HomeMy WebLinkAbout10 ANN'L S C&G REPAIR 09-06-94 NO. 10
9-6-94
Inter-Com
DATE:
SEPTEMBER 6, 1994
TO:
FROM:
SUBJECT:
WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
ANNUAL SIDEWALK AI~D CURBAND GUTTER REPAIR PROJECT, 1994-95 FY
RECOMMENDATIONS:
For consideration by the City Council, at their meeting of September 6,
1994. It is recommended that the City Council adopt the attached
resolution approving the plans and specifications for subject project
and directing the City Clerk to advertise for bids.
FISCAL IMPACT:
The estimated cost of this project is $225,521.60 and has a budget of
$235,000.00 as a part of the Field Services 4030-6235 operating account.
Of this budgeted amount, $1,735.00 is being used in conjunction with
Community Development Block Grant (CDBG) funds for the Americans with
Disabilities Act compliance. This work is a part of the City's on-going
Maintenance of Effort requirements for Measure M and Proposition 111.
BACKGROUND:
This project consists of the removal and replacement of portland cement
concrete sidewalk, curb and gutter and drive aprons. The majority of
the areas of removal and replacement have been caused by street tree
roots, traffic or water damage. The project will also include the
trimming and removing of damaging tree roots.
A tentative schedule for this project is as follows:
Authorization to advertise for bids ............
First legal advertisement
Second legal advertisement . . .
Bid opening ........................
Award of Contract ...... .
September 6, 1994
September 15, 1994
September 22, 1994
October 4, 1994
October 17, 1994
Robert S. Ledendecker
Director of Public Works/City Engineer
RSL: Wq~H: ccg: annc&g
Wendy E.~Hallman
Junior Civil Engineer
Attachment
1
2
3
4
5
6
7
8
9
10
11
12
13
15
16
17
18
20
21
24
27
28
RESOLUTION NO. 94-112
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, APPROVING PLANS AND SPECIFICATIONS FOR ANNUAL
SIDEWALK AND CURB AND GUTTER AND REPAIR PROJECT, 1994-95
FY
WHEREAS, it is the intention of the city Council of the
city of Tustin, california to contract for the construction of
and replacement of PCC sidewalk, curb and gutter and drive
aprons at various locations.
WHEREAS, the City Engineer has presented
specifications for the construction of said work;
plans and
NOW, THEREFORE, BE IT RESOLVED that the plans and
specifications presented by the city Engineer be and are
hereby approved as the plans and specifications for:
Annual Sidewalk and Curb and Gutter Repair Project,
1994-95 FY
BE IT FURTHER RESOLVED that the City Clerk is hereby
authorized and directed to advertise as required by law for
the receipt and sealed bids for proposals for the doing of the
work specified in the aforesaid plans and specifications;
BE IT FURTHER RESOLVED that this project is categorically
exempt from the requirements of the California Environmental
Quality Act; Class I: Existing Facilities.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin held on the 6th day of September
1994.
Thomas R. Saltarelli, Mayor
ATTEST:
city Clerk