HomeMy WebLinkAboutRDA ASBESTOS TEST 11-15-93AGENDA
RDA NO. 7
1-15-93
DATE:
NOVEMBER 15, 1993
Inter-Corn
TO: WILLIAM A. HUSTON, CITY MANAGER AND EXECUTIVE DIRECTOR
FROM: COMMUNITY DEVELOPMENT DEPARTMENT
SUBJEC~ INDEPENDENT TESTING LAB AND ASBESTOS CONSULTANT-
TUSTIN CIVIC CENTER EXPANSION/RENOVATION-
................. · (11 I
RECOMMENDATION:
It is recommended that the Redevelopment Agency authorize a change
order in the amount of $5866.48 to finalize the cost of contract
services previously awarded to Wyman Testing Laboratories. Wyman
performed as the Agency's independent testing laboratory and
certified asbestos air monitor in conjunction with the Civic Center
expansion project.
FISCAL IMPACT:
Independent testing services were always anticipated as part of the
Civic Center total projec= budget.
BACKGROUND:
During the August 5, 1991 meeting, the Redevelopment Agency
retained Wyman Testing Laboratories to perform the certified
inspection and material testing for the Civic Center expansion
project. The Agreement fcr Consulting Services dated July 29, 1991
was subsequently executed in the amount of $50,000.
The $50,000 agreement was estimated to include testing services for
both Phase I and II construction. In June 1992, the Agency
authorized a change order in the amount of $13,250 to extend
Wyman's services due to unanticipated soils conditions.
However, so as not to result in construction delays, the Project
Manager had to request services for high strength bolting, soils
testing and concrete tests beyond the additional June 1992 change
order amounts. In addition, the Project Manager had to order
additional soils testing in May of 1993 when the final curb and
gutter work was in progress.
City Council Report
Independent Testing Lab and Asbestos Consultant
Page 2
The outstanding sum due to Wyman as recommended by the Project
Manager is:
Invoice .Amount
Description
92321 (old invoice) $5,298.48 Testing
93260 328.00 Soils
93334 90.00 Report
93119 150.00 Report
Total $5,866.48
Authorization for final payment is now being requested.
Christine ~Shi~gleton//
Assistant City Manag~er
Edward Elowe
Project Manager
CC rpt: br: wyman: EE