AWARD OF CONTRACT - CENTENNIAL PARR PLAY STRUCTURES
RECOMMENDATION:
Award the contract for Centennial Park Play Structures in the
amount of •$11,950 to Miracle Recreation Equipment Company.
BACKGROUND:
On July 1, 1991 the City Council authorized advertisements for bids
for Centennial Park Play Equipment. Bid packets were sent to a
total of seven firms. This equipment will complete the replacement
of all Centennial Park Play Structures as recommended for
replacement by the playground equipment safety audit.
DISCUSSION:
The bids were opened August 6, 1991. The results were as follows:
Miracle Recreation Equipment Company $11,950.00
The bid includes delivery and installation. An amount of $12,000
was appropriated in the 1990/91 Capital Improvement Budget for the
project so it can be completed within budget.
Miracle Recreation Equipment Company is a reputable firm having
built playgrounds throughout Southern California as well as in
Tustin. After awarding the contract, .it generally takes six to
eight weeks to order and install the play structures. The project
is expected to be complete by mid October.
Susan ionesV
Recreation Supervisor
GM:
7P
A:CENTPARK.Bm
L�-
Royleen A. White
Community and Administrative
Services