HomeMy WebLinkAbout05 TCA RIGHT-OF-WAY 04-03-95 NO. 5
4-3-95
, -oo m
,.,ATE:
APRIL 3, 1995
TO: WILLIAM A. HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
FROM:
AUTHORIZATION FOR THE TRANSPORTATION CORRIDOR AGENCIES (TCA)
SUSJEC~ TO ACQUIRE RIGHT-OF-WAY FOR THE JAMBOREE ROAD/EDINGER AVENUE
INTERCHANGE IMPROVEMENTS ASSOCIATED WITH THE EASTERN
TRANSPORTATION CORRIDOR (ETC) WEST LEG TRANSITION AREA
RECOMMENDATION
It is recommended that the City Council, at their meeting of April
3, 1995, authorize the TCA to acquire right-of-way for the subject
interchange at Jamboree Road/Edinger Avenue.
FISCAL IMPACT
Acquisition of the needed right-of-way will be initially funded by
the TCA subject to future fair share reimbursement from the cities
of Tustin and Irvine as part of a yet to be finalized comprehensive
funding agreement between the three parties.
BACKGROUND
On September 6, 1994, the City Council approved a Memorandum of
Understanding (MOU) with the TCA and the City of Irvine regarding
Jamboree Road improvements south of the terminus of the west leg of
the ETC. The MOU designated the TCA as lead agency for the
project. Additionally, the MOU stipulated that the interchange
(grade separation) of Jamboree Road/Edinger Avenue shall be
constructed prior to the opening of the west leg of the ETC.
DISCUSSION
As part of the Jamboree Road/Edinger Avenue interchange
improvement, it is necessary to acquire a portion of the property
at the northwest corner of the Jamboree Road/Edinger Avenue
intersection (Jamboree Plaza). This portion of the property was
previously reserved for future acquisition as a condition of the
deVelopment review process, by the Jamboree Plaza developer, for
the future widening/interchange improvements at Jamboree
Road/Edinger Avenue.
The interchange design process is currently underway by Greiner
Engineering under a contract with the County of Orange which is
acting as an administrator on this phase of the project on behalf
of the TCA.
To expedite the interchange project the TCA has agreed to acquire
the needed right-of-way on behalf of the City of Tustin along the
eastern side of the Jamboree Plaza site adjacent to Jamboree Road.
It is therefore recommended that the City Council authorize the TCA
to perform the needed right-of-way acquisition services.
Tim D. Serl~t
Director of Public Works/
City Engineer
Dana R. Kasdan ~
Engineering Services Manager
TDS: DRK: NM;klb: e,u:rl'wy
A-nchm~nts
49
4~4-2 0
I"=200'
~,, M. 1-88
~. ~. 276-54
NO TE - ASSESSOR'S BLOCK &
PA RCEL NUMBERS
SHOWN IN CIRCLES
ASSESSOR'S uAP
BOOK 454 ~ .~¢E
COUN I' Y OF ,' :..4