HomeMy WebLinkAbout10 T SPTS PK TRACK 07-18-94NO. 10 7-18-94 DATE: JULY 18, 1994 Inter-Corn TO: FROM: SUBJECT: WILLIAM A. HUSTON, CITY MA~IAGER COMMUNITY DEVELOPMENT DEPARTMENT TUSTIN SPORTS PARK - MULTI-USE T~ACK RECOMMENDATION It is recommended that the City Council direct staff to negotiate a change order on the Sports Park project for construction of a multi-use path for jogging and rollerskating. FISCAL IMPACT The cost to add a multi-use track is estimated at approximately $170,000. If approved by the City Council, the project budget would be amended to include she actual change order amount. The original jogging path was es5imated to cost $83,000. DISCUSSION At the City Council meetin~ on July 5th, Mayor Saltarelli and Councilperson Worley requested that staff consider the addition of a multi-use track for jogging and/or roller skating at the Tustin Sports Park. While one of the recommended designs for the Sports Park included a 6 foot wide jogging path construcsed largely of aggregate base and extending around the inside parameter of the park site, the path was deleted in final review of %he Sports Park Master Plan and budget by the City Council. Additiun of a multiuse track capable of serving the needs of jogging and roilerskating would require a 10 foot wide asphalt surfaced path to safely allow for jogging and skating simultaneously. Exlsting lighting at the park should be adequate for evening use. A cost estimate for the track is a~%ached as Exhibit A. The Sports Park contractor k~s advised staff that the addition of a track could be done simultenecusis-wish the remainder of the work if started soon. Staff woui!, %herefcre, recommend that the City Council provide staff with iirectirn to negotiate a change order City Council Report Tustin Sports Park - Multi-Use Track July 18, 1994 Page 2 with the Sports Park architect and Sports Park contractor for construction of a multi-use path. Christine A. Sh.i.~eton Assistant City Manager Edward Elowe Project Manager :CAS :kbc\mltustrk. cas EXHIBIT A 4 o COST ESTIMATE ADD A MULTI-USE TRACK TO TUSTIN SPORTS PARK Minor regrade and construct 10 feet wide asphalt track with sprinkler modifications per IRWD standards 40,000 square feet @ $3.00 $120,000 Concrete mow strip 4,000 square feet @ $6.00 Colored seal coat and striping 40,000 square feet @ $0.50 Delete hydroseed at new track 40,000 square feet @ $0.06 Subtotal Professional fees (architect, project management) Estimated Total (if needed or other alternative) 6% 24,000 20,000 <2,400> $161,600 9,600 $171,200