HomeMy WebLinkAboutCC 6 NOC GUTTER RPR 07-06-93AGENOA.
DATE:
JULY 6, 1993
CONSENT CALENDAR NO. 6
'7-6-93
e r- C o m xt ,./
TO: WILLIAM.A. HUSTON., CITY MANAGER
FROM: '.P6SLIC WoRKs DEPARTMENT/ENGINEERING DIVISION
ACCEPTANCE OF IMPROVEMENTS AND AUTHORIZING RECORDATION OF
SUBJEC~ "NOTICE OF COMPLETION" FOR SIDEWALK AND CURB AND GUTTER REPAIR
PROJECT, 1992-93 FY, PHASE II
RECOMMENDATIONS
It is recommended that the City Council, at their meeting of July 6,
1993, adopt the attached resolution accepting the works of improvement
and repair and authorizing the recordation of the Notice of Completion
for the subject project.
Assuming no claims or stop notices are filed, it is further recommended
that 35 days after the date of the recordation of the Notice of
Completion, the City Council authorize payment of the final 10%
retention amount of $11,269.02. This amount together with the previous
payments of $101,421.22 represents 100% of the final contract amount of
$112,690.24.
FISCAL IMPACT
The final cost of this project is $112,690.24. This amount represents
a decrease of 0.2% under the original contract amount of $112,962.00.
Because of the time constraints on this project, some areas of repair
were eliminated from this fiscal year's project, but will be included
with the next fiscal year's project. This project is funded through the
Public Works Department, Street Division Budget.
BACKGROUND
This project consisted of the removal and replacement of existing
portland cement concrete sidewalks, curb and gutter and drive aprons as
well as the pruning of tree roots to limit future damage.
This work has been completed to the satisfaction of the City Engineer.
Robert S. Ledendecker
Director of Public Works/City Engineer
RSL: WEH' ccg: .~ocsc&g
Attachment
Wendy E: Hallman
Junior Civil Engineer
1
2
$
4
5
6
?
9
10
11
12
13
14
15
16
17
19
20
21
RESOLUTION NO. 93-72
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND REPAIR AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION FOR
SIDEWALK AND CURB AND GUTTER REPAIR PROJECT, 1992-93 FY,
PHASE II
WHEREAS, Lambaren Contractors, Inc. having a contract
with the City of Tustin to construct the hereinafter described
public work and improvement; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said public improvements
hereinafter mentioned in manner satisfactory to the City
'Council of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinafter more
particularly described in accordance with the provisions of
the contract documents and the Notice of Completion and
acceptance of said public work and improvement should be filed
and payment of the balance due said contract authorized in
accordance with the contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council'of the
City of Tustin that said public work and improvement be, and
the same is hereby accepted. Said work and improvements more
particularly described as follows:
The removal and replacement of sidewalk and curb
and gutter at various locations within the public
right-of-way
NOW, THEREFORE, BE IT FURTHER RESOLVED that the City
Engineer of the City of Tustin be, and is hereby authorized to
execute and file a Notice of Completion and acceptance of said
public work and improvement described herein as required by
law.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin held on the 6th day of July 1993
25
26
ATTEST:
Jim Potts, Mayor
27