HomeMy WebLinkAboutCC 6 PROJECT 600095 11-18-91CONSENT CALENDAR NO. 6
11-18-91
A G E N D 11--1-
ATE: NOVEMBER 12, 1991
TO: WILLIAM A. HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT FOR WATER MAIN RELOCATION IN EL CAMINO WAY
(PROJECT NO. 600095, P.W. FILE W91 -3A)
RECOMMENDATION
It is recommended that the Tustin City Council, at their meeting of
November 18, 1991, award the contract to John T. Malloy and John T.
Malloy, Inc., a joint venture, in the amount of $82,918.40 for the
subject project.
BACKGROUND
Six bids were received on November 12, 1991 and are summarized as
follows:
John T. Malloy and John T. Malloy, Inc.
a Joint Venture, Los Angeles .......................$ 82,918.40
Atlas Allied, Inc., Anaheim........................$87,873.20
Steve Casada Construction Co., Anaheim .............$ 89,042.00
Robert Brkich Construction, Arcadia ................$ 99,780.00
R.L.T. Construction, Inc. ,Anaheim .................$108,475.00
Robert G. Castognia, Inc., Downey .................. $134,116.20
The low bid is 4.5% below the engineer's estimate of $86,834.00.
The current budget provides $500,400.00 for water main relocations
prompted by Caltrans freeway widening Stage III. Therefore,
$417,481.60 will remain for the water main relocations on Main
Street at I-5 freeway, Main Street at SR -55 freeway, and on Nisson
Road between Pasadena Avenue and "B" Street.
Ila a, 001 / 4 rx:-f
Robert S. Ledend cker Nestor Mondok
Director of Publ c Works/ Assistant Civil Engineer
City Engineer
BL:NM:ccg:WMRAWARD