FEBRUARY 28, 1990
WILLIAM HUSTON, CITY MANAGER
CONSENT CALENDAR NO. 9
3-5-90
Inter - Com
PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION
SUBJECT: AWARD OF CONTRACT - JAMBOREE ROAD EXTENSION PROJECT (BARRANCA
PARKWAY TO-EDINGER AVENUE) THRU MCAS
RECOMMENDATION:
For consideration by the City Council at their meeting of March 5, 1990.
It is recommended that the City Council award the contract for
construction of Jamboree Road (Barranca Parkway to Edinger) thru MCAS to
E. L. Yeager Construction Company, Inc. in the amount of $10,636,440.00,
and authorize the Mayor and City Clerk to execute the contract documents
on behalf of the City.
BACKGROUND:
Bids were opened on February 20, 1990 for the subject project and five
(5) proposals were received as follows:
E. L. Yeager
Brutoco
Griffith Company
Daley Corporation
Sully -Miller
$101636,440.00
$10,810,073.40
$11,2961932.85
$11,4641525.70
$11,488,390.13
The low bid by E. L. Yeager is 29.6% below the engineer's estimate of
$15,099,351.70. The project is a cooperative effort between the Cities
of Irvine and Tustin, and The Irvine Company. Project construction
costs will be borne by the three parties at previously -agreed cost
sharing percentages (City of Irvine - 46%; The Irvine Company - 36%;
City of Tustin - 18%). The City of Tustin has budgeted $2,790,000.00 in
the current 1989-90 Capital Improvement Program to cover its share of
the project construction costs.
It should be indicated that approvals from all of the affected
governmental agencies have now been received.
Bob Ledendecker
Director of Public Works/City Engineer
BL: DRK:mv
Dana . Ka
Engineering ery ces Manager