HomeMy WebLinkAboutCC 6 WTR MAIN REPLACE 09-16-91CONSENT CALENDAR NO. 6
c
9-16-91
AG E N DA_
ATE: SEPTEMBER 91 1991
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR WATER MAIN REPLACEMENT ON WOODLAND
DRIVE, ZIG ZAG WAY AND "B" STREET. PROJECT NOS. 600089,
_------------
RECOMMENDATION
It is recommended that the Tustin City Council at their meeting of
September 16, 1991 award the contract for the subject project to R.L.T.
Construction, Inc., of Anaheim, California, in the amount of $125,671.00.
BACKGROUND
Bids were opened September 5, 1991 for subject project and twelve (12 ) bids
were received as follows:
1. R.L.T. Construction Inc.
2. R & L Sewers, Inc.
3. Marina Contractors, Inc.
4. Amick Construction Co., Inc.
5. Jana Contracting Corp.
6. Steve Casada Construction Co.
7. Artukovich Construction, Inc.
8. Gary J. Herman, Inc.
9. Ruiz Engineering Co.
10. Macco Constructors, Inc.
11. Steven F. Shacklett
12. Southern California Pipeline
Construction, Inc.
$125,671.00
$139,014.25
$142,723.35
$144,820.00
$156,192.00
$158,212.50
$184,176.52
$194,875.50
$197,518.80
$209,427.50
$229,401.00
$229r699.37-
The
229,699.32
The low bid by R.L.T. Construction, Inc. is 28% under the engineer's
estimate of $175,514.00.
These projects will provide for the replacement of deteriorated water
mains sawcut and removal and replace asphalt concrete at various locations
mentioned above in the City of Tustin and in the unincorporated territory
of Orange County.
Funding for these projects will be provided by the 1991-92 FY Capital
Improvement Budget. Currently there is a total of $257,100.00 budgeted for
these projects.
Bob Ledendecker Dave Balbas
Director of Public Works/City Engineer Project Engineer
DB:kIb:WATERMAIN