AWARD OF CONTRACT FOR THE ASPHALT CONCRETE REHABILITATION AND
OVERLAY PROJECT, FY 1993-94
RECOM2(ENDATION:
It is recommended that the Tustin City Council, at their meeting of
March 21, 1994, award the FY 1993-94 Asphalt Concrete Rehabilitation and
Overlay Project contract to Boral Resources, Inc., in the amount of
$388,822.62.
FISCAL IMPACT:
The street rehabilitation/overlay Project will be funded from the 1993-
94 FY CIP, Major Maintenance Program item with available funds exceeding
the amount of this award.
BACKGROUND:
Eight (8) bids were received on March
follows:
10, 1994 and are summarized as
Boral Resources, Inc., Pomona .......................
R.J. Noble Co., Orange-~ ..............................
Sully-Miller Contracting Co Orange
e,
Ail American Asphalt, Corona ........................
Ben's Asphalt and Seal Coating, Inc.
Garden Grove .........................................
Silvia Construction, Inc., Upland ...................
Excel Paving Co., Long Beach ............. ...........
Griffith Co., Santa Aha .............................
$388,822.62
$390,097.12
$396,379.08
$412,706.67
$419,891.40
$420,217.44
$424,870.45
$456,241.75
The low bid is 20.8% below the engineer's estimate of $491,202.83. The
references and the Contractor's State License of Boral Resources, Inc.
have been checked and are appropriate for the subject project.
.. -
It is staff's intent, to expand the scope of work in this contract to
utilize the 1993-94 budgeted funds in order to satisfy the required
Maintenance of Effort (MOE) requirements for Measure M and CMP Funding
Programs.