,,:,TE: May 11, 1993 I n t e r -Com ` M
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: COMMUNITY SERVICES DEPARTMENT
SUBJECT: SPORTS PARK DESIGN UPDATE - MAY 17, 1993
RECOMMENDATION:
Receive and file.
FISCAL IMPACT'
Not applicable.
BACKGROUND'
The City Council has requested updates on the progress of the
preparation of the Master Plan and working drawings and bid
- specifications for the Sports Park. This progress is documented below.
TENTATIVE
TASKS COMPLETION DATE STATUS
Prepare topographic
survey
1/22
- 2/19
Complete
Prepare schematics
(Master Plan task)
O Building Plan
1/20
- 2/3
Complete
O Hardscape Plan
1/27
- 2/9
Complete
O Planting Plan
1/27
- 2/9
Complete
City review of
schematics
2/9 -
2/12
Complete
Revise as required
2/12
- 2/17
Complete
Prepare agronomist's
report
2/3 -
2/19
In progress
Establish program,
Concession/Pro Shop
2/3 -
2/19
In progress,
program is being
tied to the
selection RFP for
special consultant
TENTATIVE
COMPLETION DATE
Select specialized,
consultant, if required
Prepare design development
drawings
O Park Plan
O Sports field design
O Building design
O Grading
O Outline specifications
O Prepare estimate
Submit to design development
drawings City for review
Revise design development
drawings
Submit design development
drawings to City for
approval
Prepare construction
documents
11 Architectural
O Structural
O Mechanical
O Electrical
O Landscape
O Irrigation
C Civil Engineering
O Specifications
O Estimate
2/19 - 2/26
Request for proposal
now being drafted
2/19
- 3/12
Complete
2/19
- 3/12
Complete
2/19
- 3/12
Complete
2/19
- 3/12
Complete
2/19
- 3/12
Complete
2/19
- 3/12
Complete
3/12
- 3/16
Complete
3/16
- 3/19
Complete
3/19
- 3/23
Complete
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
3/16
- 5/31
In progress
Submit to City for 500
complete plan check 4/16
Complete
As a result of the 50% plan check comments, it was found that there is
a potential for significant cost overruns. The architect is currently
developing revised estimates for the project based on the following
areas of concern:
Addition of a large transformer and pad.
IRWD may reguire a booster pump for the irrigation system.
Addition of fire sprinklers and fire hydrant to serve the site
structures.
Civil corrections increase the scope of work at the storm
drain system.
Jogging track and related lighting add cost.
Building design appears to be more expensive than budgeted.
At the City Council meeting on May 3, 1993, the Council was informed
that staff has asked the architect to stop work on the bid documents.
The project was put on hold to provide time to re-evaluate the cost
estimate and develop design alternatives before proceeding any further.
While currently in progress, the cost re-evaluation and alternative
design development will add approximately 30 days to the schedule.
Staff will provide a report on the updated cost estimate at the June 7th
meeting.
TASKS
Submit to City for 80%
complete plan check
Submit to City for bidding
95% complete
Building Department
corrections; release to bid
Prepare addendum to bid
documents
Bidding Completed
Award Contract
Start Construction
TENTATIVE
COMPLETION DATE STATUS
6/14 Future
6/31 Future
7/5 - 7/14 Future
7/5 - 7/22 Future
Mid August
Late August
Early September
The Design Review Process for the project is in progress. The
Commission approved the design and will review revised playground
schemes at the May 20, 1993 meeting. The Planning Commission will
review the designs and consider a Conditional Use Permit after the
design project resumes.
4and 'estrick
Recr ..ion Supervisor
P .'1 : 5175PUPD. cc
/