HomeMy WebLinkAbout06 I-5/SR-55 FWY CONST 04-03-95A G E N DA Inter-Com NO. 6 4-3-95 JATE: APRIL 3, 1995 TO: FROM: SUBJECT: WILLIAM A. HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION I-5/SR-55 FREEWAY CONSTRUCTION STATUS REPORT RECOMMENDATION It is recommended that the City Council at their meeting of April 3, 1995 receive and file this report. FISCAL IMPACT None. BACKGROUND AND DISCUSSION The following information relates to the status of the Caltrans I- 5/SR-55 Freeway interchange construction. Overall completion of the I-5/SR-55 interchange is delayed due to the recent rains and tentatively scheduled for late summer, 1995. The northbound SR-55' to northbound I-5 connector was originally opened at ground level. A newly constructed elevated connector (flyover) was completed and opened to traffic on February 2, 1995 to replace the old ground level connector. The southbound SR-55 to southbound I-5 connector is currently open at ground level. This connector will also be an elevated (flyover) upon completion of the project and is tentatively scheduled to open on April 29, 1995. The following connectors are currently open at ground level and will stay open with minor overnight and/or weekend closures on an as-need basis: Southbound I-5 to southbound SR-55 Northbound I-5 to northbound SR-55 These connectors are tentatively scheduled for final completion in June 1995. The northbound SR-55 to southbound I-5 connector is currently open at ground level and will stay open with minor overnight and/or weekend closures on an as-need basis. Final completion is tentatively scheduled for April 29', 1995. The northbound I-5 to southbound SR-55 connector is the only one currently closed and will stay closed until final completion of the project in late summer, 1995. The SR-55 northbound off-ramp to Irvine Boulevard/4th Street is tentatively scheduled to be closed for a period of one month in May 1995. Main Street between Williams and Stoneglass is currently partially open and is scheduled for final completion in May/June 1995. Nisson Road between Pasadena and "B" Street was partially opened to through traffic on August 20, 1992. This partial opening consists of a 24 foot wide street with curb and gutter on the south side, and concrete barrier, curb and gutter and/or white edge stripe on the north side. The ultimate street construction is tentatively scheduled for completion in April/May 1995. The I-5 southbound off-ramp to Newport Avenue is currently open and is scheduled to close on March 27, 1995 for a period of 34 days. The Newport Avenue widening under I-5 is tentatively scheduled for completion in April/May 1995. The above information and schedule was furnished through discussions with the Caltrans Resident Engineer and is subject to change based upon weather conditions and contractor's scheduling. Tim D. S~r/et Director of Public Works/ City Engineer Wisam Altowaij i Associate Civil Engineer TI)S:WA:klb: fwycomp Attachn~nt: I-5/SR-55 Interchange Plan WILUAMS STREET 'rUSTIN VILLACE W~ O <j~ ',,-r ,o LCONSUEL~ I! I1--., I CORTEZ ! II II t! .ml PASADENA AV. PACIFIC ST. CAUFORNIA ST. EBEL DR. // C' EL PACIFIC ST. ST. 'C" S? CAMINO $OUTEir.~.~T FIRST ST. ~TJ3~$~V CE4NNZ~- GOLDEN CIRCLE -I !11 m -4 PASADENA AV. M'm'ru~ ~ t ...... '^v. Z PACIFIC ST. YORBA STREET MOUNTAIN VIEW DR.1 N. "A' ST. N. 'B' ST. JZ .;u, & & & ;' ;' ;'