04_ AGENDA REPORT Reviewed: /
City Manager
G
STFinance Director NSA
MEETING DATE: JUNE 2, 2015
TO: JEFFREY C. PARKER, CITY MANAGER
FROM: , DOUGLAS S. STACK, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER
SUBJECT: AWARD CONTRACT FOR THE FY 2014-15 ROADWAY REHABILITATION
AND SIDEWALK REPAIR PROJECT CIP 70014
SUMMARY
Staff is requesting the City Council award a construction contract to the lowest
responsive/responsible bidder for the Fiscal Year (FY) 2014-15 Roadway Rehabilitation and
Sidewalk Repair Project CIP 70014.
RECOMMENDATION
It is recommended that the City Council award a construction contract to the lowest
responsive/responsible bidder, R.J. Noble Company in the amount of $1,347,937.29, for the FY
2014-15 Roadway Rehabilitation and Citywide Sidewalk Repair Project CIP 70014 and authorize
the Mayor and the City Clerk to execute the contract documents on behalf of the City.
FISCAL IMPACT
Sufficient funds in the amount of $1,765,000 have been budgeted and appropriated in the Fiscal
Year 2014-2015 Capital Improvement Program Budget. CIP 70014 is part of the City's on-going
Maintenance of Effort (MOE) obligation to maintain eligibility for Renewed Measure M (M2)
funding. Effective July 1, 2014, the new MOE benchmark was adjusted to increase from
$1,110,535 to $1,222,756 for FY 2014-15. Funding is provided through a combination of General
Fund and Gas Tax.
CORRELATION TO THE STRATEGIC PLAN
Rehabilitation of roadways and repair of sidewalks contribute to the fulfillment of the City's
Strategic Plan Goal B: Public Safety and Protection of Assets. Specifically, the project implements
Strategy #3, which among other items, is to ensure continuous maintenance and improvement of
public facilities.
DISCUSSION
The Roadway Rehabilitation and Citywide Sidewalk Repair CIP 70014 for Fiscal Year 2014-15
includes asphalt concrete pavement repair, asphalt concrete overlay, slurry sealing, and traffic
striping on various streets within Zone 3 of the City's Pavement Management Program. Zone 3 is
generally bounded by city boundary to the north, Newport Avenue to the west, El Camino Real to
the south, and Browning Avenue to the east. The project also includes citywide sidewalk repair
which focuses on removal and replacement of damaged sidewalk at numerous locations
throughout the City based on an annual field survey conducted by the Engineering Division. The
Engineer's Estimate is $1,463,000.
FY 2014-15 Roadway Rehabilitation & Citywide Sidewalk Repair CIP 70014
June 2, 2015
Page 2
Formal bids were publicly opened on May 12, 2015 and reviewed by Public Works. Six (6) bids
were received and are summarized below by order of least dollar amount:
• R.J. Noble Company $ 1,347,937.29
• Sequel Contractors, Inc $ 1,360,092.05
• Eagle Engineering and Development $ 1,412,208.15
• All American Asphalt $ 1,492,492.00
• Hardy & Harper, Inc $ 1,522,521.73
• Palp, Inc. dba Excel Paving $ 1,574,250.23
• Vido Samarzich, Inc. $ 1,678,398.70
Staff has reviewed the references and the State Contractor's License for RJ. Noble Company and
has determined that they are appropriate for the subject project.
It is recommended that the City Council award the construction contract to the lowest
responsive/responsible bidder, R.J. Noble Company for the FY 2014-15 Roadway Rehabilitation
and Sidewalk Repair Project CIP 70014 and authorize the Mayor and the City Clerk to execute the
contract documents on behalf of the City.
�•ugl.� Stack, P.E.
Jirec • Public Works/City Engineer
Attachment: Location Map
S:\City Council Items\2015 Council Items\06-02-2015\Award of Contract for Roadway Rehab and Sidewalk Repair (CIP
70014)\Award of Contract for Roadway Rehab(CIP 70014).docx
CITY OF TUSTIN
. S7�1s1_ --F ,' # �_ I diel to CI' r /, a Zy�:} *h ti�1/ 11'2�V�.•/ ----r ,
I., a ,- -�' II 1 \";—"-',./;e.,. KVO' </ ///\\\II���'����d 'Y!4—�
L �Tlr ,s Citi J >e.:w JU ° ' \ / `;•..i`a"N ��'
it �• I !Icr 1�.._ ` 4, / ^e NO SCALE
rus,i."'I= 1171 I ! / , / / /P / C , , 0; /hA
LL..�.wY..1.��JI -ILL �111 / " 'S, \•_\ l � �- /P '' :4:. 1 )•�
%
u
�: e I' U l ��€ n 'L— �� 'LOt �\4N t
../ �\ 4 \1 �,\\%> Ke••� /pq�/�icy
"lea it;s7
1 D,i)L 1 IS' 1 1 rifLa=-J ; rigii0000a,e40'c ,N,,, ,,,,n ct:y.,/, //i-t 0, )c.// Kot.
d j 9 f_I I rFIR I I I I II 01: / �/„\M 4+ \\\`�JA /..�1 'W a \ <t4\ ..� yy '
J, rib \. , /^
� _. . i //if •/: /,‘,.(6 ..,:„•%/i..5� :„ a.„ `/,/ fie'-_ A c„
J^\v—m IiU .. ,'V ' ,� / 7.4 (�(17X< Thz/r/ �/1�.y4 � -2 �
` \ ` r � Rw��5
a , '� ZONE 3 - �' / bfl *o .Arz�zzr�
r••:•. .1.,5,,,
r5' 1;ife''s .W" ��t r — �9�
1/:::"4Ataf,:;„?'
ir
,.fwoua /(1.1 //c„ , �:-*•2\•
•*J
—_�f r . ,, ,\®�� - (`z.J.-,.?' •9,4:';--...a.�...- `sir\ -
r RR..II N r /, r� l(•i �K.a'8 _45/e iit,J o v.5��
Icif
a,, t rV •;� q(4'
(.. .�CY
u 8 '1 /,¢,y •� �s. \ j\' �w<•a � `7 J,�`'a.,\V`/yam` 't�5,
Q. ar uta 4, ._ v`?",44',\�,.. -%. ,.ay, Ia �^\�\\ \�?, ; ��iL p�iYh
ilf(° /� N.e4SPA �M1:�d \ v? XCa3#1 \ �W- \�r1 /JiN' ;t �s'Ll'j/ =;l'
FILE: OPJO0O1 14-15 DWG
PROJECT NAME: ANNUAL ROADWAY & PUBLIC INFRASTRUCTURE MAINTENANCE PROGRAM (MOE) (CIP NO. 70014)