HomeMy WebLinkAboutRPT 4 GRADE SEP'S 12-21-92REPORTS NO. 4
12-21-92
AGENE)A
'ATE: DECEMBER 21, 1992
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
FUTURE EDINGER AVENUE GRADE SEPARATIONS AT TUSTIN RANCH ROAD,
SUBJECT: AT RED BILL AVENUE AND NEWPORT AVENUE EXTENSION TO EDINGER
AVENUE
RECOMMENDATIONS:
That the Tustin City Council approve the following:
1. Reactivate the Tustin Ranch Road extension project
(Walnut Avenue to Edinger Avenue) to pursue a roadway
design including conceptual/preliminary design of the
grade separation structure and access ramps at Edinger
Avenue based upon and coordinated with the Marine Corps
Air Station Base Reuse Plan.
2. At the completion of the Moulton Parkway (Edinger Avenue)
Super Street EIR, evaluate the Red Hill Avenue conceptual
overpass alternatives as presented -and proceed with a
formal project as desired.
3. Negotiate with Catellus Development to accelerate the
plan preparation for both Phase I and Phase II of the
Newport Avenue extension.
BACKGROUND
The City Council, at their meeting of December 7, 1992, requested
staff to prepare a status update and suggested actions on three key
roadway improvements within the City:
1. Extension of Tustin Ranch Road southerly from Walnut
Avenue to Edinger Avenue inclusive of a grade separation
over the AT&SF Railroad Tracks, Flood Control Channel and
Edinger Avenue with access ramps to and from Edinger
Avenue. Additionally, the further extension of Tustin
Ranch Road to Barranca Parkway at the Von Karmon Avenue
intersection.
2. A grade separation of Red Hill Avenue at both Edinger
Avenue and the AT&SF Railroad/Flood Control Channel.
3. The extension of Newport Avenue southerly from its
current terminus to Edinger Avenue as an underpass below
the AT&SF Railroad and Flood Control Channel.
It was the City Councils desire to pursue and complete the
environmental documentation and the preparation of construction
drawings so that these projects would be shelf ready in the event
any outside funding sources would become available.
Future Edinger Avenue Grade Separation
December 21, 1992
Page 2
DISCUSSION:
Each of the identified projects will be discussed individually as
follows:
TUSTIN RANCH ROAD
This project will consist of the construction of a six -lane major
arterial highway between Walnut Avenue and Edinger Avenue with a
bridge structure spanning the Orange County Flood Control Channel,
AT&SF Railroad tracks and Edinger Avenue. The roadway improvements
would initially terminate southerly of Edinger Avenue and include
access ramps both to and from Edinger Avenue. Ultimately, it is
planned to extend Tustin Ranch Road southerly from Edinger Avenue
to Barranca Parkway through the Marine Corps Air Station (MCAS) to
align with Von Karmon Avenue. This extension of Tustin Ranch Road
to Barranca Parkway will be studied and included with the Base
Reuse Plan, which is currently in progress.
The City was previously proceeding with the environmental
documentation and plan preparation for the initial extension of
Tustin Ranch Road from Walnut Avenue to Edinger Avenue inclusive of
the grade separation and interchange ramps to Edinger Avenue prior
to the announcement of the MCAS Base closure. This design was
based upon the concept of minimum impact to the MCAS military
reservation per previous discussions with the military and economic
reasons. After the announcement of the base closure and at the
recommendation of staff, the City Council, at their meeting of
February 3, 1992, put the environmental document presentation and
plan preparation of the Tustin Ranch Road facilities on hold until
such time as the Base Reuse Plan had progressed to a point where it
could be determined what areas would be available for road
construction without impacting any remaining MCAS facilities.
At this time staff suggests that the Tustin Ranch Road project be
reactivated to pursue a roadway design including
conceptual/preliminary design of the grade separation structure and
access ramps to and from Edinger Avenue. This would also be a
benefit to -the Base Reuse Plan and the MCAS so as to coordinate
access for the remaining base facilities such as housing, etc.
There is currently $231,800.00 budgeted in the 1992-93 Capital
Improvement Program which could be applied to the reactivation of
this project. - The total estimated environmental document
preparation and engineering design cost is $500,000 to $600,000
resulting in an unbudgeted amount of approximately $368,200.
RED HILL AVENUE
This project will conceptually consist of one grade separation
structure over Edinger Avenue, the AT&SF Railroad Tracks and the
Flood Control Channel and would consist of ramps for the northbound
access from Red Hill Avenue to Edinger Avenue and access to
southbound Red Hill from Edinger Avenue and a new street system for
Future Edinger Avenue Grade Separation
December 21, 1992
Page 3
access to Edinger Avenue from both northbound and southbound Red
Hill Avenue.
This intersection study is being included within the Moulton
Parkway (Edinger Avenue) Super Street Environmental Document on a
conceptual basis only as it is not intended to be included within
the current super street construction project. The Moulton Parkway
Environmental Document is being prepared by the County and is
scheduled for completion in fall of 1993. At that time, after the
project impacts have been evaluated by the City and if found to be
acceptable, it is suggested that the project be formalized with a
final environmental document and that the City proceed with final
construction drawings and right-of-way acquisition as funding
becomes available.
The estimated cost of final environmental documentation and
engineering design of this project ranges from $900,000 to
$1,300,000.
NEWPORT AVENUE
This project will consist of the southerly extension of Newport
Avenue from its current terminus to Edinger Avenue as an underpass
below the AT&SF Railroad and Flood Control Channel. This extension
will require the relocation of the northbound Route 55 on-off ramps
and the further southerly extension of Newport Avenue to Valencia
Avenue to accommodate the ramp relocations. Catellus Development
Company is the catalyst for the initiation of this project with
their proposed Pacific Center East Development.
The Newport Avenue project, as it is planned today, is funded by
Development, Redevelopment Agency Funds and any competitive Measure
'M' Funds which may be available.
The first phase of the Newport Avenue extension project is the
Route 55 northbound ramp relocations and the construction of the
Newport Avenue extension between Edinger Avenue and Valencia
Avenue, which is development (Catellus) driven. The second phase
between Edinger Avenue and the current Newport Avenue terminus is
primarily development driven and supported by Redevelopment Agency
Funds which also depends upon development/property improvement to
generate tax increment revenues. The design of improvements for
both Phase I and Phase II has been assigned as a developer
responsibility with the approval of the Pacific Center East
Specific Plan. It is staffs understanding that Catellus does not
envision any major development within Pacific Center East for
another five to seven years, as a result of the current economic
environment.
It is suggested that the City work out a plan with Catellus to
proceed with the preparation of plans, etc. for the required
Newport Avenue improvements so as to accelerate the project once
Future Edinger Avenue Grade Separation
--- December 21, 1992
Page 4
the economy/development industry returns to a favorable status.
The estimated cost of engineering design for both Phase I and II of
this project ranges from $900,000 to $1,300,000.
These three projects are all key elements to the City's north -south
traffic circulation system. In reviewing the potential
construction impacts to existing traffic circulation, it is
suggested that the actual construction/ implementation be pursued in
the following order.
1. Tustin Ranch Road
2. Newport Avenue
3. Red Hill Avenue
Red Hill Avenue will most likely require a complete closure during
certain phases of construction and the existence of the other
roadways would certainly help to minimize any adverse traffic
impacts to the community.
Robert Ledendecker
Director of Public Works/City Engineer
RL:ccg:gradesep