HomeMy WebLinkAboutCC 5 PROJECT 600095C 09-08-92CONSENT CALENDAR NO. 5
9-8-92
DATE: AUGUST 25, 1992
Inter -Com
04t -T.�
WILLIAM A. HUSTON, CITY MANAGER
TO:
FROM:PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS WATER MAIN
SUBJECT: CONSTRUCTION MAIN STREET AT SR -55 FREEWAY, BETWEEN STONEGLASS
AND PASADENA AVENUE (PROJECT NO. 600095C, P.W. FILE NO. W91 -
3C)
RECOMMENDATION
It is recommended that the City Council at their meeting of
September 8, 1992 adopt the attached resolution accepting said work
and authorizing the recordation of the Notice of Completion.
Assuming no claims or stop payment notices are f iled, it is further
recommended that 35 days after the date of recordation of the
notice of completion, that the Council authorize payment of the
final 10% retention amount of $12,338.10. This amount, together
with previous payments of $111,042.90 represents 100% of the final
contract amount.
BACKGROUND
This project encompassed the relocation of water mains on Main
Street at SR -55 Freeway, between Stoneglass and Pasadena Avenue, to
accommodate Caltrans I-5/SR-55 Interchange Project, Stage 3.
The work has been completed to the satisfaction of the Engineering
Division.
The final contract amount for this project is $123,381.00. This
represents a decrease of 0.59 percent from the original contract
amount of $124,107.00. The majority of the cost to relocate water
mains, to accommodate Caltrans I-5/SR-55 Interchange Project Stage
3, will be reimbursed to the City through Caltrans Utility
Agreement No. 12088.
04 -RoSert S. Ledendecker
Director of Public Works/
City Engineer
RSL:kIb:STONEGLA
?&A A-X4�
Nestor Mondok
Assistant Civil Engineer
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16'
17
18
19
20
21
22
23
24
25
26
27
28
RESOLUTION NO. 92-105
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION FOR THE
WATER MAIN CONSTRUCTION ON MAIN STREET AT SR -55 FREEWAY,
BETWEEN STONEGLASS AND PASADENA AVENUE, PROJECT 600095C
WHEREAS, G.R. McKervey, Inc. having a contract with the
City of Tustin to construct the hereinafter described public
work and improvement; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said public improvements
hereinafter mentioned in a manner satisfactory to the City
Council of the City of -Tustin; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinafter more
particularly described in accordance with the provisions of
the contract documents and the notice of completion and
acceptance of said public work and improvement should be filed
and payment of the balance due said contract authorized in
accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Tustin that said public work and improvement be and
the same is hereby accepted. Said public work and improvement
is more particularly described as follows:
The Water Main Construction on Main Street at SR -55
Freeway, between Stoneglass and Pasadena Avenue, Project
No. 600095C
AND BE IT FURTHER RESOLVED that the City Engineer of the
City of Tustin be and is hereby authorized to execute and file
a notice of completion and acceptance of said public work and
improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin on the 8th day of September,
1992.
ATTEST:
City Clerk
Mayor