautwein Construction
10. Terra-Cai Construction
11. R & L Sewers, Inc.
12. Wayne Perry, Inc.
13. S.J. Burkhardt, Inc
14. Byron L. Crume, Inc.
15. So. Ca. Underground Const.
16. Savala Construction Co.
$683,793.60
$689,8O8.00
$729,945.39
$734.594.00
$790,440.16
$815,179.25
$834,958.40
$844,239.14
The low bid by RLT Construction, Inc. is 12.0% under the engineer's estimate of $637,000.00.
The Contractor's references have been verified and their past job performances are satisfactory.
DISCUSSION:
This project consists of replacing old deteriorated city water mains in Linda Lane/Laurie Lane/Laurinda
Way, Clarissa Lane, Arbolada Way/Fiesta Way, Norwood Park Place (Prospect to Livingston), Bigelow
Park Drive, Livingston Street, Kirk Avenue/Dali Lane/Norwood Park Place, and Holt Avenue.. These
water mains will improve water system supply and circulation and reduce maintenance and repair costs in
these areas.
Following is the anticipated schedule for completion of the project:
Award of Contract ........................................................... 10/7/96
Begin Construction ........................................................... 11/12/96
Complete Construction .................................................. 04/28/97
Director of Public Works/City Engineer
TS :GRV:jtm
Gary-R. Veeh
Water Services Manager
August 1, 1996 Tustin City Council Recommendation - Phase I, Task 7 Pipeline Award - R.L.T. Construction.doc