HomeMy WebLinkAbout06 PROJECT 600116 01-03-95AGENDA -
DATE:
JANUARY 3, 1995
i
Inter-Com
NO. 6
1-3-95
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/WATER DIVISION
FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS - WATER MAIN
REPLACEMENT FOR 17TH STREET AND BRENAN WAY (PROJECT NO. 600116)
RECOMMENDATION:
It is recommended that the Tustin City Council at their meeting of January 3, 1995, adopt the attached
Resolution No. 95-4 accepting said work and authorizing the recordation of the Notice of Completion.
Assuming no claims or stop payment notices are filed, it is further recommended that the City Council
authorize payment of the 10% retention amount of the $12,571.50, thirty-five days after the date of
recordation of the Notice of Completion. This amount, together with previous payments of $113,143.53
represents 100 % of the final contract.
FISCAL IMPACT:
· Amount of this contract - $125,715.03
· Current amount budgeted - $205,300.00
· Total estimated project cost - $160,000.00
BACKGROUND:
This project consisted of the replacement of a deteriorated and undersized water main on Brenan Way
from 17th Street to Vanderlip Avenue and the installation of a new water main on 17th Street from
Esplanade Avenue to east of the new City desalter plant.
Both mains will help to improve water supply and system reliability in the area.
This portion of the above project has been completed to the satisfaction of the Water Division.
Tim Serlet
Director of Public Works/City Engineer
TS:MKM:cmc
Attachment
Michael Martin
Water Service Engineer
1
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
29.
23
24
25
26
27
28
RESOLUTION NO. 95-4
A RF_SOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION FOR
THE WATER MAIN REPLACEMENT FOR 17TH STREET AND BRENAN
WAY, PROJECT NO. 600116.
WHEREAS, S.J. Burkhardt, Inc. having a contract with the City of Tustin to
construct the hereinafter described public Wor~ and improvement; and
WHEREAS, the City Engineer has duly certified to the construction and completion
of said public improvements hereinafter mentioned in a manner satisfactory to the City
Council of the City of Tustin; and
WHEREAS, the City Council finds that .said contractor has completed said public
improvement hereinafter more particularly described in accordance with the provisions of the
contract documents and the notice of completion, and acceptance of said public work and
improvement should be filed and payment of the balance due said contract authorized in
accordance with the contract document.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tustin
that said public work and improvement be and the same is hereby accepted. Said public work
and improvement is more particularly described as follows:
The Water Main RePlacement for 17th Street and Brenan Way, Project
No. 600116.
BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin be and
is hereby authorized to execute and file a notice of completion and acceptance of said public
work and improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Tustin, held on the 3rd day of January, 1995.
Thomas R. Saltarelli, Mayor
Mary E. Wynn, City Clerk