HomeMy WebLinkAboutNB 2 ST LIGHT CONDUIT 02-21-89,;~ ?':~ ~ '- /~\ NEW BUSINESS
DATE: ~B~g~ ~ ~ ~989
TO:
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUSJ£OT: AWARD OF CONTRACT FOR THE INSTALLATION OF STREET LIGHT CONDUIT
AT GLENARBOR AVENUE AND HOLLYHOCK AVENUE (FILE #2151)
RECOMMENDATION:
That the City Council at their meeting of February 21, 1989, award a
contract for the subject project to Building Energy Consultants of
Huntington Beach in the amount of $7,932.60, and to authorize a
supplemental 1988-89 budget appropriation in the amount of $1,900. for
the complete installation of the street lights.
BACKGROUND:
This project provides for the installation of street light conduit at
Glenarbor Avenue and Hollyhock Avenue. The conduit will be utilized to
install one street light on the east side of each street. Bids for this
work were opened on February 14, 1989 and summarized as follows:
Building Energy Consultants, · Huntington Beach . . $ 7,932.60
Steiny and Company, Inc., Fullerton ....... $ 7,995..00
William R. Hahn, Norco · , ......... $10,647.00
Raymor Electric Co., San Gabriel ........ $11,505.00
The low bid is 10% below the Engineer's estimate of $8,775.
A total of $7,200 is budgeted for this project. A supplemental budget
of $1,900' is required for the complete installation of the street
lights including Southern California Edison fees.
Bob Ledendecker
Director Public Works/City Engineer
BL: PH: b f
Junior Civil Engineer