HomeMy WebLinkAbout07 PROJECT 600121 01-03-95AGEN DA
DATE: JANUARY .3, 1995
NO. 7
, i 1-3-95
inter-Corn
TO:
FROM:
SUBJECT:
WILLIAM HUSTON, CITY MANAGER
PUBLIC WORKS DEPARTMENT/WATER DIVISION
FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS - WATER
REPLACEMENT PROJECTS (PROJECT NO. 600121)
RECOMMENDATION:
It is recommended that the Tustin City Council at their meeting of January 3, 1995, adopt the attached
Resolution No. 95-5 accepting said work and authorizing the recordation of the Notice of Completion.
Assuming no claims or stop payment notices are filed, it is further recommended that the City Council
authorize payment of the 10% retention amount of the $37,285.85, thirty-five days after the date of
recordation of the Notice of Completion. This amount, together with previous payments of $335,572.63
represents 100% of the final contract.
FISCAL IMPACT:
· Amount of this contract - $372,858.48
· Current amount budgeted - $452,800.00
· Total estimated project cost - $420,000.00
BACKGROUND:
This project encompasses the ultimate replacement of deteriorated and undersized water mains on
Pasadena Avenue, 2nd Street, "A" Street, Country Lane, Sierra Alta Drive, Windsor Lane and
Ranchview Drive.
These new mains will help to provide a more substantial water supply and circulation in the area.
This portion of the above project has been completed to the satisfaction of the Water Division.
Tim Seflet
Director of Public Works/City Engineer
TS:MKM:cmc
Attachment
Michael Martin
Water Service Engineer
1
2
5
$
?
8
9
10
11
12
13
15
16
18
19
21
22
23
2~
25
27
RESOLUTION NO. 95-5
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF TUSTIN,
CALIFORNIA, ACCEPTING WORKS OF IMPROVEMENT AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION FOR
THE WATER MAIN REPLACEMENT PROJECTS, PROJECT NO. 600121
FOR PASADENA AVENUE, 2ND STREET, "A" STREET, COUNTRY
LANE, SIERRA ALTA DRIVE, WINDSOR LANE AND RANCHVIEW
DRIVE.
WHEREAS, RLT Construction, Inc. having a contract with the City of Tustin to
construct the hereinafter described public work and improvement; and
WHEREAS, the City Engineer has duly certified to the construction and completion
of said public improvements hereinafter mentioned in a manner satisfactory to the City
Council of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has completed said public
improvement hereinafter more particularly described in accordance with the provisions of the
contract documents and the notice of completion, and acceptance of said public work and
improvement should be filed and payment of the balance due said contract authorized in
accordance with the contract document.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Tustin
that said public work and improvement be and the same is hereby accepted. Said public work
and improvement is more particularly described as follows:
The Water Main Replacement Projects, Project No. 600121 for
Pasadena Avenue, 2nd Street, "A" Street, Country Lane, Sierra Alta
Drive, Windsor Lane, and Ranchview Drive.
BE IT FURTHER RESOLVED that the City Engineer of the City of Tustin be and
is hereby authorized to execute and file a notice of completion and acceptance of said public
work and improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council of the City of
Tustin, held on the 3rd day of January, 1995.
Thomas R. Saltarelli, Mayor
Mary E. Wynn, City Clerk