HomeMy WebLinkAboutRPT 3 FWY CONST RPT 03-15-93A^ E NDA3^ 9 ? REPORTS N0. 3
Qw°r J 3-15-93 _
Inter-Comp�j.
DATE: MARCH 15, 1993 "It,
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: FREEWAY CONSTRUCTION STATUS REPORT (P.W. FILE NO. 896)
RECOMMENDATION
Receive and file.
BACKGROUND
Following information relates to both freeway and local street
closures as they pertain to the Tustin area.
Route 55 northbound off -ramp to Irvine Boulevard/4th
Street tentatively scheduled to open in late April or
early May, 1993.
Main Street (closure No. 1) between Williams Street and
— Stoneglass was closed on May 5, 1992 and is scheduled to
open in June, 1993.
Main Street (closure No. 2) between Myrtle Avenue and
Stoneglass which was tentatively scheduled between mid-
1993 and late -1993 (5 months) is now being reevaluated
and Caltrans is working with the prime contractor to
delete this closure.
° First Street bridge across Route 55 is scheduled for
opening in April, 1993.
Nisson Road between Pasadena Avenue and "B" Street was
opened partially to through traffic on August 20, 1992.
This partial opening consists of 24' wide street with
curb and gutter on the south side and concrete barrier,
curb and gutter and/or white edge stripe on the north
side. The ultimate construction is tentatively scheduled
for mid-1993.
I-5 northbound on-ramp from Newport Avenue to close in
early April, 1993 for three weeks.
I-5 southbound off -ramp to Newport Avenue to close in
May, 1993 for three weeks.
The above schedule was furnished by Caltrans Resident Engineers and
is subject to weather conditions.
Caltrans and St. Jeanne DeLestonnac school officials have
apparently reached an agreement regarding the Main Street driveway
access. Plans for the driveway construction/modification have been
William A. Huston
Freeway Construction Status Report
March 15, 1993
Page Two
submitted to both Caltrans and the City for review. The work is
now being coordinated by the consultant with all affected utility
companies and Caltrans. It is anticipated that the driveway
construction will occur either concurrently with the Main Street
reconstruction or immediately after its completion in June, 1993.
Staff will continue to update this item as information is received
from either Caltrans or St. Jeanne DeLestonnac school.
Robert S. Ledendecker
Director of Public Works/City Engineer
RSL:klb:fwystrpt