HomeMy WebLinkAboutRPT 2 T SPTS PARK UPDT 01-17-94DATE:
January 10, 1994
REPORTS NO. 2
; ; 1-17-94
·
TO:
FROM'
_ SUBJECT:
WILLIAM A. HUSTON, CITY MANAGER
COMMUNITY SERVICES DEPARTMENT
TUSTIN SPORTS PARK DESIGN UPDATE - JANUARY 3, 1994
RECOMMENDATION:
Receive and file.
FISCAL IMPACT:
Not applicable.
BACKGROUND:
The City Council has requested updates on the progress of the
preparation of the working drawings and bid specifications for the
Sports Park. The project is currently out to bid. On December 6,
~993, the City Council conducted a public hearing on an appeal to
· include additional lighting for the project. At that meeting, the
Council approved the addition of lighting for the
soccer/multipurpose fields and the basketball.courts.
TENTATIVE
TASKS COMPLETION DATE STATUS
Establish program,
Concession/Pro Shop,
Draft RFP for
concessionaire
Conduct Public Hearing on
appeal for additional
lighting
Prepare addendum to bid'
documents
Bidding Completed
12/93 In progress
12/6/93 Complete
12/28/93 Complete
1/18/94 Future
TENTATIVE
TASKS ' COMPLETION DATE STATUS
Award Contract
2/7/94 Future
Start Construction
February Future
As of January 10, 1994, thirty contractors have checked out plan
sets for bidding. Bids will be opened at 2 p.m. on Tuesday,
January 18, 1994.
Susan M. Jones
Recreation Superintendent
RW1:117SPUPD. CC