HomeMy WebLinkAbout23 ROLLER HOCKEY 07-05-94AGENDA
NO. 23
7-5-94
DATE:
JULY 5, 1994
Inter-Com
TO:
FROM'
SUBJECT:
WILLIAM ~. HUSTON, ASSISTANT CITY MANAGER
COMMUNITY SERVICES AND COMMUNITY DEVELOPMENT DEPARTMENT
ROLLER HOCKEY UPDATE
RECOMMENDATION
Pleasure of the City Council.
FISCAL. IMPACT
In the event the City Council wishes no construct a roller hockey
rink at the SPorts Park, minimum construction costs could range
from $274,400 for one rink to over $449,400 for two rinks.
Additional costs for construction delay or construction of a
concession building could also occur.
BACKGROUND AND DISCUSSION
At the City Council meeting of J'~e 20th, Councilman Potts
requested that staff return with a repor5 examining the possible
addition of an "in-line skating" or "ru!lerblading" hockey rink at
the Tustin Sports Park currently in ccnst_~-uction. Staff consulted
the architect, landscape architect, and project manager on the
Sports Park to gain a perspective on the most suitable location for
a skating rink at the park, construction costs, implications to the
existing facility, and options for developing a roller hockey rink
and concession. A number of members cf 5he City's design team at
the Sports Park have also had experience in planning, design and
construction of roller hockey rinks.
The Tustin Sports Park site is approximately 20 acres with 50% of
the site designed to a~commodate three softball fields, six tennis
courts, a concession/restroom building, playground, and 200 parking
spaces. The remainder of the site is designed for two basketball
courts, two soccer fields, and a group picnic shelter. The park is
adjacent to a 10 acre elementary schocl site, and was designed for
off-hour joint use of the soccer fields and parking lot by the
school in return for joint use of 5he school's auditorium and
parking lot on special occasions.
City Council Report
Roller Hockey Update
July 5, 1994
Page 2
A roller hockey rink requires an area of 85 feet x 200 feet (17,000
s.f.) with fencing, lighting, team boxes, penalty boxes, and a
score keepers box. In addition, the surface must be free of cracks
and coated with'a durable finish to denote court lines and maximize
slip resistance. Sidewalks are required around the rink for
pedestrian circulation. Bleachers may also be required for
spectator seating high enough to see above the crash boards.
A facility for a concession vendor and equipment storage would also
need to be studied. Under the current design, the-concession
facility under construction at the Sports Park only provides for a
tennis pro shop and a food concession." It is not close to the
soccer fields, and not easily adaptable for expansion.
Should the City Council decide that they want a roller rink at the
Sports Park, the most appropriate location for the rink would be at
the soccer field closest to the basketball courts. It is close to
the parking lot, would have the least noise and lighting impacts on
the existing residential development at Keller, and avoid conflict
with the new storm drain system.
There are a number of implications to be considered for
introduction of a skating rink at the Sports Park:
· A roller rink would replace one soccer field. Two rinks would
also be able to be accommodated in the area planned for one
soccer field. Ideally, two rinks would provide the optimum
space for staging a roller hockey program in order to provide
for; a warm-up area for teams wai.ting to play, program
expansion, and staging of tournaments. The potential location
for one or two~ro!ler rinks at the Sports Park is shown as
Exhibit A.
One rink would have the same impact on parking as one soccer
field. Two rinks' could potentially place additional heavy
demand on parking a~nd should really necessitate an extra 15 to
20 parking spaces. The site cannot accommodate additional
parking without sacrifice of the tennis courts, a softball
field, or a soccer field.
The adopted Master Plan for the Sports Park identified soccer
as high priority. AYSO Region 96 has 1,480 soccer
participants with ratios of 240 participants in summer, 1,000
in fall, and 240 in winter. Due to the high volume of soccer
participants in the fall, it is anticipated that softball
fields at the Sports Park would need to be shared as soccer
City Council Report
Roller Hockey Update
July 5, 1994
Page 3
practice fields. Elimination of one soccer field would reduce
overall soccer practice area by 20% and reduce soccer
tournament play by 50%.
The addition of a roller hockey rink would require Design
Review by the Planning Commission for any new improvements in
order to replace a soccer field. In the event sports field
lighting needs to be moved, a revised Conditional Use Permit
would also be required.
Under a scenario where the C~sy would build the rink, a
schedule could be anticipated as follows:
Exhibits, reports, Plannin~ Commission 60-75 days
Draw plans, plan check, permits 30-45 days
Construction period 30-45 days
TOTAL 120-165 days
If a vendor provides the plans and construction services, the
time period could be considerab2y longer.
Park construction is currentSy 25% complete. Grading,
underground plumbing, undergroun~ etecsrica!, and storm drain
systems are completed. Fencing, building walls, and
irrigation are in progress. .~k~ contractor for the Sports
Park expects to reach substantial completion by the end of
November 1994, approximately 15~ days =rom now.
The addition of a roller hockey rink would require a change in
the existing grades at the soccar fields. The flow of water
across the 10 acre portion of k_ ire currently planned for
the soccer fields would be affer~ed. As much as $ acres of
the site would require re-gra~ing. Existing electrical
conduits would have to be relocated. Additional storm drain
piping may be required to car~ water away from the large
concrete pad needed for a rink ~ue to 5he change in grades.
Soils compaction and import of base material would be required
similar to what.was needed fcr the existin~ building pad
(concession). Overall, the work would affect 35% of the site
and could delay use of the rema±ning soccer field until the
construction for the rink is ~complete~. Since there is a
presence of expansive soil in Eas[ Tus%Sn, there will also be
a need to construct the rink ccncre~e pad using post tension
slab construction, a more cos%2y conssruction method which
will prevent slab cracking.
Should the COuncil decide that nhe¥ would like to see a roller
hockey rink/concession~built at the Spor%s Park, there are a number
City Council Report
Roller Hockey Update
July 5, 1994
Page 4
of operational/construction options that will need to be fully
explored:
A,
A private concessionaire could draw plans, obtain the permit
for improvements, build the facilities and operate the
concession. City staff would have ~o process a competitive
proposal package for Council to review and approve.
Contracts, bonds and insurance wou2d have to be executed.
Construction would occur after the Sports Park is completed
and operational. Use of the remaining soccer field would be
disrupted or delayed. There would be concerns about the
impact of disrupting what will be existing services such as
electricity and plumbing on the site during construction.
The City would issue a change order 5o the existing architect
and provide the plans. A change order would be issued to the
existing contractor to build the facility. Staff would obtain
competitive proposals from vendors tc operate and maintain the
facility and concession services. This option could occur
under two scenarios with very different implications:
.
Stop construction of the soccer fields to minimize
construction rework costs. The change order would have
to compensate the existing con%ractor for the
delay/disruption of the work wkich is currently 30 days
ahead of schedule. Potential cost for delay is in the
range of $90,000 - $120,000 in addition to construction
costs.
o
Allow construction to proceed on the Sports Park and
build the rink after substansial completion by the
contractor. This is less risk, ~eletes the potential for
a delay claim, but has a higher construction cost.
Either option would delay use of the remaining soccer field.
Selection of either a vendor to build and/or to operate the
.~.~cility, should be ~n open competitive proposal process.
Preparation of the request for proposal, solicitation of proposals,
review, contract execution and processing will add 5ime and cost in
excess of the construction estimate noted herein.
In the event the City builds the roller hockey rink, minimum
construction 'costs could be expected ~o be approximately $274,400
for one rink with no concession building, or $449,400 for two rinks
without a concession building. The a5di%ion cf a concession
building would add approximately $45,C~0. Exhibi5 B provides
compl, ete detail on all construction, i= it is the desire of the
City Council Report
Roller Hockey Update
July 5, 1994
Page 5
Council to stop construction in the Sports Park soccer fields, an
additional $90,000 - 120,000'in contract delay costs may also be
considered.
City construction estimates vary significantly from the proposal
submitted at the City Council meeting on June 20th to the City by
Rennie Clarke representing Tustin In-Line Skate who projected costs
for two rinks of only approximately $195,566. However, the Tustin
In-Line estimate appears to have assumed a flat piece of raw land,
did not consider the current state of construction at the Sports
Park, the presence of expansive soils, or design costs (Exhibit C).
With the current construction progress so advanced on the Sports
Park, the City Council may still want to also reexamine whether
construction of an outdoor rink facility at another location such
as Columbus-Tustin (in cooperation with the School District) which
is already improved with adequate parking, or a commercially owned
vacant property somewhere in the City would be possible.
~_~d Eiowe
Project Manager
EE :kbc\roller2 .ee
Rec~=~t ion~ Supervisor
CONSTRUCTION COST ESTIMATe.
ROLLER HOCKEY RINK
AT SPORTS PARK
EXHIBIT B
One Roller Hockey Rink
Re-survey, re-grade existing soccer fields, and a~d area drain
laterals to existing storm drain system
348,000 s.f. @ $0.10 $ 35,000
.
Rework existing underground electrical, rework irrigation and
landscape. Add separate circuits for skating rink $ 10,000
.
Excavate building pad, haul excess soild, import base, compact
pad to 95%, and fine grade (Including walks)
22,000 s.f. @ $0.50 $ 11,000
.
New 6" steel reinforced concrete slab. Add pos% tension for
crack control at expansive soil
17,000 s.f. @ $2.50 $ 68,000
.
New 4" concrete walks
4,500 s.f. @ $2.50
$ 11,200
o
Polyurethane slab finiSh and game lines
17,000 s.f. @ $1.50
$ 25,500
.
Electrical light fixtures & poles
4 @ $1,500 each
$ 6,000
·
Boards and framing; 4 gates
2,280 s.f. @ $7.00
$ 16,000
·
Chain link fencing and posts
2,960 s.f. @ $3.50
$ 10,300
10. ' Electrical scoreboard (allowance)
$ 2,000
!!. Paintboards/framing both sides
2,280 s.f. @ $.90
$ 2,000
12. Contractor's Overhead & Profit
Subtotal
15% $ 29,500
$226,500
13. Bonds
i.~% $ 3,400
Subtotal $229,900
14. Contingency .
Construction Total
5% $!!, 500
$241,400
Architectural/Engineering Fees
Project Management Fees
· Total Development Cost for one (1) rink
$ 25,000
$ 8,000
$274,400
· Add a second rollerhockey rink
$175,000'
Add a 600 s.f. concession building compatible
to design standards for East Tustin 600 s.f. @ £75
$ 45,000
GRAND TOTAL
$494,400
* excludes re-work of parking; scope unknown at %kis time
EXHIBIT C
Tustin In-Line Skate and Hockey
Cost proposal for two full size rinks (200 x 85 ft)
Construction Costs
Excavation ((34,000 sq ft)
Rebar
Forming
Concrete (420 cu yds @ $47.50/cu yd)
Concrete Finishing (34000 ,sci ft @ $0.34 ,SCl ft)
Polyurethane Finish (34000 sq ft @ $1.50 sq ft)
subtotal
Electrical (Halogen lighting & standards)
Boards (1140 lineal ft @ $26 p/Ift)
Chainlink Fence
Electrical Scoreboards
Paint for boards & weather proofing)
Subtotal
General Contractor (@ 15%)
Contingency
$ 2,000
$ 10,000
$ 4,000
$ 19,950
$ 11,560
$ 51,000
$ 12,000
$ 29,640
$ 20,000
$ 4,000
$ 3,000
$ 25,073
$ 3,343
I $195,5661
$ 98,510 *
$167,150
Tustin In-Line would like an office, equipment and concession building which would accomodatc
sales, rentals, repairs and administration as well as equipment storage for goals and other
equipment ouLside of operating hours. These facili;ics would nccd to be approximately 600 fl2
and could be cilhcr of stick cons;ruction or portable such as a Butler building. Electrical,
plumbing and tc!cphonc services are required. Initial estimates for this facility arc $25,000 at
approximztely $41.70 fl:' ,
If the City of'l'ttstin opts to provide the two concrete slabs plus polyurethane finish
the construction costs would be this amount.
, ..J ....... I.L