HomeMy WebLinkAboutRDA 7 CATELLUS DEV AG 06-21-93 RDA NO. 7
6-21-93
DATE: JUNE 21, 1993 - ~
-TO:
FROM:
SUBJECT:
WILLIAM A. HUSTON, EXECUTIVE DIRECTOR, TUSTIN COMMUNITY
REDEVELOPMENT AGENCY
COMMUNITY DEVELOPMENT DEPARTMENT,' PUBLIC WORKS
DEPARTMENT/ENGINEERING DIVISION
AGREEMENT WITH CATELLUS DEVELOPMENT CORPORATION FOR
PREPARATION AND PROCESSING OF A PROJECT STUDY REPORT FOR THE
NEWPORT AVENUE/SR-55 INTERCHANGE RECONFIGURATION PROJECT
RECOMMENDATIONS
It is recommended that the Tustin Community Redevelopment Agency, at
their meeting of June 21, 1993, authorize the Executive Director and
City Clerk to execute an agreement with Catellus Development Corporation
for preparation and processing of a Project Study Report (PSR) to
caltrans for the Newport Avenue/SR-55 Interchange Northbound Ramp
Reconfiguration Project.
FISCAL IMPACT '~ ''
The cost at this time to the Agency is estimated at $2b0,000. Future
execution of a Development Agreement with Catellus will delineate legal
and financial responsibilities for the Pacific Center East Specific
Plan. Funds expended by the Agency to prepare and process the PSR are
to be fully applied to offset against the Agency's negotiated cost share
percentage of future construction related improvements. Funds to
accomplish work tasks such as the PSR have been advanced by the Agency
to the City and are available for accomplishment of work efforts
associated with carrying out the Redevelopment Plan for the South
Central Project Area.
DISCUSSION
As part of the City's approval of the Pacific Center East Specific Plan,
' a detailed Phasing Concept Plan was included which outlined the amount
of permitted development based upon the sequence of plan preparation and
completion of certain circulation improvements required within the
Specific Plan Area for development and redevelopment to occur.
Essential to implementation of any future phase of the Specific Plan is
the preparation and processing of a Project Study Report (PSR) to
approval by Caltrans for the Newport Avenue/SR-55 Interchange Northbound
Ramp Reconfiguration. The Developer, Catellus Development Corporation,
has been responsible for the costs of preparation and processing of the
PSR, and have previously retained the firm of Dokken Engineering to
undertake this work on their behalf.
Unfortunately, the current economic downturn has had an unforseen
negative impact upon Catellus' financial ability to proceed at this time
with Dokken's consulting engineering services necessary to complete,
process and obtain approval of the PSR. The subject agreement between
the Agency and Catellus provides for the Agency to assume the financial
and contract administration responsibility for completion and processing
of the PSR to Caltrans for approval in light of Catellus' current
financial inability to move forward with the Dokken Engineering work.
The Agreement with Catellus Development CorporatiOn-'w~i~l~ ~n.a~l~m'
critical link in the accomplishment of the South Central Project Are
infrastructure improvements to begin to be realized, that is, the future
approval by Caltrans of the Newport Avenue/SR-55 Interchange Northbound
Ramp Reconfiguration. Without Caltrans ' approval of this work,
implementation of the full Newport Avenue extension project from its
present termination to Valencia Avenue, including other accompanying
necessary infrastructure in the Pacific Center East Specific Plan Area
will be seriously hampered.
A separate Professional Services Agreement between the City and Dokken
Engineering for the PSR work will be considered under separate agenda
items by both the City Council and the Tustin Community Redevelopment
Agency.
Christine A. Sh~leton
Assistant City Manager
Robert S. Ledendecker
Director of Public Works/
City Engineer
Engineering Services Manager
CAS: RSL: DRK: ccg: psr
Attachment
AGREEHENT FOR PREPARATION ~
PROCESSING OF A PROJECT STUDY
REPORT (PSR) TO CALTRANS FOR THE
NEWPORT AVENUE/SR-55 INTERCHANGE
NORTHBOUND RAMP RECONFIGURATION
This AGREEMENT is made and entered into this day of
, 1993, by and between the Tustin Community Redevelopment
Agency ("Agency") and Catellus Development Corporation ("Developer").
RECITALS.
A. The CITY OF TUSTIN has certified Environmental Impact Report
(EIR) 90-01 (SCH No. 89091320), and has adopted General Plan Amendment
Nos. 90-03(a) and 90-03(b) and Zone Change No. 90-04 which approved the
Pacific Center East Specific Plan.
B. The Pacific Center East Specific Plan ("Specific Plan") is a
major tool for implementing the
Tustin Community Redevelopment
Project.
C. Current
City of Tustin's General Plan and the
Agency's South/Central Redevelopment
infrastructure inadequacies in the South Central
Project Area in the vicinity of the South Newport Avenue/Edinger Avenue
area are currently a major constraint to development and redevelopment
within the South Central Project Area. Blighted conditions (including
underutilized properties, a lack of continuity and cohesiveness) would
likely not be reversed or alleviated without action by the Agency.
Additional new development in the Project Area would also not be able to
occur without infrastructure improvements. The southerly extension of
Newport Avenue and its crossing under an existing railroad right-of-way
and flood control channel, construction of a new ramp interchange at
Rev~ sed 6/14/93 --1--
Newport Avenue and the SR-55 Freeway,
associated water, storm drain and
parcels to be reconfigured for
improvements to Edinger Avenue and
utility improvements will enable
non-rail users and facilitate
redevelopment of the southerly portion of the South Central Project
Area.
D. The Specific Plan has been designed as a mechanism by which
to develop the necessary infrastructure, support services and
facilities, and implementation programs needed to facilitate the
redevelopment of the southerly portion of the South Central Project
Area. As such, the Specific Plan includes a Phasing Concept Plan
important to development and' redevelopment of the Specific Plan
Area. The Phasing Concept Plan as shown on Exhibit A attached
hereto, outlines the amount of permitted development based on the
sequence of plan preparation and completion of certain circulation
improvements required within the Specific Plan area for development and
redevelopment to occur. The phasing of development is tied to
eliminating circulation and infrastructure inadequacies and providing
for additional capacity, approval of circulation plans by State agencies
and approval of a railroad right-of-way and flood channel crossing north
of Edinger Avenue at Newport Avenue. As part, and "key link" of the
Phasing Concept Plan, the preparation and processing for approval of a
Project Study Report ("PSR") to Caltrans for the Newport Avenue/SR-55
Interchange Northbound Ramp Reconfiguration is ,essential to
implementation of any future phase of the Specific Plan.
E. The Developer is responsible for the costs of preparation and
processing for approval of a PSR to Caltrans for the Newport Avenue/SR-
55 Interchange Northbound Ramp Reconfiguration ("Interchange Project").
The firm of Dokken Engineering has been previously retained by the
Revised 6/14/93 --2--
_Developer to undertake work associated with advancing the Interchange
?roject through the Caltrans PSR and Final Environmental Document
approval process. Dokken Engineering under contract to the Developer
has previously performed significant amounts of work on the PSR valued
at approximately $400,000.00.
F. Phasing of development within the Specific Plan Area is not
only based upon the sequence of circulation and infrastructure
improvements within the Specific Plan Area, but also based upon market
demand, development opportunities, circulation capacity and financing
factors. Unfortunately, the Developer has represented that the current
economic downturn has had an unforeseen negative impact upon the
financial ability of the Developer to proceed with the consulting
engineering services of Dokken Engineering. The Developer has indicated
_ that they do not have sufficient funds at the present time to pay for
the consulting engineering services necessary to complete, process and
obtain approval of the PSR.
G. 'The Agency and Developer agree that it would be beneficial to
both parties to expeditiously proceed toward gaining PSR approval from
Caltran~ for the Interchange Project.
H. The certified EIR for the Specific Plan describes the various
circulation and infrastructure improvements necessary to mitigate the
expected traffic capacity deficiencies and infrastructure inadequacies
associated with implementation of the Specific Plan and the Developer's
fair share percentage obligation for transportation mitigation
improvements within and outside of the boundaries of the Specific Plan.
I. It is anticipated that the Agency will negotiate Agency
- ~articipation with Developer in certain transportation and
infrastructure mitigation improvements within and outside the boundaries
Revised 6/1&/9~ --3--
of the Specific Plan Area in the City and South Central Project Area
necessary to accommodate development within the South Central Project
Area and Specific Plan Area.
J. In light of the Developer's current financial inability to
proceed with the Dokken Engineering work at the present time, but
anticipated ability to pay such costs at a future date, the Agency and
Developer are willing at this time to enter into this Agreement to
provide for financial and project contract management responsibilities
for completion and processing of the final PSR to Caltrans for approval.
NOW, THEREFORE, IT IS MUTUALLY AGREED by the parties that:
1. The Agency will retain and fully administer the services of
Dokken Engineering, under a separate Agency Professional
Services Agreement ("Dokken Agreement"), to proceed with the
preparation and processing of a PSR to Caltrans for approval
of the Interchange Project. The Agency shall have the sole
authority for reviewing and determining whether the work
performed by Dokken Engineering is satisfactory and if not,
how best to correct the deficiencies in the work, including
the ability to terminate the Dokken Agreement and to replace
Dokken Engineering with a firm of the Agency's sole choice.
Should the Agency terminate the Dokken Agreement, Dokken
Engineering shall be required to forward to the Agency any and
all documents prepared by Dokken Engineering ~ith respect to
the PSR for the Interchange Project. Developer shall forward
to the Agency all documents prepared by Dokken Engineering
2 o
pursuant to Dokken Engineering's contract
should the Agency request such documents.
The Agency will pay with its own funds for
with Developer
the consulting
Revised 6/14/93 --4--
services of Dokken Engineering and the services of any other
consultant(s) deemed necessary to expedite the completion and
processing, of the PSR.
The Agency will be fully responsible for the project
management of the PSR including any change orders necessary to
complete the PSR for the Interchange Project.
The cost to the Agency to fully prepare and process the PSR is
$200,000 which includes Dokken Engineering
environmental consulting work ($15,000);
($17,000); and city administrative costs
estimated at
($153,000)
Contingencies
($15,000).
Developer and
intended only
Agency agree that the present arrangement is
as a means to move the Specific Plan project
forward and to complete phasing steps needed to eliminate
infrastructure and circulation inadequacies within the South
Central Project Area. The Agency and Developer agree that
completion of a Development Agreement must be initiated at the
earliest possible date. Such Development Agreement will
clearly delineate the responsibilities, both legal and
financial, for the development of the Pacific Center Specific
Plan Area, including completion of infrastructure and
circulation improvements and completion of all infrastructure
improvements required by Environmental Impact Report 90-01.
The Developer agrees that any and all funds expended by the
Agency to prepare and process the PSR shall be fully applied
to and offset against the Agency's negotiated cost share
percentage of future construction for traffic and
infrastructure mitigation improvements within and outside the
Revis~ 6/1&/93 --5--
10.
boundaries of the Specific Plan Area as required by the
certified EIR for the Specific Plan.
The various headings and numbers herein, the groups of
provisions of this Agreement into separate sections and
paragraphs, and the organization hereof are for convenience
only and shall not be considered otherwise.
The parties agree to cooperate and enter into any and all
other agreements reasonably necessary or convenient to provide
for future project implementation stages.
The Agency retains the right, in its sole discretion, to
assign all of its rights and obligations under this Agreement
to the City of Tustin.
Each party represents that they have been duly authorized to
enter into this Agreement on behalf of the party for whom they
sign.
Revised 6/14/93 --6--
Date:
COMMUNITY REDEVELOPMENT AGENCY
BY:
William A. Huston
Executive Director
ATTEST:
APPROVED AS TO FORM:
BY:
City Clerk
BY:
City Attorney
Date:
CATELLUS DEVELOPMENT CORPORATION
BY:
Corporate Officer
BY:
Revise(] 6/14/93 -7-
City of Tuxtin
Table 3
PHASING SCHEDUI .E
PHASE 1
ImprQvement or Action Ne~led
Complianee with all conditions of appro~d and
eomplianee with original dewlopmcnt and
Conditional Usc Permit (CUP) 84-20, inclvdlng
any neeessary infrastructure improwments.
B. Required Plan Submittals
Project study report to Caltraus for New-
port Avenu¢/SR-55 interchange
northbound ramp reconfiguration.
2. P!an% specifications, agreements for:.
a. SR-55 northbound ramp configuration
b. Newport Avenue extension south of
Edinger Avenue to Valencia Avenue.
c. Edlnger Avenuc widening enst of SR-
55.
d. DelAmo Avcnuc extension and widen-
ing from reconfigared SR-55 ramp to
Edingcr Avenue.
Approved plans for additional traffic im-
provements needed to mitigate impacts of
Phase i square footage for which eertiticate
of occupancy will be issued, induai-~
Within City of Tustin
Red Hill Avenue and Edinger Avenue2
Add third northbound through lane
Add third westbound through lane
Add second southbound left-turn lane
Within City of Santa Ana
SR-55 SB ramp and Edinger Avanue2
Add second westbound left-turn lane
Building Permits or Certificates
of Qccuuancv May Be Issued For
permits for 224,520 square feet of offiee and eertifi-
cate of occupancy for 224,~20 square feet of office
already entitled by CUP 84-20 to be located In
Planning Area 8 only (must be consistent with
approved development plan for CUP 84-20).
Permits for 100,000 square feet of office, minimum
250-room hotel and 100,000 square feet of eom-
mercial in Phase II.B and permits for 224,520
square feet of additional office in Planning Area 8
in Phase IA (in the event proposed development
does not comply with CUP 84-20 entitlement).
29
EXHIBIT "A"
.,tic Center East Specific Plan
Table 3 (cont'd)
Improvemen~ or Action Needed
C. Plan Approvals or Construction Complefiom
L Approval of all submittals, plans ahowa in
IB1 and IB2.
2. Completion of all improvements aa shown
in 11t3.
Building Permits or Certificates
9f Occupancy May Be Issued For_
Certificate of occupancy for permits authorized to
be i~ued for in Phase lB and IA (in the event
proposed development doez not comply with CUP
84-20 entitlement).
PHASE II
Improvement[ or Action Needcx!
Required Plan Submittals
1. Plans, specifications, and reports for New-
port Avenue extension north of Edinger
hvcnnc.
2. Approved ~ for all traffic improvements
noted /n klF. and n¢ce.ssa~ to mitigate
traffic impacts of Ph~¢ H ~quar¢ footag¢$
for which c~rfificate~ of occupancy will b~
issued, inchdin~
Within (~itv of Tusfin
Red Hill at Walnut and Sycamore1
Remo~ parking and stripe northbound
and southbound through huc~
Del Arno and Edinger2
Add second northbound left-tm lane
Red Hill and Valencia2
Add second northbound left-turn lade
Building Permits or Certific,?tes
of Occuoancv May Be Issued FOr
WithinCi of Santa Aaa
SR-55 SB ramp and Edinger1' 3
Add third eastbound through lane
Add third wc~tbotmd through lane
Edlnger intersections in Santa Ana1 (at
Ritchey, Lyon and Grand)
PartJdpate in improvements through
TSIA fees3
permits for 500,000 square feet of office, 50,000
square feet of commercial
3O
City of Tustin
Table 3 (cont'd)
Improvement or Action Needed
' Within Project Area
B. Plan Approvals or Completion of Construction
L Completion of all improvements as shown
2. Completion of improvements shown in
Ill.?-
Building Permits or Certificates
9f Occuoancv Ma'/Be Issued For
Certificate of occupancy for permits authorized to
be issued in Phase I1
PHASE III
ImprOvement or Action Needed
Required Plan Submittals or Approvals
Approved plans for additional traffic im-
provements needed to mitigate impacts of
phase III square footages for which ceatifi-
cates o~ occupancy will be issued, including:
Newport and Walnut1
Add tl~'d nortbhotmd througl~ lane
Acid third southbound through lane
Add eastbound right-turn lane
Add second southbound left-turn lane
Newport and Sycamore2
Add westbound left-turn lane
Add second eastbound through lane
Add second eastbound left-turn 'lane
Add second northbound left-turn lane
Add third northbound through lane
Add third southbound through lane
Red Hill and Valencla2
Add southbound right-turn lane
Add westbound right-turn lane
Add eastbound free right-turn lane
Building Permits or Certificates
of Occuoancv May Be Issued For
31
EXHIBIT "A"
?acific Center East Specific Plan
Table 3 (cont'd)
Improvement or Action Needed
.Within~
Edinger intersections in Santa Anal' 3 (at
Ritchey, Lyon and Grand)
Partidpate in improvements through
Building Permits or Certificates
of Occupancy MaY Be Issued For
Within Cities of Tustin and Santa Ann
Red Hill and Warner~
Add southbound right-turn lane
Red Hill and Dyer1
Participate in improvements through
2.
Approval of plans and issuance of con-
struction permits for Newport Avenuc
extension north of Edingcr Avenue includ-
ing approvals from Orange County En-
vironmental Managemcnt Agency and
AT&SF railroad.
Approved plans for all traffic improvements
noted in EIR necessary to mitigate traffic
implcts of cem~inlng specific plan buildout
square footage, as listed in III A.1.
B. Completion of Construction
1. Completion of improvements down in IH
A.1 and IH AS..
Permits for 300,000 square feet of ofllee and 10,000
square feet of commercial
Permits for remaining buildout square footages
authorized by the specific plan
Certificate of occupancy for permits authorized to
be issued la Phase Ill, including bnildout of the
specific plan
1
2
3
Project contribution to thlg improvement.
Project mitigation improvement.
Improvenients to Edinger Avenue in proximity to the SR-55 overpass are linked to the design of Newport
Avenue extension north of Edinger Avenue. Other improvements along Edinger in the City of Santa and
actual improvement design and timing for completion of these improvements will be subject to approval by
the City of Santa Aua. However, since the project is contributing to areawide improvements, any discretion
on design or timing as determined by Santa Ama will not affect issuance of entitlements on the Pacific Center
East project in Tustin. Since this section of roadway is part of the CMP network, improvements will be
designed for this location so that adequate levels of service will be attained to meet CMP eligibility
requirements.
32
EXHIBIT "A"