HomeMy WebLinkAboutNB 3 WTR MAIN IMPROV 05-01-89TO:
WILLIAM HUSTON, CITY MANAGER
FROM: PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT:
AWARD OF CONTRACT FOR WATER MAIN IMPROVEMENTS ON REBECCA LANE,
RECOMMENDATION:
It. is recommended that the City Council award the contract for subject
project to RLT Construction in the amount of $98,775.00.
BACKGROUND :,
On March 20, 1989, the City Council approved plans and specifications
and authorized the advertisement for bids for the subject project.
DISCUSSION:
Sealed bids f.or this work were opened on April 25,
and were received as follows:
1989 at 10:00 A.M.'
RLT Construction, Anaheim ........
Valverde Construction, San~i;Fe ~i~ ....
Spear Pipeline, Orange .........................
Williams Supply Co., Ventura ...................
Bobco Construction, Anaheim ....................
CK Construction, .Signal Hill ...................
$ 98,775.00
$100,600.00
$102,045.00
$104,859.00
$109,938.00
$110,320.10
The low bid is 12.9% below the engineer's estimate of $113,449.00.
There is presently $148,700.00 allocated in the FY 1988-89 budget for
this project.
Bob Ledendecker
Director of Public Works/City Engineer