HomeMy WebLinkAbout16 PROJECT 600101 02-21-95NO. 16 2-21-95 .)ATE: FEBRUARY 21, 1995 TO: FROM: SUBJECT: WILLIAM A. HUSTON, CITY MANAGER PUBLIC WORKS DEPARTMENT/WATER DIVISION FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS - WATER MAIN REPLACEMENT FOR NEWPORT AVENUE AND WARREN AVENUE (PROJECT NO. 600101) RECOMMENDATION: It is recommended that the Tustin City Council at their meeting of February 21, 1995, adopt the attached Resolution No. 95-24 accepting said work and authorizing the recordation of the Notice of Completion. Assuming no claims or stop payment notices are filed, it is further recommended that the City Council authorize payment of the 10% retention amount of the $114,334.97, thirty-five days after the date of recordation of the Notice of Completion. This amount, together with previous payments of $1,029,014.69 represents 100% of the final contract. FISCAL IMPACT: · Amount of this contract - $1,143,349.65 · Amount budgeted - $1,892,100.00 · Total estimated project cost - $1,253,000.00 BACKGROUND: This project consisted of replacing a deteriorating 16-inch rivetted steel main (installed in 1907) in Newport Avenue from north of Foothill Boulevard to south of Warren Avenue, and the installation of a new main in Warren Avenue from Holt Avenue to Newport Avenue. These new mains were tied into the existing water mains and reservoirs to increase system pressure and reliability, and have also interconnected the City's pressure zones. This project has been completed to the satisfaction of the Water Division. .. Tim D. Serlet Director of Public Works/City Engineer TS :MKM:cmc Attachment Michael Martin Water Service Engineer 1 2 3 4 5 6 ? 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 RESOLUTION NO. 95-24 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN, CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND AUTHORIZING RECORDATION OF NOTICE OF COMPLETION FOR THE WATER MAIN REPLACEMENT FOR NEWPORT AVENUE AND WARREN AVENUE, PROJECT NO. 600101 WHEREAS, Riverside Pipeline, Inc. dba Horizontal Boring having a contract with the City of Tustin to construct the' hereinafter described public work and improvement; and WHEREAS, the City Engineer has duly certified to the construction and completion of said public improvements hereinafter mentioned in a manner satisfactory to the City Council of the City of Tustin; and WHEREAS, the City Council finds that said contractor has completed said public improvement hereinafter more particularly described in accordance with the provisions of the contract documents and the notice of completion, and acceptance of said public work and improvement should be filed and payment of the balance due said contract authorized in accordance with the contract document. NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tust that said public work and improvement be and the same is hereby accepted. Said public work and improvement is more particularly described as follows: The Water Main Replacement for Newport Avenue and Warren Avenue, Project No. 600101. BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin be and is hereby authorized to execute and file a notice of completion and acceptance of said public work and improvement described herein as required by law. PASSED AND ADOPTED at a regular meeting of the City Council of the City of Tustin, held on the 21st of February, 1995. Thomas R. Saltarelli, Mayor Mary E. Wynn, City Clerk