FEBRUARY 6, 1995
RDA NO. 3
2-6-95
Inter-Com
TO' WILLIAM A. HUSTON, EXECUTIVE DIRECTOR
FROM: COMMUNITY DEVELOPMENT DEPARTMENT
SUBJEC~ AUTHORIZATION TO ISSUE REQUEST FOR QUALIFICATIONS/PROPOSALS
RECOMMENDATION
It is recommended that the Agency authorize the issuance of a
Request for Qualifications/Proposals for the solicitation of a
developer for the Old Town Gateway Project.
FISCAL IMPACT
While the issuance of the Request for Qualifications/Proposals will
not have any fiscal impact on the AgencY, the Agency may ultimately
incur costs for the redevelopment of the property. Any such costs
will be incurred after selection of a developer and the negotiation
of a Disposition and Development Agreement, subject to the
direction and approval of the AgenCy.
BACKGROUND
In June, 1991, the Redevelopment Agency sponsored an Old Town
Charette, bringing together over 70 Old Town business and property
owners, community leaders, citizens and City officials and staff to
identify constraints and opportunities within Old Town. During the
course of the Charette, the participants walked, reviewed and
studied Old Town with an eye to what improvements needed to be made
to provide for revitalization and reinvestment.
As a result of the Charette process, the Agency commissioned a
Regional/Urban Design Assistance Team (R/UDAT) of the American
Institute of Architects to undertake a focused study of Old Town
and to recommend broad development parameters for specific
properties, as well as overall Old Town.
The R/UDAT study identified E1 Camino Plaza, and the property
between the Plaza and Newport Avenue, as one of the most important
opportunities the City has to strengthen and reinvigorate Old Town.
As the R/UDAT study states, this property "...is the most critical
edge from a design standpoint, because development south of Sixth
Street faces onto the Old Town center at Main and E1 Camino. Newer
development to the south of Sixth Street should play a significant
role in becoming more fully integrated into the overall Old Town
William A. Huston
Issuance of RFQ/RFP
February 6, 1995
Page 2
fabric."
In discussing specific development of the property, the R/UDAT
states:
"This important Site anchors the south end of the core as the
Retail/Transition zOne. E1 Camino Real should be abandoned
and the properties south as it would be consolidated into a
single entity. This new node could become an extension of E1
Camino Plaza, giving the center a Newport Avenue presence.
New structures within this redeveloped area would supplement
the center with night-time entertainment and eating
establishments, anchored by Elizabeth Howard's Curtain Call
Dinner Theater. The theater's presence should be made more
evident by making it visible from the E1 Camino Real street
frontage. A new campanile/theater marquee will terminate the
south vista of E1 Camino Real and give the center scale and
prominence from the freeway. A cluster of new buildings
containing coffee houses and other evening uses would tie the
Theater to the street through a landscaped forecourt.
The updating of the center would be anchored by the
construction of the Old Town Trellis inserted at the center's
inner courtyard. This dramatic structure would give the
theater a great sense of scale, relate it better to Old Town,
and provide another skyline event that would create a dramatic
nighttime signature when illuminated.
Suggested new businesses to enhance the tenant mix are:
Specialty food markets
Theme restaurants
Ethnic restaurants
Comedy club or other night clubs
"Revival movie house"
Since 1991, the retail market in Orange County has been saturated
with unleased space. Little or no new development has been
undertaken and private financing for new centers has, for the most
part, been non-existent. However, the vacancy rate in retail space
in Orange County has been falling over the past 12 months and
developers are again looking for prime opportunities for investment
and development during the next two to three years. Therefore,
staff believes this is an opportune time to solicit developers for
this property.
In 1992, the Agency sent formal notification to the property and
business owners on site of the Agency's intent to redevelop the
William A. Huston
Issuance of RFQ/RFP
February 6, 1995
Page 3
property. Each was asked to return a Statement of Interest in
Participating, if they wished to be considered for the development
of the property. The Agency received Statements of Interest from
three property owners, one of whom owns property which is not
included in the proposed development site, and one tenant,
specifically Elizabeth Howard's Curtain Call Dinner Theater. The
property owner of E1 Camino Plaza, the largest property on the
site, did not respond at that time.
However, the staff has also been in contact with the owner of E1
Camino Plaza, which represents approximately. 75% of the total site.
He has indicated a growing concern for the condition and future of
the center and has given his support to the Agency's efforts to
bring about redevelopment of his property.
DISCUSSION
The staff is recommending a traditional approach to the
redevelopment of this property. This approach calls for the
solicitation and selection of a developer, negotiations of a
Disposition and Development Agreement (DDA) and Agency assistance
in land assembly and, possibly, ~ financial assistance, if deemed
necessary, to reach the community's goals for the property.
The developer solicitation process is a lengthy one, anticipated to
take close to a year before a DDA is brought to the Agency for
approval. It is divided into several phases.
The first phase is a Request for Qualifications (RFQ). The
preparation of formal proposals for redevelopment of property is a
costly one for the private sector. Few, if any development
companies will undertake preparation of such proposals unless they
have a reasonable chance to be selected. The purpose of the RFQ
phase is to reduce the number of potential developers to a few,
between three and five, to make it worthwhile for the selected
developers to undertake the effort and expense to prepare full
proposals.
If the Agency authorizes the issuance of the Request for
Qualifications/Proposals, staff expects to release it by February
13, 1995. Statements of Qualifications will be due by March 23,
1995. These statements will include background information on the
potential developers, including their experience with similar
projects, their financial capability, and their relationships with
ultimate users, lenders and other government agencies in similar
projects. It will also include conceptual discussions of the
developer's vision for the property.
William A. Huston
Issuance of RFQ/RFP
February 6, 1995
Page 4
Based on a review of these statements, the staff will recommend a
small group of developers to enter the second phase of the process
by inviting them to submit formal proposals. The staff currently.
anticipates these invitations being issued on May 4, 1995.
The developers will be given three months to prepare full
proposals. The proposals will be required to include full site
plans, elevations and floor plans, identification of major users,
development and operating pro formes as well as a discussion of the
anticipated assistance from the Agency, if any.
These proposals will be fully reviewed by staff and consultants
and,.subsequently, the staff will recommend that the Agency enter
into an Exclusive Right to Negotiate Agreement with the selected
developer. This agreement would bind the Agency and the developer
to negotiate in good faith, only with each other, to develop a DDA
acceptable to both parties. Negotiations are expected to take
approximately 90 to 120 days. Upon successful completion of these
negotiations, a DDA would be presented to the Agency for approval,
which is expected early in 1996.
A schedule for developer selection as outlined in the attached
RFQ/RFP is included as Attachment I.
After entering into a DDA, the developer would then be required to
obtain entitlements for the development, financing for the project,
signed" leases with major tenants and to begin the actual
redevelopment of the site. The Agency will also be required to
fulfill its obligations, which may include land assembly, swift
processing of development plans and building permits, or assistance
in financing.
CONCLUSION
Attached for Agency consideration and approval is the draft Request
for Qualifications/Proposals. Staff recommends the Agency
authorize its issuance to the property and business owners of the
'/Chr~i~-~/~~site' as well as the developmelnt~mmunity.:/~~~/~i
' -' i'e ~ Sh~ngleton ~h~d~im~er '
Assistant City Manager /RedevelOpment Program Manager
ATTACHMENT 1
SCHEDU___LE OF DEVELOPER SELECTION PROCESS
PHASE 1
QUALIFICATIONS PHASE
February 13, 1995
2:00 PM
February 28, 1995
Issuance of Solicitation
Presubmittal meeting on RFQ
5:00 PM
March 23, 1995
Submittal of Statements of
Qualifications
March 23 - May 1, 1995
Agency review of Statements of
Qualifications
May 1, 1995
Selection of Proposers
PHASE 2
PROPOSAL PHASE
May 4, 1995
Invitations for Proposals
Issued
May 16, 1995
Presubmittal Meeting on
Proposals
August 18, 1995 Submittal of Proposals
August 18, 1995 Completion of Draft Exclusive
Right to Negotiate
August 18 - September 18, 1995 Staff Review of Proposals
September 18, 1995
September 18, - December 18,
1995
January 2, 1996
Agency Selection of Developer
and Approval of Exclusive
Right to Negotiate
Negotiation of Disposition and
Development Agreement
Agency Approval of Disposition
and Development Agreement