August 29, 1990
William A. Huston, City Manager
Public Works Department/ Engineering Division
CONSENT CALENDAR NO. 5
9-4-90
Inter - Com
SUBJECT: Award of Contract for Construction of Edinger Avenue Storm Drain
Improvements between Red Hill Avenue and Del Amo Avenue
Proiect No. 900026, (File No. 1358)
Recommendation:
That the Tustin City Council at their meeting of September 4, 1990 award the contract
for the subject project to the low bidder, Silverie & LeBouef JV of Anaheim, in the
amount of $399,669.00.
BACKGROUND:
On July 10, 1990, the Tustin City Council approved the plans and specifications for
the subject project and authorized the advertisement of bids for said work. Funding
for this project will be provided through the City's Redevelopment Agency.
DISCUSSION:
Fifteen sealed bids were received and opened at 10:30 A.M. on August 21, 1990 and
are summarized as follows:
1. Silverie & LeBouef JV, Anaheim
2. Peter C. David Co., Laguna Hills
3. Mike Prlich & Sons, South E1 Monte
4. Mike Masanovich Const. Co., Arcadia
5. The Beecher Const. Co., West Covina
6. Guild Construction, Anaheim
7. Prkaein Company, Laguna Niguel
8. Valverde Construction, Whittier
9. Vicco Construction, La Verne
10. John T. Malloy, Los Angeles
11. Drainage Construction Co., Vista
12. Miramontes Construction Co., Baldwin Park
13. Bebek Company, Irvine
14. Jana Contracting Corp., Anaheim
15. Clarke Contracting Corp., Compton
$399,669.00
413,106.00
433,764.00
435,010.00
439,679.00
439,910.00
439,993.00
441,323.00
441,640.00
443,980.00
463,750.00
479.125.00
480,561.00
494,123.00
510,247.40
The low bid is 16% under the engineer's estimate of $476,115.00.
It is anticipated that construction will start in early October this year and be
completed in late January next year.
Bob Lc detidecker
Director L'uhl.ic Warks/City t-.nhtneer