RECOMMENDATION
It is recommended the Redevelopment Agency authorize the Assistant
City Manager to negotiate and return to the Agency with an Owner
Participation Agreement to provide a deferred loan of $27,120 to
assist the property owners of 100 West Main Street to renovate and
rehabilitate the existing building pursuant to Agency approved
Design Review 93-012.
FINANCIAL IMPACT
The Town Center Financing Plan, approved by the Redevelopment
Agency on March 4, 1991, identified $200,000 in tax increment funds
from the Town Center Project Area as being available for commercial
rehabilitation projects by Fiscal Year 1993-94. When the Owner
Participation Agreement is returned to the Agency for approval, the
Agency will be required to appropriate $27,120 from the projected
1993-94 Town Center Capital Account for this assistance.
BACKGROUND
In June, 1991, the City received the summary report on The Old Town
Charette. The Charette participants included numerous local
residents and business owners, planning and architectural
professionals as well as city representatives. Its purpose was to
identify strengths and weaknesses within the Old Town area. The
subject building, located at 100 West Main Street (the southwest
corner of Main Street and E1 Camino Real) and referred to in the
Charette as "The Roach Building", was defined as an "onion" by the
participants. "Onions" were those features of the Old Town which
the workshop participants identified as undesirable or in need of
improvement.
The Charette participants developed a "vision" of Old Town which,
among other characteristics, envisioned a village atmosphere, which
utilizes E1 Camino Real as the central corridor and creates and
enhances a pedestrian environment in a manner which capitalizes on
the unique character of Tustin.
Subsequent to the Charette, the Redevelopment Agency sponsored a
Regional/Urban Design Assistance Team (R/UDAT) of the American
Institute of Architects to analyze the findings of the Charette, as
well as the Old Town area as a whole, and to make specific
Redevelopment Agency Report
Agency Financial Assistance
100 West Main Street (Thompson)
October 4, 1993
Page 2
recommendations concerning improvements needed to maintain the
viability and historic nature of Old Town. The R/UDAT, in
answering the question "What can Old Town Be?" provided four
answers:
le
TUSTIN'S HEART: A common center that portrays the image
of what the City and its values are.
·
AN ECONOMICALLY VIABLE PLACE: An area with its own
economic niche in the community, not trying to compete
with other business areas.
·
A PLACE FOR ITS RESIDENTS: An area which recognizes the
importance and integrity of the residential neighborhoods
and provides businesses that serve the Old Town
residents.
·
A PLACE FOR NEW BUSINESSES AND RESIDENTS: An area that
expands its viability and dynamism by attracting new
residential, commercial and office development.
Concerning the subject property, the R/UDAT stated:
"The Roach Building site and the adjacent office court
should be redeveloped according to the following
objectives:
·
Improve the architectural character of the
Main Street/E1 Camino Real intersection.
·
Enhance the identity of Old Town's retail
core."
Jeff and Cherie Thompson have recently purchased the "Roach"
building and have been working with the Community Development
Department to meet the concerns of the Charette and the objectives
of the R/UDAT. They are proposing extensive exterior renovation to
make the building compatible with the Cultural Resources District
and to bring back to Old Town some of the architectural features
which existed in the past. They also are proposing to make
structural and tenant changes in the building to attract retail
users to the first floor storefronts.
The elevations of the building will be redesigned, with modern
adaptations, to be reminiscent of the old brick First National Bank
of Tustin, which previously existed across the street from this
Redevelopment &genc¥ Report
&gency Financial Assistance
100 West Main Street (Thompson)
October 4, 1993
Page 3
building, at the northwest corner of E1 Camino Real and Main
Street. Included in the renovation will the construction of a
focal point two-story corner turret, similar to the one which was
featured on the bank building¥~renovating the windows and doors as
well as covering the exterior walls of the building along E1 Camino
Real and Main Street with a brick veneer. A number of other
improvements are proposed to make the building compatible with the
historic elements of Old Town.
On June 21, 1993, the Redevelopment Agency approved Design Review
93-012 for the renovation of the subject building, as shown in the
attached renderings (Exhibit 1). The Agency also waived the lease
fee for five parking spaces owned by the Agency in the Steven's
Square parking structure.
The property owners have also been working with the City Staff as
part of the City's federally funded Commercial Rehabilitation
Program. Under this program, property owners in the Old Town area
can receive a $10,000 grant to offset design and engineering costs
for rehabilitation and seismic retrofitting work as well as another
$10,000 grant to offset construction costs. Both of these grants
are financed through the Community Development Block Grant (CDBG)
Program.
The Community Development Department Staff have already approved
the property owner's application and have allocated $10,000 from
CDBG funds for the design and engineering assistance, as well as an
additional $10,000 to offset construction costs for rehabilitation
activities.
DISCUSSION
In addition to assistance from the federally funded Commercial
Rehabilitation Program, the property owners have requested
additional Redevelopment Agency assistance in off-setting costs
associated with the rehabilitation of the property. The estimated
total cost for renovating the building will be approximately
$87,486, based on information provided by the property owners'
architect. The cost breakdown is attached as Exhibit 2.
The property owners are substantiating their request partially
based on future anticipated City and Agency revenue that will be
derived from the project over time and also on the benefits of the
project to the Old Town. The property owners intend to replace the
tenants on the first floor of the building with retail users, as
recommended by the R/UDAT, and to place non-retail users on the
second floor. This is expected to increase sales tax revenues to
Redevelopment Agency Report
Agency Financial Assistance
100 West Main Street (Thompson)
October 4, 1993
Page 4
the City of Tustin by approximately $11,663 over a ten year time
frame. (See Exhibit 3)
The renovation of the build-ing is also substantial enough to
anticipate an increase in tax increment received by the
Redevelopment Agency over a ten year period by approximately
$5,475. (See Exhibit 4). This, along with the sales tax, would
provide a total income stream to the City and the Agency over ten
years of $17,138. (See Exhibit 5).
Furthermore, one of the primary goals of The Town Center
Redevelopment Plan is to preserve and enhance the historic nature
of the Old Town area, and to ensure the area's financial viability.
In considering whether Redevelopment Agency assistance might be
provided, the Staff would recommend the Agency be guided by the
following principles:
®
The Agency assistance should be provided for costs for
renovations which either preserve an historically
significant building in Old Town or which makes an
otherwise non-historical building substantially
compatible with the character of Old Town.
·
Agency assistance should be limited to the level which
can 'not reasonably be expected to be financed by the
private sector through conventional lending practices.
Under conventional lending practices, the owner could
reasonably be expected to obtain financing for 65% of the
proposed improvements.
·
Agency assistance should recognize the risk factor
involved in making substantial improvements in the Old
Town Area, but at the same time, not allow for public
subsidy of immediate profits made on the public
investment.
In addressing the first principle, above, the total project cost
anticipated by the property owners will contribute significantly
towards making the existing building compatible with the character
of Old Town. Under the second principle, staff believes that any
proposed Agency assistance should be limited to $27,120 or
approximately 35% of the expected improvement costs. And, in
considering the third principle, staff believes that any Agency
assistance to the property owner should be in the form of a
deferred loan without payments, of which 10% of the loan is
forgiven for each year the property owners hold title to the
Redevelopment Agency Report
Agency Financial Assistance
100 West Main Street (Thompson)
October 4, 1993
Page 5
property.
forgiven.
At the end of ten years, the entire loan would be
To determine the level of assistance, the Staff reduced the total
estimated project costs of approximately $87,486 by the $10,000
rebate that will be provided to the property owner through the
Commercial Rehabilitation Program grant for construction. The
staff then determined the amount of the remaining cost (65%) which
could be financed by conventional methods, if the property owner
wished to utilize conventional financing. This resulted in a
projected Agency assistance level of $27,120.
Total Construction Cost
CDBG Construction Grant
Non-funded Construction Cost
$87,486.00
10,000.00
77,486.00
Percentage Privately Financed
Total Financed Conventionally
65.00%
$50,366.00
TOTAL AGENCY DEFERRED LOAN
$27,120.00
As noted above, the loan will be forgiven at 10% per year ($2,712)
as long as the property owner continues to own the property. In
the event the property owner sells the property before the ten year
loan term, the non-forgiven balance would be due and payable.
With this financial assistance package the property owner will be
eligible to receive $47,120 in combined funding from the City and
the Redevelopment Agency for construction of the proposed
improvement. In summary, this funding is from the following
sources:
CDBG Design and
Engineering Grant $10,000.00
CDBG Construction Grant 10,000.00
'RDA Financial Assistance 27,120.00
TOTAL CITY/AGENCY PROJECT ASSISTANCE $47,120.00
CONCLUSION
Based on the above principles and analysis, the staff believes
there are significant compelling reasons to provide Agency
assistance to the subject property owners for the following
reasons:
.
The subject property has been identified by the community
through the Old Town Charette as hindering the overall
Redevelopment Agency Report
Agency Financial Assistance
100 West Main Street (Thompson)
October 4, 1993
Page 6
atmosphere of Old Town.
·
The R/UDAT singled out this building for redevelopment in
a manner which weuld strengthen the architectural
character of Old Town.
·
The intersection of Main Street and E1 Camino Real is the
primary focal point of Old Town.
·
The City and the Redevelopment Agency will realize
additional tax revenues over ten years totalling
approximately $17,138.
·
The proposed level of assistance reflects the market
forces which currently exist for this type of improvement
project.
·
The proposed structure of the Agency assistance (as a
deferred loan to the property owner) limits any undue
profit being realized by the property owner through the
use of tax increment funds.
The staff, therefore recommends approval of the proposed financial
ass~ nce program·
~, ha~ ~ Zim~, er~'
~levelopm~ogram Manager
r z imme r \ c ct hemp. mem
J~
EXHIBIT 2
PROJECTED REHABILITATION COSTS
100 WEST MAIN STREET
Demolition
New Metal Tower and
Metal Detailing
New Cornice Line "~
New Brick Veneer
New Wood Sills
New Plaster Lintels
New Plaster Base
New Window Assemblies
New Downspouts
New Light Fixtures
and Tower Lighting
Building Directory
Display Case Structures
Painting
SUBTOTAL
15% Contingency
TOTAL PROJECT COSTS
$ 3,500.00
12,500.00
4,620.00
31,917.00
288.00
1,500.00
2,868.00
3,000.00
207.00
3,000.00
575.00
2,100.00
10,000.00
$76,075.00
11,411.00
$87,486.00
EXHIBIT
PROJECTED CITY SALES TAX INCOME
FROM THE REHABILITATION OF 100 WEST MAIN STREET
ASSUMPTIONS
CURRENT SALES TAX TO CITY
48.00
Retail Floor Space--~
after Renovation
Projected Base Year Annual
Sales per Square Foot
TOTAL PROJECTED BASE YEAR
ANNUAL SALES
1,019.00 square feet
$1oo.oo
$101,900.00
Percent Sales Tax To City
BASE YEAR INCOME TO CITY
1.00%
$1,019.00
ANNUAL PERCENTAGE INCREASE
4.00%
ANALYSIS
YEAR
ANNUAL SALES
CURRENT
SALES TAX SALES TAX
TO CITY TO CITY
NET SALE
TAX TO CITY
Year l(Base) 101,900.00
Year 2
Year 3
Year 4
Year 5
Year 6
Year 7
Year 8
Year 9
Year 10
105,980.00
110,215.00
114,624.00
119,209.00
123,977.00
128,936.00
134,093.00
139,457.00
145,035.00
TOTAL NET SALES TAX TO CITY
1,019.00 48.00
1,060.00 50.00
1,102.00 52.00
1,146.00 54.00
1,192.00 56.00
1,240.00 58.00
1,289..00 60.00
1,341.00 62.00
1,395.00 64.00
1,450.00 67.00
$ 971.00
1,010.00
1,050.00
1,092.00
1,136.00
1,182.00
1,229.00
1,279.00
1,331.00
1,383.00
$11,663.00
EXHIBIT 4
PROJECTED TAX INCREMENT INCOME
FROM THE REHABILITATION OF 100 WEST NAIN STREET
ASSUMPTIONS
ADDED ASSESSED VALUATION
52,000.00
PERCENT OF ASSESSED'~ALUE
TO AGENCY
1.00%
ANNUAL PERCENTAGE INCREASE
2.00%
ANALYSIS
YEAR ASSESSED VALUE
Year 1 50,000.00
Year 2 51,000.00
Year 3 52,020.00
Year 4 53,060.00
Year 5 54,122.00
Year 6 55,204.00
Year 7 56,308.00
Year 8 57,434.00
Year 9 58,583.00
Year 10 59,755.00
TOTAL TAX INCREMENT
TAX INCREMENT
500.00
510.00
520.00
531.00
541.00
552.00
563.00
574.00
586.00
598.00
5,475.00
EXHIBIT 5
TOTAL PROJECTED INCOME
TO CITY AND REDEVELOPMENT AGENCY
FROM THE REHABILITATION OF 100 WEST MAIN STREET
Total Sales Tax Income
Total Tax Increment-~
TOTAL INCOME TO CITY AND
REDEVELOPMENT AGENCY
$11,663.00
5,475.00
$17,138.00
rz immer \ cct homp. mem