PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
AUTHORIZE TO ADVERTISE FOR BIDS - JAMBOREE ROA~. WIDENING
BETWEEN EL CAMINO REAL ANDTHE I-5 FREEWAY NORTHBOUND ON-RAMP
RECOMMENDATION
For consideration by the City Council, at their meeting of April 4,
1994. It is recommended that the City Council adopt the attached
resolution approving the plans and specifications for subject
project and directing the City Clerk to advertise for bids.
FISCAL IMPACT
The Engineer's cost estimate for this project is $171,585.00 and
funds have been allocated for this project in the 1993-94 FY East
Tustin Assessment District 85-1 Capital Improvement Program budget.
BACKGROUND
This project provides for the improvement of Jamboree Road between
E1 camino Real and the I-5 Freeway northbound on-ramp. The scope
of the project includes additional asphalt concrete pavement,
removal and reconstruction of curb and gutter, retaining walls,
landscaping, installation of traffic striping and markings, traffic
loop detectors, traffic signal interconnect and ramp meter
modifications.
Below is the tentative schedule for this project:
Bid Authorization .............................. April 4,
First Legal Advertisement ..................... April 14,
Second Legal Advertisement .................... April 21,
Bid Opening ...................................... May 5,
Award Contract .................................. May 16,
Begin Construction .............................. June 1,
Complete Construction ........................ August 10,
1994
1994
1994
1994
1994
1994
1994
Robert S. Ledendecker
Director of Public Works/
City Engineer
Dave Balbas
Junior civil Engineer
RSI..:DB:l~:j~mwid
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
24
26
27
28
RESOLUTION NO. 94-37
.
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
TUSTIN, CALIFORNIA, APPROVING PLANS AND
SPECIFICATIONS FOR THE JAMBOREE ROAD WIDENING,
BETWEEN EL CAMINO REAL ANDTHE I-5 FREEWAY NORTHBOUND
ON-RAM~, AND AUTHORIZING THE ADVERTISEMENT FOR BIDS
WHEREAS, it is the intention of the City Council of the
City of Tustin, California to contract construction for the
improvements of Jamboree Road between E1 Camino Real and the I-
5 Freeway northbound on-ramp; and
WHEREAS, the City Engineer has presented plans and
specifications for the construction of said work;
NOW, THEREFORE, BE IT RESOLVED that the plans and
specifications presented by the City Engineer be and are hereby
approved as the plans and specifications for:
Jamboree Road Widening Between E1 Camino Real
and the I-5 Freeway Northbound On-ramp
BE IT FURTHER RESOLVED, that the City Clerk is hereby
authorized and directed to advertise as required by law for the
receipt of sealed bids or proposals for the doing of the work
specified in the aforesaid plans and specifications;
BE IT FURTHER RESOLVED, that this project is categorically
exempt from the requirements of the California Environmental
Quality Act; Class I: Existing Facilities.
PASSED AND ADOPTED at a regular meeting of the City
Council of the City of Tustin held on the 4th day of April,
1994.
Jim Potts, Mayor.