FINAL ACCEPTANCE OF PUBLIC IMPROVEMENTS
CONSTRUCTION OF STORM DRAIN IMPROVEMENTS ON 6TH AND PACIFIC STREETS
RECOMMENDATION:
It is recommended that the City Council, at their meeting of January 2, 1990,
adopt the attached Resolution accepting said work and authorizing the
recordation of the Notice of Completion.
Assuming no claims or stop payment notices are filed, it is further recommended
that 30 days after the date of recordation of the Notice of Completion, that
the Council authorize payment of the final 10% retention amount $31,889.09.
This amount together with previous payments of $287,001.85 represents 100% of
the final contract amount.
BACKGROUND:
This project encompassed the installation of storm drain pipe, junction
structures, and catch basins on 6th Street from "B" Street westerly to the
cul-de-sac, and on Pacific Street from 6th Street to Main Street. This work
has been completed to the satisfaction of the Engineering Division. The final
contract amount is $318,890.94. This represents an overrun of 7.8% from the
original contract amount of $295,698.00. This overrun was documented by
contract change order No. 1, due to delay and extra work encountered during the
relocation of underground utilities.
Ae
Bob Ledend ker Wisam Altowaiji
Director Public Works/City Engineer Associate Civil Engineer
BL: WA: j
Attachment
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20'
21
22
23
24
25
26
27
28
RESOLUTION NO. 90-2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY
OF TUSTIN ACCEPTING WORKS OF IMPROVEMENT AND
AUTHORIZING RECORDATION OF NOTICE OF COMPLETION
(CONSTRUCTION OF STORM DRAIN IMPROVEMENTS ON 6TH
AND PACIFIC STREETS, PROJECT NO. 900028)
WHEREAS, Janna Contracting Corporation, having a contract
with the City of Tustin to construct the hereinafter described
public work and improvement; and
WHEREAS, the City Engineer has duly certified to the
construction and completion of said public improvements
hereinafter mentioned in manner satisfactory to the City Council
of the City of Tustin; and
WHEREAS, the City Council finds that said contractor has
completed said public improvement hereinafter more particularly
described in accordance with the provisions of the contract
documents and the notice of completion and acceptance of said
public work and improvement should be filled and payment of the
balance due said contract authorized in accordance with the
contract documents.
NOW, THEREFORE, BE IT RESOLVED by the City Council of the
City of Tustin that said public work and improvement be, and the
same is hereby accepted. Said public work and improvement is
more particularly described as follows:
CONSTRUCTION OF STORM DRAIN IMPROVEMENTS ON 6TH AND
PACIFIC STREETS 1988-89 FY, PROJECT NO. 900028
AND BE IT FURTHER RESOLVED that the City Engineer of the
City of Tustin be, and is hereby authorized to execute and file a
notice of completion and acceptance of said public work and
improvement described herein as required by law.
PASSED AND ADOPTED at a regular meeting of the City Council
of the City of Tustin on , 1990.
ATTEST:
CITY CLERK