Loading...
HomeMy WebLinkAboutCC 19 WTR MAIN RELOC 03-19-90DATE: TO: FROM: MARCH 13, 1990 WILLIAM HUSTON, CITY MANAGER CONSENT CALENDAR NO. 19 3-19-90 Inter - Com PUBLIC WORKS DEPARTMENT/ENGINEERING DIVISION SUBJECT: AWARD OF CONTRACT FOR WATER MAIN RELOCATION ON FIRST STREET AND SR 55 FREEWAY (File #2892) RECOMMENDATION: It is recommended that the City Council at their meeting of March 19, 1990 award the contract for subject project to Golem Construction Company of Compton, CA, in the amount of $99,840.50. BACKGROUND: On December 4, 1989, the City Council approved plans and specifications and authorized the advertisement for bid for the subject project. This project encompasses the relocation of the existing water mains on First Street, Tustin Avenue, and Pasadena Avenue to accommodate Caltrans I-5/SR 55 Interchange, Stage 2, Project. The City of Tustin has prior rights easements for the mains to be relocated. Caltrans will reimburse all project costs to the City. DISCUSSION: Sealed bids for this work were opened on March 13, 1990 at 10:00 A.M. and were received as follows: Golem Construction Co. .............. $ 99,840.50 RLT Construction, Inc. .............. $123,643.00 Mac Group, Inc. ..................... $131,850.00 Valverde Construction, Inc. ......... $133,543.40 Changing Times Enterprises,Inc. ..... $147,785.15 Herman Weissker, Inc. ............... $153,295.00 Atlas -Allied, Inc. .................. $179,919.00 The low bid is $32,515.00 or about 24.6% below the engineer's estimate of $132,355.00. Per Utility Agreement No. 12004, the State of California will reimburse the City for all construction costs as well as any engineering costs incurred in all preparation of plans and estimates for this project. 51 Bob Ledendecker Pke- Nestor Mondok Director of Public Works/City Engineer Junior Civil Engineer BL: NM: mv